Procurement Plan PPCR-Building Resilience to Climate Related Hazzard Project – P127508 I. General II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) (>=US$ 1 million) >= US$ 4 million All for Moderate risk 2. NCB (Goods) (= US$ 4 million All for Moderate risk 3. ICB (Works) (>=US$ 5 million) >= US$ 15 million All for Moderate risk 4. NCB (Works) (=US$ 15 million All for Moderate risk 5. (Non-Consultant Services) >= US$ 4 million All for Moderate risk 6. Shopping (Goods) (<=US$ 0.025 NA million) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) >= US$ 2 million All for Moderate risk 2. Individual >= US$ 0.4 million All for Moderate risk 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 4. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement)- excluding procurement packages under implementation [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domestic Review Comments No. Cost Preference by Bank US$ (yes/no) (Prior / Post) Summary of the ICB - - - - (Works) Summary of the NCB - - - - (Works) Summary of the ICB - - - - (Goods) Summary of the NCB 868,000 3 - Post (Goods) Summary of the RFQ 28,950 2 - Post (Goods) Summary of the DS - - - - (Goods) Summary of the NCB - - - - (Non-Consultant Services) Summary of RFQ (Non- - - - - Consultant Services) III. Selection of Consultants 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. Description of Estimated Packages Review Comments No. Assignment Cost by Bank US$ (Prior / million Post) Summary of number of 608,000 1 Prior contracts that will be let under QCBS Summary of number of 266,000 6 Post INDV contracts that will be let under other methods PROCUREMENT Nepal : Building Resilience to Climate Related Hazards PLAN General Information Country: Nepal Bank’s Approval Date of the Original Procurement Plan: 2017-06-07 2019-07-08 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P127508 GPN Date: Project Name: Building Resilience to Climate Related Hazards Loan / Credit No: TF / 13665, TF / 13557 Executing Agency(ies): Department of Hydrology and Metereology WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PPCR/DHM/W/NCB-11 / Construction of infrastructure (approach road, store, water Single Stage - One TF / 13665 Post Request for Bids Open - National 140,835.09 Signed 2017-07-30 2017-08-04 2017-09-15 2017-10-15 2017-11-19 2018-01-18 tank etc) for installation of Envelope RADAR centre in Surkhet (B.1.4) PPCR/DHM/W/NCB-12 / Construction of infrastructure (approach road, store, water Single Stage - One TF / 13557 Post Request for Bids Open - National 0.00 Canceled 2017-06-30 2017-07-05 2017-08-16 2017-09-15 2017-10-20 2018-04-18 tank etc) for installation of Envelope Upper Air Radiosonde in Kirtipur (B1.5) PPCR/DHM/W/SH-15 / Maintenance of Store house Request for Single Stage - One TF / 13665 Post Limited 10,016.90 Signed 2018-05-18 2018-07-13 2018-12-10 at RADAR site Quotations Envelope Surkhet(B.1.4) PPCR/DHM/W/NCB-12-1 / Construction of infrastructure (approach road, store, water Single Stage - One TF / 13665 Post Request for Bids Open - National 50,507.31 Signed 2018-02-08 2018-02-13 2018-03-27 2018-04-26 2018-05-31 2018-07-15 tank etc) for installation of Envelope Upper Air Radiosonde in Kirtipur (B1.5) PPCR/DHM/W/SH-14 / Shifting of electric pole and Request for Single Stage - One electrification to the TF / 13665 Post Limited 13,465.00 Signed 2018-05-23 2018-07-18 2018-11-15 Quotations Envelope Radiosonde site in Kirtipur, Kathmandu (B.1.4) PPCR/DHM/W/ICB-10 / (Re) construction & refurbishment Open - Single Stage - One TF / 13557 Post Request for Bids 3,013,680.96 Signed 2018-09-30 2018-10-05 2018-11-16 2018-12-16 2019-01-20 2019-07-19 of DHM office building (B International Envelope 5.1) PPCR/DHM/W/SH-17 / Pending Improvement of Hydrological Request for Single Stage - One TF / 13665 Post Limited 0.00 Implementati 2019-03-05 2019-04-30 2019-07-29 Station of Saptakoshi river Quotations Envelope on at Chatara (B.1.2) PPCR/DHM/W/SH-18 / Improvement of Hydrological Pending Request for Single Stage - One stations of Sunkoshi River TF / 13665 Post Limited 0.00 Implementati 2019-03-20 2019-05-15 2019-08-13 Quotations Envelope at Hampachuwar and Arun on river at Simle (B.1.2) Page 1 PPCR/DHM/W/SH-19 / Improvement of Hydrological Under Request for Single Stage - One stations of East Rapti River TF / 13665 Post Limited 0.00 Implementati 2019-03-30 2019-05-25 2019-08-23 Quotations Envelope at Rajaya and Bagmati at on Raigaun and Bhorleni (B.1.2) PPCR/DHM/W/SH-20 / Under Improvement of Hydrological Request for Single Stage - One TF / 13665 Post Limited 0.00 Implementati 2019-04-15 2019-06-10 2019-09-08 stations of West Rapti Quotations Envelope on River at Kusum (B.1.2) PPCR/DHM/W/SH-21 / Improvement of Hydrological Under Request for Single Stage - One stations of Tamor river, TF / 13665 Post Limited 0.00 Implementati 2019-04-15 2019-06-10 2019-09-08 Quotations Envelope Mewa Khola and Kabeli on Khola at Taplejung (B.1.2) PPCR/DHM/W/SH-22 / Improvement of Hydrological stations of Indrawati, Pending Request for Single Stage - One Dolalghat, Sunkoshi TF / 13665 Post Limited 0.00 Implementati 2019-04-20 2019-06-15 2019-09-13 Quotations Envelope Tokselghat and Khokhajor on Khola Hariharpur Gadi (B.1.2) PPCR/DHM/W/SH-13 / Construction of Compound Request for Single Stage - One wall, Fencing, Water Tank TF / 13557 Post Limited 19,060.00 Completed 2019-03-15 2019-05-10 2019-11-06 Quotations Envelope etc at RADAR site in Surkhet (B1.5) PPCR/DHM/W/NCB-7 / Improvement of hydrological Pending stations including Single Stage - One TF / 13665 Post Request for Bids Open - National 0.00 Implementati 2019-03-31 2019-04-05 2019-05-17 2019-06-16 2019-07-21 2019-11-18 Establishment of Cable way Envelope on system at selected stations(B.1.2) PPCR/DHM/W/SH-16 / Construction of Protection Request for Single Stage - One TF / 13665 Post Limited 6,797.93 Completed 2019-03-05 2019-04-30 2019-06-29 wall in Approach Road at Quotations Envelope RADAR site Surkhet. (B.1.2) PPCR/DHM/W/SH-24 / Construction of High Quality Pending Request for Single Stage - One Earthing System for TF / 13557 Post Limited 0.00 Implementati 2019-04-15 2019-06-10 2019-08-09 Quotations Envelope Lightning Safety at RADAR on Site (B. 1.2) GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PPCR/DHM/G/ICB-25 / Technical Re-equipment of Hydrological Network and Special Equipment for Open - Single Stage - One TF / 13557 Prior Request for Bids 1,938,600.54 Signed Hydrological Stations International Envelope (Supply, Delivery, Installation and Commissioning ) Page 2 PPCR/DHM/G/ICB-23 / Surface Meteorological Open - Single Stage - One Network (Supply, Delivery, TF / 13557 Prior Request for Bids 3,780,599.43 Signed International Envelope Installation and Commissioning PPCR/DHM/G/DC-33 / Procurement of 4WD Double TF / 13557 Prior Direct Selection Direct 125,567.23 Signed Cab Pickup (4 Pieces) PPCR/DHM/G/ICB-46 / Establishment of Under Open - Single Stage - One Meteorological Instrument TF / 13665 Post Request for Bids 159,653.00 Implementati 2017-08-10 2017-08-15 2017-09-29 2017-10-29 2017-12-03 2018-10-02 International Envelope Calibration Laboratory on (B.1.9) PPCR/DHM/G/ICB-29 / Delivery and installation of Weather Radar for detection Single Stage - One TF / 13557 Prior Request for Bids Open - National 1,560,349.39 Signed 2017-06-21 2017-06-26 2017-08-07 2017-09-06 2017-10-11 2018-10-11 of heavy precipitation and Envelope other meteorological phenomenon (B.1.4) PPCR/DHM/G/ICB-45 / Establishment of Hydro- meteorological work stations Open - Single Stage - One TF / 13665 Prior Request for Bids 1,031,728.00 Signed 2017-08-10 2017-08-15 2017-09-26 2017-10-26 2017-11-30 2018-11-29 and automated production International Envelope system (C.1.1, C.2.2, C.3, C.4.1, C.4.3 ) PPCR/DHM/G/ICB-28 / Highpower Computers for Open - Single Stage - One TF / 13665 Post Request for Bids 327,327.00 Signed 2017-07-19 2017-07-24 2017-09-04 2017-10-04 2017-11-08 2018-10-21 Neumerical Weather International Envelope Prediction(B.3.1) PPCR/DHM/G/NCB-17 / Single Stage - One Remote sensing and GIS TF / 13557 Post Request for Bids Open - National 225,115.27 Signed 2017-11-18 2017-11-23 2018-01-04 2018-02-03 2018-03-10 2018-09-06 Envelope Laboratory(B.2.3) PPCR/DHM/G/ICB-34 / Bank Operating Discharge Measurement System at four Single Stage - One TF / 13557 Post Request for Bids Open - National 0.00 Canceled 2017-08-01 2017-08-06 2017-09-17 2017-10-17 2017-11-21 2018-11-16 reivrs (Koshi, Narayani, Envelope West Rapti and Karnali) (B.1.1) PPCR/DHM/G/ICB-43 / Pilot operation of water quality Open - Single Stage - One TF / 13557 Post Request for Bids 0.00 Canceled 2017-12-30 2018-01-04 2018-02-18 2018-03-20 2018-04-24 2018-11-30 and sediment monitoring International Envelope Stations (B.4.1) PPCR/DHM/G/NCB-30 / Communication Equipment Single Stage - One for ICT Infrastructure and TF / 13557 Post Request for Bids Open - National 173,372.85 Signed 2017-12-28 2018-01-02 2018-02-13 2018-03-15 2018-04-19 2018-10-16 Envelope Management System(DHM Networks and Offices) (B.2.1) PPCR/DHM/G/ICB-24 / Open - Single Stage - One lighting detection network TF / 13557 Post Request for Bids 344,277.00 Completed 2017-11-18 2017-11-23 2018-01-04 2018-02-03 2018-03-10 2018-09-06 International Envelope (lightning detectors) (B.1.7) PPCR/DHM/G/SH-39 / Procurement of Request for Single Stage - One Scooter/motorbikes (4 pieces) TF / 13665 Post Limited 7,167.27 Signed 2018-05-19 2018-07-07 2018-08-06 Quotations Envelope to support PMU Operation (B.1.10) Page 3 PPCR/DHM/G/SH-51 / Procurement of Heavy duty Request for Single Stage - One multiple printer (including TF / 13665 Post Limited 0.00 Canceled 2018-05-23 2018-07-18 2018-08-17 Quotations Envelope software and accessories) (1 pieces) (A.3.2) PPCR/DHM/G/SH-52 / Pending Procurement of Furniture TF / 13665 Post Direct Selection Direct 0.00 Implementati 2018-11-15 2018-11-20 2018-12-25 2019-01-24 and Fixture (A.3.2) on PPCR/DHM/G/SH-53 / Request for Single Stage - One Procurement of Monitors for TF / 13665 Post Limited 0.00 Canceled 2018-04-25 2018-06-13 2018-07-13 Quotations Envelope Desktop Mounting (A.3.2) PPCR/DHM/G/SH-50 / Procurement of Color printer- Request for Single Stage - One 1 (including software, other TF / 13665 Post Open - National 0.00 Canceled 2018-02-20 2018-04-17 2018-06-16 Quotations Envelope equipment and machines etc)- (A.3.2) PPCR/DHM/G/ICB-47 / Establishment of Weather Open - Single Stage - One TF / 13665 Post Request for Bids 314,649.42 Signed 2018-09-10 2018-09-15 2018-10-30 2018-11-29 2019-01-03 2019-10-30 Broadcasting TV Studio International Envelope (C.1.2) PPCR/DHM/G/SH-49 / Procurement of laptop-8 Pending Request for Single Stage - One (including software, other TF / 13665 Post Limited 0.00 Implementati 2019-03-05 2019-04-30 2019-08-28 Quotations Envelope office equipment and on machines)-(A.3.2) PPCR/DHM/G/ICB-48 / Open - Single Stage - One Establishment of Tracer TF / 13665 Post Request for Bids 0.00 Canceled 2018-11-05 2018-11-10 2018-12-25 2019-01-24 2019-02-28 2019-10-26 International Envelope Laboratory (B.1.3) PPCR/DHM/G/SH-44 / Procurement of Desktop Pending Request for Single Stage - One Computer for 28 Synoptic TF / 13665 Post Limited 0.00 Implementati 2019-07-05 2019-08-30 2019-12-28 Quotations Envelope and Aerosynoptic Stations (B on 1.7) PPCR/DHM/G/ICB-36 / Snow,Glacier and Weather Open - Single Stage - One TF / 13557 Prior Request for Bids 0.00 Canceled 2017-08-30 2017-09-04 2017-10-16 2017-11-15 2017-12-20 2018-06-18 Monitoring (Equipment and International Envelope pilot survey) (B.1.8) PPCR/DHM/G/ICB-42 / Pilot Open - Single Stage - One operation of air quality TF / 13665 Post Request for Bids 0.00 Canceled 2017-12-31 2018-01-05 2018-02-19 2018-03-21 2018-04-25 2018-10-22 International Envelope monitoring Stations (B.4.1) PPCR/DHM/G/ICB-42-2 / Under Pilot operation of Air Open - Single Stage - One TF / 13665 Post Request for Bids 0.00 Implementati 2019-02-28 2019-03-05 2019-04-19 2019-05-19 2019-06-23 2019-12-20 Quality Monitoring Stations International Envelope on (B.4.1) PPCR/DHM/G/NCB-56 / Under Single Stage - One Furniture and Fixture for TF / 13665 Post Request for Bids Open - National 0.00 Implementati 2019-04-25 2019-04-30 2019-06-11 2019-07-11 2019-08-15 2019-11-13 Envelope DHM new Building (B.5.1) on PPCR/DHM/G/NCB-53 / Under Procurement of Six meter Single Stage - One TF / 13557 Post Request for Bids Open - National 0.00 Implementati 2019-04-15 2019-04-20 2019-06-01 2019-07-01 2019-08-05 2019-12-03 Mast for AWS installed at Envelope on Airports (B.1.7) Page 4 PPCR/DHM/G/DC-60 / Pending Procurement of Digital TF / 13557 Post Direct Selection Direct 0.00 Implementati 2019-04-30 2019-05-05 2019-06-09 2019-12-06 Forecast Data from on ECMWF(B.3.1) NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PPCR/DHM/NS/SH-5 / Under Procurement Management Request for Single Stage - One TF / 13665 Post Limited 0.00 Implementati 2018-11-06 2019-01-01 2019-01-31 Training to BRCH/DHM Quotations Envelope on Personnel (A 2.1) PPCR/DHM/NS-6 / Driver to run the project vehicle at TF / 13665 Post Direct Selection Direct 0.00 Canceled 2017-07-16 2017-07-21 2017-08-25 2018-08-24 central and field level(A.3.2) PPCR/DHM/NS-7 / Driver to run the project vehicle at TF / 13665 Post Direct Selection Direct 0.00 Canceled 2017-07-16 2017-07-21 2017-08-25 2018-08-24 central and field level(A.3.2) PPCR/DHM/NS/SH-2 / Development of Audio Visual Request for Single Stage - One TF / 13665 Post Limited 0.00 Canceled 2019-01-21 2019-03-18 2019-07-16 Documentary of Project Quotations Envelope Activities (C 4.5) PPCR/DHM/NS/IND-10-11 / Pending Security Guard-2(two) for TF / 13665 Post Direct Selection Direct 0.00 Implementati 2019-02-28 2019-03-05 2019-04-09 2019-10-06 Upper Air Radio Sonde site on at Kirtipur, Kathmandu PPCR/DHM/NS/IND-9-10 / Pending Security Guard-2(two) for TF / 13665 Post Direct Selection Direct 0.00 Implementati 2019-02-28 2019-03-05 2019-04-09 2019-10-06 RADAR Centre site at on Surkhet (A.3.2) PPCR/DHM/NS/SH-8 / Pending Financial Management Request for Single Stage - One TF / 13665 Post Limited 0.00 Implementati 2019-03-15 2019-05-10 2019-06-09 Training to BRCH/DHM Quotations Envelope on Personnel (A 2.1) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PPCR/DHM/S/FBS-11 / GENERAL CONSULTANT - SYSTEM INTEGRATOR, Fixed Budget Open - Consulting Service for TF / 13665 Prior 2,627,441.05 Signed Selection International Detailed Design of the DHM System, Procurement and Implementation Support PPCR/DHM/S/CQS-13 / Consultant Development of a legal and Open - TF / 13557 Prior Qualification 91,048.78 Signed regulatory framework for International Selection DHM Operations Page 5 PPCR/DHM/S/CQS-54 / Consultancy service for Consultant Development and TF / 13665 Post Qualification Open - National 0.00 Canceled 2017-10-10 2017-10-31 2017-12-14 2018-01-13 2018-02-17 2018-08-16 Operationalization of Selection Forecast Verification System (C 1.3) PPCR/DHM/S/CQS-56 / Consultancy service for Consultant Development of an TF / 13665 Post Qualification Open - National 32,405.36 Signed 2017-09-01 2017-09-22 2017-11-05 2017-12-05 2018-01-09 2018-07-08 Integrated Web Portal for Selection DHM (C.1.2) PPCR/DHM/S/CQS-40 / Development of Cost Consultant Recovery System/Business TF / 13665 Post Qualification Open - National 0.00 Canceled 2017-06-21 2017-07-12 2017-08-25 2017-09-24 2017-10-29 2018-04-27 Model of DHM(specially for Selection Aeronautical Forecasting Services) (A.1.2) PPCR/DHM/S/CQS-26 / Consultancy service for Consultant Development of digital TF / 13665 Post Qualification Open - National 48,200.68 Signed 2017-06-21 2017-07-12 2017-08-25 2017-09-24 2017-10-29 2018-04-27 elevation map for Terai Selection Region (C.2.3) PPCR/DHM/S/CQS-41 / ICT Consultant Infrastructure and Data TF / 13665 Post Qualification Open - National 106,426.74 Signed 2017-07-06 2017-07-09 2017-08-07 2017-08-22 2017-10-03 2018-08-03 Management System for Selection DHM (B 2.2) PPCR/DHM/S/CQS-42 / Implementing and commissioning of High Consultant Resolution Local Area TF / 13665 Post Qualification Open - National 146,230.00 Signed 2017-06-21 2017-07-12 2017-08-25 2017-09-24 2017-10-29 2018-08-28 Numerical Weather Selection Prediction System at DHM (B 2.2) PPCR/DHM/QCBS-34 / Consultancy service for "Establishment of " END-To- END" Flood Early Warning Quality And Cost- Open - System in Koshi & West TF / 13665 Prior 792,788.03 Signed 2017-10-23 2017-11-13 2017-12-27 2018-01-24 2018-02-23 2018-03-30 2018-05-04 2018-11-20 Based Selection International Rapti River Basins to Support & Strengthen Disaster Risk Management" (C2) PPCR/DHM/S/CQS-8 / Consultancy firm for the Consultant Under detailed design and TF / 13665 Prior Qualification Open - National 0.00 2017-11-18 2017-12-09 2018-01-22 2018-02-21 2018-03-28 2018-09-24 Implementation supervision of DHM office Selection building construction (A.3.4) PPCR/DHM/S/CQS-52 / Consultant Development of mobile apps TF / 13665 Post Qualification Open - National 0.00 Canceled 2017-06-21 2017-07-12 2017-08-25 2017-09-24 2017-10-29 2018-02-26 for hydro-meteorological Selection services (C.4.5) PPCR/DHM/S/QCBS-37 / Support to development of Quality And Cost- Open - National Framework for TF / 13557 Post 0.00 Canceled 2017-06-21 2017-07-12 2017-08-25 2017-09-22 2017-10-22 2017-11-26 2017-12-31 2018-09-30 Based Selection International climate services and support to sectoral work groups(C4.2) Page 6 PPCR/DHM/S/CQS-54-2 / Consultancy service for Consultant Development and Under TF / 13665 Post Qualification Open - National 0.00 2018-10-15 2018-11-05 2018-12-19 2019-01-18 2019-02-22 2019-08-21 Operationalization of Implementation Selection Forecast Verification System (C 1.3) PPCR/DHM/CQS-37 / Support to Development of Consultant National Framework for Open - Under TF / 13665 Post Qualification 0.00 2019-01-31 2019-02-21 2019-04-06 2019-05-06 2019-06-10 2019-11-07 Climate Services and International Implementation Selection Support to Sectoral Workgroup (C 4.2) PPCR/DHM/S/CQS-55 / Consultant Consultancy service for End Under TF / 13665 Post Qualification Open - National 0.00 2019-03-31 2019-04-21 2019-06-04 2019-07-04 2019-08-08 2019-11-06 Line User's Satisfaction Implementation Selection Survey (A.3.2) PPCR/DHM/S/CQS-60 / Consultant Open - Pending Twinning operation support TF / 13665 Post Qualification 0.00 2019-03-31 2019-04-21 2019-06-04 2019-07-04 2019-08-08 2019-10-07 International Implementation and capacity building (A.1.3) Selection PPCR/DHM/S/CQS-35 / Consultancy service for Consultant development of needs TF / 13557 Post Qualification Open - National 0.00 Canceled 2017-06-21 2017-07-12 2017-08-25 2017-09-24 2017-10-29 2018-04-27 assessment and design of Selection water quality and sediment monitoring networks(A.3.3) PPCR/DHM/S/CQS-92 / Consultancy Service to Consultant Conduct Training Course on Under TF / 13665 Post Qualification Open - National 0.00 2019-04-30 2019-05-21 2019-07-04 2019-08-03 2019-09-07 2019-11-06 "Using Modern Weather Implementation Selection Observation System For Nowcasting (A.2.1i) INDIVIDUAL CONSULTANTS Page 7