Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: July 27, 2015]: Revision 9 of Updated Procurement Plan, Mar 2, 2017] 2. Date of General Procurement Notice: July 2015 3. Period covered by this procurement plan: The procurement period of project covered from Jul 2015 to December 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Prior Review Threshold Comments US$ 1. Goods Above USD 2M All 3. Reference to (if any) Project Operational/Procurement Manual: Project Operations Manual and SOPs for Procurement III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 3. Consulting firms Above USD 1M All 4. Individual Consultants Above USD 0.3 M All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None Apr 18, 2017 PROCUREMENT Pakistan : FATA Temporarily Displaced Persons Emergency Recovery Project PLAN General Information Country: Pakistan Bank’s Approval Date of the Original Procurement Plan: 2016-05-05 2020-01-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P154278 GPN Date: Project Name: FATA Temporarily Displaced Persons Emergency Recovery Project Loan / Credit No: IDA / 57190, IDA / 61390 Executing Agency(ies): National Database and Registration Authority WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Early NADRA/PMO/93, EAD PP, Recovery Package for Request for Open - Activity 3 / First Shopping IDA / 57190 Prior 15,822.21 Signed Temporary Displaced Quotations International for EAD-PMU Persons NADRA/PMO/93, NADRA PP, Activity 1 & 3 / Standard Bidding Documents Component 1: Early for ICB Procurement under Recovery Package for Open - Single Stage - One TDP-ERP NADRA IDA / 57190 Prior Request for Bids 199,984.39 Signed Temporary Displaced International Envelope procurement plan for the Persons Activity 1( IT HQ Equipment & Activity 3 ( Equipment for OSS) PK-NADRA-75-GO-RFQ / Component 3: Strengthening Project Office Renovation Request for Single Stage - One IDA / 57190 program management and Post Open - National 25,733.01 Completed 2016-05-17 2016-07-12 2017-01-08 work (Purchase of furniture Quotations Envelope oversight & Office equipment) PK-NADRA-76-GO-RFQ / Component 3: Strengthening Request for Single Stage - One Purchase of Vehicles IDA / 57190 program management and Prior Open - National 179,480.57 Signed 2016-05-21 2016-07-16 2017-01-12 Quotations Envelope (NADRA) oversight PK-NADRA-77-GO-RFQ / Component 3: Strengthening Purchase of Communication Request for Single Stage - One IDA / 57190 program management and Post Open - National 10,602.43 Completed 2016-05-14 2016-07-09 2017-01-05 equipment (Mobile Quotations Envelope oversight Phones)NADRA PK-NADRA-78-GO-RFQ / Component 3: Strengthening Pending Request for Single Stage - One Purchase of OSS network IDA / 57190 program management and Post Open - National 0.00 Implementati 2016-05-14 2016-07-09 2017-01-05 Quotations Envelope equipment(NADRA) oversight on PK-NADRA-79-GO-RFQ / Component 3: Strengthening Pending Request for Single Stage - One Purchase of OSS Furniture IDA / 57190 program management and Post Open - National 0.00 Implementati 2016-05-14 2016-07-09 2017-01-05 Quotations Envelope & Fixtures (NADRA) oversight on PK-NADRA-83-GO-RFQ / Component 3: Strengthening Request for Single Stage - One OSS Laptops & Printer IDA / 57190 program management and Post Open - National 35,918.50 Completed 2016-05-14 2016-07-09 2017-01-05 Quotations Envelope (NADRA) oversight Page 1 PK-NADRA-86-GO-RFQ / IT Equipment ( Component 3: Strengthening Pending Photocopier,Desktop Request for Single Stage - One IDA / 57190 program management and Post Open - National 0.00 Implementati 2016-05-14 2016-07-09 2017-01-05 computer,printers,laptops,fax Quotations Envelope oversight on machines,digital camera,LED) FDMA Component 3: Strengthening PK-NADRA-89-GO-RFQ / Request for Single Stage - One IDA / 57190 program management and Post Open - National 0.00 Canceled 2016-06-04 2016-07-30 2017-01-26 Office furniture Quotations Envelope oversight PK-NADRA-96-GO-RFQ / Component 3: Strengthening Request for Single Stage - One Communication Devices IDA / 57190 program management and Post Open - National 0.00 Canceled 2016-06-04 2016-07-30 2017-01-26 Quotations Envelope (Mobile Phones)EAD oversight PK-NADRA-100-GO-RFQ / Component 3: Strengthening Pending Request for Single Stage - One Furniture and Fixtures IDA / 57190 program management and Post Open - National 0.00 Implementati 2016-05-15 2016-07-10 2017-01-06 Quotations Envelope (EAD) oversight on PK-NADRA-84-GO-RFB / Component 3: Strengthening Single Stage - One Purchase of Laptops & IDA / 57190 program management and Post Request for Bids Open - National 41,283.83 Completed 2016-06-26 2016-07-01 2016-08-12 2016-09-11 2016-10-16 2017-04-14 Envelope Printers for OSS (NADRA) oversight PK-NADRA-82-GO-RFB / Purchase of Thumb Component 3: Strengthening Digitizer,Barcode Single Stage - One IDA / 57190 program management and Prior Request for Bids Open - National 46,848.81 Signed 2016-05-15 2016-05-20 2016-07-01 2016-07-31 2016-09-04 2017-03-03 Reader,LED,switch 24 Envelope oversight port,WAP,Satellite Link,UPS (NADRA) PK-NADRA-184-GO-RFQ / Component 3: Strengthening Request for Single Stage - One Purchase of Vehicles-PMU IDA / 57190 program management and Post Open - National 39,924.93 Completed 2016-07-18 2016-09-12 2017-03-11 Quotations Envelope EAD oversight Component 3: Strengthening PK-NADRA-85-GO-RFQ / Request for Single Stage - One IDA / 57190 program management and Post Open - National 0.00 Canceled 2016-05-14 2016-07-09 2017-01-05 Solar Refrigerators (DoH) Quotations Envelope oversight PK-NADRA-4258-GO-DIR / Component 3: Strengthening Procurement of Solar IDA / 57190 program management and Prior Direct Selection Direct 37,966.14 Signed 2016-12-07 2016-12-12 2017-01-16 2017-07-15 Refrigerators for DoH oversight PK-NADRA-13054-GO-RFB / Procurement of IP Phone, CCTV/IP Camera per site solution, Mac Book, iPad Pro Component 3: Strengthening 9.7", Small & Medium Scale Single Stage - One IDA / 57190 program management and Post Request for Bids Open - National 27,353.53 Completed 2017-04-26 2017-05-01 2017-06-12 2017-07-12 2017-08-16 2018-02-12 Card Project Printer with Envelope oversight Laminator,Thumb Digitizer 1:1,Barcode Reader,LED,Switch 24 Port , Wireless Access Point,UPS PK-NADRA-23067-GO-RFQ / Component 3: Strengthening Request for Single Stage - One Procurement of Scale Card IDA / 57190 program management and Post Open - National 10,975.75 Completed 2017-08-06 2017-10-01 2018-03-30 Quotations Envelope Printer including Laminator, oversight Component 3: Strengthening PK-NADRA-40050-GO-RFQ / Request for Single Stage - One IDA / 57190 program management and Post Open - National 6,772.01 Completed 2017-12-31 2018-02-25 2018-08-24 Procurement of LED TV Quotations Envelope oversight PK-NADRA-62898-GO-RFQ / Component 3: Strengthening Request for Single Stage - One Procurement of 1 x 125cc IDA / 61390 program management and Post Open - National 779.13 Completed 2018-05-22 2018-07-17 2018-08-16 Quotations Envelope Motor cycle oversight Page 2 PK-NADRA-80601-GO-RFQ / Procurement of Furniture (25xComputer Tables,67 x Computer Chairs,5 x Site Incharge Tables,5xSite Component 3: Strengthening Request for Single Stage - One Incharge Chairs,15xAir IDA / 61390 program management and Post Open - National 1,594.00 Completed 2018-10-09 2018-12-04 2019-06-02 Quotations Envelope Coolers,15xWall Mounted oversight Fans, 15xWater Coolers, 130 x Waiting Chairs (3 Seats), 35 x Applicant Chairs, 04 x Executive Tables&Chairs ) PK-NADRA-119704-GO-RFQ / Procurement of Furniture Component 3: Strengthening Request for Single Stage - One for 03 x existing OSSs for IDA / 61390 program management and Post Open - National 11,549.01 Signed 2019-06-29 2019-08-24 2020-02-20 Quotations Envelope conversion into CFCs (Pilot oversight Sites) PK-NADRA-119705-GO-RFQ / Up gradation of existing 03 x OSSs for conversion Component 3: Strengthening Request for Single Stage - One into CFCs (Pilot Sites) IDA / 61390 program management and Post Open - National 56,167.43 Signed 2019-06-29 2019-08-24 2020-02-20 Quotations Envelope (Wood/Glass Partition, oversight flooring,ceiling,electrical & Paint Job etc) PK-NADRA-119707-GO-RFQ Component 3: Strengthening Pending Request for Single Stage - One / Procurement of Laptops for IDA / 61390 program management and Post Open - National 0.00 Implementati 2019-07-20 2019-09-14 2020-03-12 Quotations Envelope PMU EAD. oversight on PK-NADRA-119710-GO-RFQ Component 3: Strengthening Pending Request for Single Stage - One / Procurement of IDA / 61390 program management and Post Open - National 0.00 Implementati 2019-07-27 2019-09-21 2020-03-19 Quotations Envelope Communication Devices oversight on PK-NADRA-119717-GO-DIR Component 3: Strengthening Under / Procurement of Solar IDA / 61390 program management and Prior Direct Selection Direct 0.00 Implementati 2019-07-29 2019-08-03 2019-09-07 2020-03-05 Refrigerators oversight on (Goods) PK-NADRA-119720-GO-RFB / i.Procurement of IT Equipment & Hardware (Goods) for 05 x new sites (CFCs) at Existing Tribal Component 3: Strengthening Under Single Stage - One Districts IDA / 61390 program management and Post Request for Bids Open - National 0.00 Implementati 2019-07-01 2019-07-06 2019-08-17 2019-09-16 2019-10-21 2020-04-18 Envelope (Goods) ,07 x new sites oversight on (Sites) at Bajur & Mohmand Tribal Districts (Goods) & for existing 15 x OSSs- Server/Stroage PK-NADRA-119721-GO-RFB / Procurement of Furniture 05 x new sites (CFCs) at Existing Tribal Districts ,for Component 3: Strengthening Under 07 x new sites(CFCs) at Single Stage - One IDA / 61390 program management and Post Request for Bids Open - National 0.00 Implementati 2019-07-01 2019-07-06 2019-08-17 2019-09-16 2019-10-21 2020-04-18 Bajaur & Mohmand Tribal Envelope oversight on Districts & for existing 12 x OSSs for conversion into CFCs at existing Tribal Districts. PK-NADRA-119727-GO-RFB / Up gradation of existing 07 x OSSs for conversion into Citizen Facilitation Centers -CFCs and for the Component 3: Strengthening Under Single Stage - One establishment of 07 x New IDA / 61390 program management and Post Request for Bids Open - National 0.00 Implementati 2019-08-18 2019-08-23 2019-10-04 2019-11-03 2019-12-08 2020-06-05 Envelope Sites (CFCs) - (Procurement oversight on of Furniture and Wood/Glass Partition, flooring, roof ceiling, electrical & Paint Job etc.) Page 3 PK-NADRA-126239-GO-RFB / Up gradation of existing 5 x OSSs for conversion into Component 3: Strengthening Pending Single Stage - One CFCs (Wood/Glass Partition, IDA / 61390 program management and Post Request for Bids Open - National 0.00 Implementati 2019-09-08 2019-09-13 2019-10-25 2019-11-24 2019-12-29 2020-06-26 Envelope floor matting, electrical work oversight on etc.) and Establishment of 05 x new sites(CFCs). PK-NADRA-151630-GO-RFQ / Procurement of Goods Component 3.2: Enabling Pending through Shopping Method. Request for Single Stage - One IDA / 57190 Citizen Centric Service Post Open - National 0.00 Implementati 2019-12-31 2020-02-25 2020-08-23 (Digital Camera, Water Quotations Envelope Delivery on Coolers, Metal Detectors, Split AC, IP Phone etc). NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-NADRA-102-CS-QCBS / Component 3: Strengthening Communication Firm ,Social Quality And Cost- Open - IDA / 57190 program management and Prior 445,237.16 Signed 2016-05-16 2016-06-06 2016-07-20 2016-08-17 2016-09-16 2016-10-21 2016-11-25 2017-11-25 Mobilization, PIC & Based Selection International oversight Communication,EAD PK-NADRA-101-CS-QCBS / Component 3: Strengthening Quality And Cost- Open - Operational Review of FATA IDA / 57190 program management and Prior 445,087.90 Signed 2016-05-17 2016-06-07 2016-07-21 2016-08-18 2016-09-17 2016-10-22 2016-11-26 2017-11-26 Based Selection International TDP ERP oversight Component 3: Strengthening Consultant PK-NADRA-103-CS-CQS / Open - IDA / 57190 program management and Prior Qualification 0.00 Canceled 2016-09-01 2016-09-22 2016-11-05 2016-12-05 2017-01-09 2017-07-08 Beneficiary Survey, EAD International oversight Selection PK-NADRA-5111-CS-CQS / Component 3: Strengthening Consultant Open - Beneficiary Feedback Survey, IDA / 57190 program management and Post Qualification 0.00 Canceled 2016-12-29 2017-01-19 2017-03-04 2017-04-03 2017-05-08 2017-11-04 International EAD PMU oversight Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Actual Amount Draft Negotiated Description Component Review Type Method Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. Approach (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-NADRA-104-CS-INDV / Component 3: Strengthening Individual Management Information IDA / 57190 program management and Prior Consultant Open - National 0.00 Canceled 2016-05-10 2016-06-28 2016-07-19 2016-08-23 2017-02-19 System Specialist,EAD oversight Selection Component 3: Strengthening Individual PK-NADRA-107-CS-INDV / IDA / 57190 program management and Prior Consultant Open - National 0.00 Canceled 2016-05-10 2016-06-28 2016-07-19 2016-08-23 2017-02-19 Program Officer,EAD oversight Selection Component 3: Strengthening Individual PK-NADRA-110-CS-INDV / IDA / 57190 program management and Prior Consultant Open - National 0.00 Canceled 2016-05-13 2016-07-01 2016-07-22 2016-08-26 2017-02-22 Accountant oversight Selection Page 4 Component 3: Strengthening Individual PK-NADRA-113-CS-INDV / IDA / 57190 program management and Prior Consultant Open - National 0.00 Canceled 2016-05-13 2016-07-01 2016-07-22 2016-08-26 2017-02-22 Health Coordinator ,EAD oversight Selection Component 3: Strengthening Individual PK-NADRA-114-CS-INDV / IDA / 57190 program management and Prior Consultant Open - National 0.00 Canceled 2016-05-13 2016-07-01 2016-07-22 2016-08-26 2017-02-22 Regional Coordinator oversight Selection Component 3: Strengthening Individual PK-NADRA-115-CS-INDV / IDA / 57190 program management and Prior Consultant Open - National 0.00 Canceled 2016-05-13 2016-07-01 2016-07-22 2016-08-26 2017-02-22 MIS Associate oversight Selection PK-NADRA-119-CS-INDV / Component 3: Strengthening Individual Under Planning and Services IDA / 57190 program management and Prior Consultant Open - National 0.00 2016-05-13 2016-07-01 2016-07-22 2016-08-26 2017-02-22 Implementation Consultant oversight Selection PK-NADRA-121-CS-INDV / Component 3: Strengthening Individual Under Grievance Specialist IDA / 57190 program management and Prior Consultant Open - National 0.00 2016-05-13 2016-07-01 2016-07-22 2016-08-26 2017-02-22 Implementation ,HQ,FDMA oversight Selection PK-NADRA-122-CS-INDV / Component 3: Strengthening Individual Under Grievance IDA / 57190 program management and Prior Consultant Open - National 0.00 2016-05-13 2016-07-01 2016-07-22 2016-08-26 2017-02-22 Implementation Specialist,Field,FDMA oversight Selection PK-NADRA-123-CS-INDV / Component 3: Strengthening Individual Under Grievance IDA / 57190 program management and Prior Consultant Open - National 0.00 2016-05-13 2016-07-01 2016-07-22 2016-08-26 2017-02-22 Implementation Associate,Field,FDMA oversight Selection Component 3: Strengthening Individual PK-NADRA-124-CS-INDV / Under IDA / 57190 program management and Prior Consultant Open - National 0.00 2016-05-13 2016-07-01 2016-07-22 2016-08-26 2017-02-22 MIS Specialist,FDMA Implementation oversight Selection Component 3: Strengthening Individual PK-NADRA-125-CS-INDV / Under IDA / 57190 program management and Prior Consultant Open - National 0.00 2016-05-13 2016-07-01 2016-07-22 2016-08-26 2017-02-22 IT associate,FDMA Implementation oversight Selection Component 3: Strengthening Individual PK-NADRA-126-CS-INDV / Under IDA / 57190 program management and Prior Consultant Open - National 0.00 2016-05-13 2016-07-01 2016-07-22 2016-08-26 2017-02-22 Accountant,FDMA Implementation oversight Selection Component 3: Strengthening Individual PK-NADRA-127-CS-INDV / Under IDA / 57190 program management and Prior Consultant Open - National 0.00 2016-05-13 2016-07-01 2016-07-22 2016-08-26 2017-02-22 Health Coordinator,DoH Implementation oversight Selection PK-NADRA-105-CS-INDV / Component 3: Strengthening Individual Monitoring and evaluation IDA / 57190 program management and Prior Consultant Open - National 0.00 Canceled 2016-05-09 2016-06-27 2016-07-18 2016-08-22 2019-02-28 specialist,EAD oversight Selection Component 3: Strengthening Individual PK-NADRA-116-CS-INDV / IDA / 57190 program management and Prior Consultant Open - National 0.00 Canceled 2016-05-12 2016-06-30 2016-07-21 2016-08-25 2019-02-28 Procurement Consultant oversight Selection Component 3: Strengthening Individual PK-NADRA-118-CS-INDV / Under IDA / 57190 program management and Prior Consultant Open - National 0.00 2016-05-12 2016-06-30 2016-07-21 2016-08-25 2017-02-21 Media Consultant Implementation oversight Selection Component 3: Strengthening Individual PK-NADRA-111-CS-INDV / IDA / 57190 program management and Prior Consultant Open - National 0.00 Canceled 2016-05-12 2016-06-30 2016-07-21 2016-08-25 2019-02-28 Operations Coordinator oversight Selection Component 3: Strengthening Individual PK-NADRA-112-CS-INDV / IDA / 57190 program management and Prior Consultant Open - National 0.00 Canceled 2016-05-12 2016-06-30 2016-07-21 2016-08-25 2019-02-28 Program Manager oversight Selection Page 5 PK-NADRA-106-CS-INDV / Component 3: Strengthening Individual Financial Management IDA / 57190 program management and Prior Consultant Open - National 0.00 Canceled 2016-05-09 2016-06-27 2016-07-18 2016-08-22 2019-02-28 Specialist,EAD oversight Selection Component 3: Strengthening Individual PK-NADRA-117-CS-INDV / IDA / 57190 program management and Prior Consultant Open - National 0.00 Canceled 2016-05-12 2016-06-30 2016-07-21 2016-08-25 2019-02-28 Training Consultant oversight Selection Component 3: Strengthening Individual PK-NADRA-120-CS-INDV / Under IDA / 57190 program management and Prior Consultant Open - National 0.00 2016-05-12 2016-06-30 2016-07-21 2016-08-25 2017-02-21 FATA Coordinator, NADRA Implementation oversight Selection PK-NADRA-168-CS-INDV / Component 3: Strengthening Individual Under Grievance Specialist -I IDA / 57190 program management and Prior Consultant Open - National 0.00 2016-06-14 2016-08-02 2016-08-23 2016-09-27 2017-03-26 Implementation (Field),FDMA oversight Selection PK-NADRA-169-CS-INDV / Component 3: Strengthening Individual Under Grievance Specialist -II IDA / 57190 program management and Prior Consultant Open - National 0.00 2016-06-14 2016-08-02 2016-08-23 2016-09-27 2017-03-26 Implementation (Field),FDMA oversight Selection PK-NADRA-170-CS-INDV / Component 3: Strengthening Individual Under Grievance Specialist -III IDA / 57190 program management and Prior Consultant Open - National 0.00 2016-06-14 2016-08-02 2016-08-23 2016-09-27 2017-03-26 Implementation (Field),FDMA oversight Selection PK-NADRA-171-CS-INDV / Component 3: Strengthening Individual Under Grievance Specialist -IV IDA / 57190 program management and Prior Consultant Open - National 0.00 2016-06-14 2016-08-02 2016-08-23 2016-09-27 2017-03-26 Implementation (Field),FDMA oversight Selection PK-NADRA-172-CS-INDV / Component 3: Strengthening Individual Under Grievance Specialist -V IDA / 57190 program management and Prior Consultant Open - National 0.00 2016-06-14 2016-08-02 2016-08-23 2016-09-27 2017-03-26 Implementation (Field),FDMA oversight Selection PK-NADRA-173-CS-INDV / Component 3: Strengthening Individual Under Grievance Associate -I IDA / 57190 program management and Prior Consultant Open - National 0.00 2016-06-15 2016-08-03 2016-08-24 2016-09-28 2017-03-27 Implementation (Field),FDMA oversight Selection PK-NADRA-174-CS-INDV / Component 3: Strengthening Individual Under Grievance Associate -II IDA / 57190 program management and Prior Consultant Open - National 0.00 2016-06-15 2016-08-03 2016-08-24 2016-09-28 2017-03-27 Implementation (Field),FDMA oversight Selection PK-NADRA-175-CS-INDV / Component 3: Strengthening Individual Under Grievance Associate -III IDA / 57190 program management and Prior Consultant Open - National 0.00 2016-06-15 2016-08-03 2016-08-24 2016-09-28 2017-03-27 Implementation (Field),FDMA oversight Selection PK-NADRA-176-CS-INDV / Component 3: Strengthening Individual Under Grievance Associate -IV IDA / 57190 program management and Prior Consultant Open - National 0.00 2016-06-15 2016-08-03 2016-08-24 2016-09-28 2017-03-27 Implementation (Field),FDMA oversight Selection PK-NADRA-177-CS-INDV / Component 3: Strengthening Individual Under Grievance Associate -V IDA / 57190 program management and Prior Consultant Open - National 0.00 2016-06-15 2016-08-03 2016-08-24 2016-09-28 2017-03-27 Implementation (Field),FDMA oversight Selection PK-NADRA-178-CS-INDV / Component 3: Strengthening Individual Under Grievance Associate -VI IDA / 57190 program management and Prior Consultant Open - National 0.00 2016-06-15 2016-08-03 2016-08-24 2016-09-28 2017-03-27 Implementation (Field),FDMA oversight Selection PK-NADRA-179-CS-INDV / Component 3: Strengthening Individual Under Grievance Associate -VII IDA / 57190 program management and Prior Consultant Open - National 0.00 2016-06-15 2016-08-03 2016-08-24 2016-09-28 2017-03-27 Implementation (Field),FDMA oversight Selection PK-NADRA-180-CS-INDV / Component 3: Strengthening Individual Under Grievance Associate -VIII IDA / 57190 program management and Prior Consultant Open - National 0.00 2016-06-15 2016-08-03 2016-08-24 2016-09-28 2017-03-27 Implementation (Field),FDMA oversight Selection Page 6 Component 3: Strengthening Individual PK-NADRA-3672-CS-INDV / Under IDA / 57190 program management and Prior Consultant Open 0.00 2016-11-24 2017-01-12 2017-02-02 2017-03-09 2018-03-04 Planning Associate Implementation oversight Selection Component 3: Strengthening Individual PK-NADRA-45325-CS-INDV Under IDA / 61390 program management and Prior Consultant Open 0.00 2018-01-29 2018-03-19 2018-04-09 2018-05-14 2019-05-14 / Network Adminisrator Implementation oversight Selection Component 3: Strengthening Individual PK-NADRA-78429-CS-INDV Under IDA / 61390 program management and Prior Consultant Open 0.00 2018-09-18 2018-11-06 2018-11-27 2019-01-01 2019-06-30 / MIS Coordinator,NADRA Implementation oversight Selection Component 3: Strengthening Individual PK-NADRA-78430-CS-INDV Under IDA / 61390 program management and Prior Consultant Open 0.00 2018-09-18 2018-11-06 2018-11-27 2019-01-01 2019-06-30 / GR Coordinator-I,NADRA Implementation oversight Selection Component 3: Strengthening Individual PK-NADRA-78431-CS-INDV IDA / 61390 program management and Prior Consultant Open 0.00 Canceled 2018-09-18 2018-11-06 2018-11-27 2019-01-01 2019-06-30 / GR Coordinator-II,NADRA oversight Selection PK-NADRA-151622-CS-INDV Component 3: Strengthening Individual Pending / Financial Management IDA / 57190 program management and Post Consultant Open 0.00 2019-12-23 2020-02-10 2020-03-02 2020-04-06 2020-10-03 Implementation Specialist for PMU EAD. oversight Selection Component 3: Strengthening Individual PK-NADRA-151624-CS-INDV Pending IDA / 57190 program management and Post Consultant Open 0.00 2019-12-23 2020-02-10 2020-03-02 2020-04-06 2020-10-03 / Accountant for PMU EAD. Implementation oversight Selection PK-NADRA-151625-CS-INDV Component 3: Strengthening Individual Pending / IT Associate for PMU IDA / 57190 program management and Post Consultant Open 0.00 2019-12-23 2020-02-10 2020-03-02 2020-04-06 2020-10-03 Implementation EAD. oversight Selection PK-NADRA-151626-CS-INDV Component 3: Strengthening Individual Pending / Program Officer for PMU IDA / 57190 program management and Post Consultant Open 0.00 2019-12-23 2020-02-10 2020-03-02 2020-04-06 2020-10-03 Implementation EAD. oversight Selection PK-NADRA-151628-CS-INDV Component 3: Strengthening Individual Pending / Procurement Officer for IDA / 57190 program management and Post Consultant Open 0.00 2019-12-23 2020-02-10 2020-03-02 2020-04-06 2020-10-03 Implementation NADRA. oversight Selection PK-NADRA-151629-CS-INDV Component 3: Strengthening Individual Pending / Procurement Assistant, IDA / 57190 program management and Post Consultant Open 0.00 2019-12-23 2020-02-10 2020-03-02 2020-04-06 2020-10-03 Implementation NADRA. oversight Selection Page 7