PROCUREMENT PLAN (Textual Part) Project information: Lebanon- Roads and Employment Project- P160223 Project Implementation agency: Council for Development and Reconstruction- CDR Date of the Procurement Plan: Initial plan of 22-Jan-19 Period covered by this Procurement Plan: From effectiveness Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Public Accounting Law of 1963 and Subsequent amendments, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable Other Relevant Procurement Information. Procurement methods and prior review thresholds Market approach Shortlist composed Goods, IT and non-consulting Works only of national services consultants Internation Engineerin National al and g& Open Open Consultin Open Open national Constructi internation internation g national national on al (shoppin al services (shopping) supervisio g) n US$ US$ US$ US$ US$ US$ US$ US$ Method ≥10,000,00 <10,000,00 < 1,000,00 ≤200,000 ≥1,000,000 ≤100,000 < 300,000 ≤500,000 Thresholds 0 0 0 Proc. All RFB RFB RFQ RFB RFB RFQ QCBS Method methods Proc prior Firms >2,000,000 >15,000,000 >4,000,000 review Ind. >400,000 PROCUREMENT Lebanon : Roads and Employment Project PLAN General Information Country: Lebanon Bank’s Approval Date of the Original Procurement Plan: 2019-01-30 2019-05-22 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160223 GPN Date: 2019-02-13 Project Name: Roads and Employment Project Loan / Credit No: IBRD / 87050, TF / A4481 Executing Agency(ies): Council for Development and Reconstruction WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PSH001 / 10 vehicles Four Wheels Drive, for the Open - Single Stage - One IBRD / 87050 Post Request for Bids 0.00 Canceled 2018-04-01 2019-01-17 2019-02-21 2019-04-07 2019-06-20 2019-10-18 Ministry of Public Works International Envelope and Transport (MoPWT). PSH005 / 5 salt spreaders Under For the Ministry of Public Open - Single Stage - One IBRD / 87050 Post Request for Bids 0.00 Implementati 2018-12-03 2019-02-14 2019-03-31 2019-04-30 2019-06-27 2019-12-24 Works and Transport International Envelope on (MoPWT) PSH003 / 15 Wheel Under loaders, for the Ministry of Single Stage - One IBRD / 87050 Post Request for Bids Limited 0.00 Implementati 2018-04-01 2018-04-06 2018-05-18 2018-06-17 2018-07-22 2019-01-18 Public Works and Transport Envelope on (MoPWT) PSH004 / 10 Snow blowers Under for the Ministry of Public Open - Single Stage - One IBRD / 87050 Post Request for Bids 0.00 Implementati 2018-12-03 2019-02-14 2019-03-31 2019-04-30 2019-06-27 2020-02-22 Works and Transport International Envelope on (MoPWT) PSH001RE / 10 Vehicles Pending Four Wheels Drive, for the Open - Single Stage - One IBRD / 87050 Post Request for Bids 0.00 Implementati 2019-04-11 2019-05-20 2019-06-20 2019-08-04 2019-10-17 2020-02-14 Ministry of Public Works International Envelope on and Transport (MoPWT) NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 FC003 / Design consultant No 3. Lot 3=171.90KM, ACE Least Cost IBRD / 87050 Post Open - National 303,260.00 Signed 2018-03-15 2018-03-15 2018-06-13 2018-09-05 2018-09-19 2018-10-16 2019-01-02 2019-06-24 (Associated Consulting Selection Engineers) FC004 / Design consultant No 4, Lot 4=86.4KM, ACE Least Cost IBRD / 87050 Post Open - National 294,940.00 Signed 2018-03-15 2018-03-15 2018-06-13 2018-09-05 2018-09-19 2018-10-16 2019-01-09 2019-07-01 (Associated Consulting Selection Engineers) FC005 / Design consultant Least Cost No 5, Lot 5=131.20KM, IBRD / 87050 Post Open - National 423,895.00 Signed 2018-03-15 2018-03-15 2018-06-13 2018-09-05 2018-09-19 2018-10-16 2019-01-17 2019-07-09 Selection Team International FC006 / Design consultant Least Cost No 6, Lot 6=140.1KM, Team IBRD / 87050 Post Open - National 252,530.00 Signed 2018-03-15 2018-03-15 2018-06-13 2018-09-05 2018-09-19 2018-10-16 2019-01-17 2019-07-09 Selection International FC007 / Supervision Quality And Cost- Open - Under consultant No 1, Lot IBRD / 87050 Post 0.00 2018-03-13 2018-08-13 2019-02-26 2019-04-27 2019-06-26 2019-08-17 2019-09-27 2021-09-26 Based Selection International Implementation 1=144.9KM FC008 / Supervision Quality And Cost- Open - Under consultant No 2, Lot IBRD / 87050 Post 0.00 2018-03-13 2018-08-13 2019-02-26 2019-04-27 2019-06-26 2019-08-17 2019-09-27 2021-09-26 Based Selection International Implementation 2=165KM FC009 / Supervision Quality And Cost- Open - Under consultant No 3, Lot IBRD / 87050 Post 0.00 2018-03-13 2018-08-13 2019-02-26 2019-04-27 2019-06-26 2019-08-17 2019-09-27 2021-09-26 Based Selection International Implementation 3=171.90KM FC010 / Supervision Quality And Cost- Open - Under consultant No 4. Lot IBRD / 87050 Post 0.00 2018-03-13 2018-08-13 2019-02-26 2019-04-27 2019-06-26 2019-08-17 2019-09-27 2021-09-26 Based Selection International Implementation 4=86.4KM FC011 / Supervision Quality And Cost- Open - Under consultant No 5, Lot IBRD / 87050 Post 0.00 2018-03-13 2018-08-13 2019-02-26 2019-04-27 2019-06-26 2019-08-17 2019-09-27 2021-09-26 Based Selection International Implementation 5=131.20KM FC012 / Supervision Quality And Cost- Open - Under consultant No 6, Lot IBRD / 87050 Post 0.00 2018-03-13 2018-08-13 2019-02-26 2019-04-27 2019-06-26 2019-08-17 2019-09-27 2021-09-26 Based Selection International Implementation 6=140.1KM FC001 / Design consultant No 1, Lot 1=144.9KM , Dar Least Cost IBRD / 87050 Post Open - National 262,000.00 Signed 2018-03-15 2018-03-15 2018-06-13 2018-09-05 2018-09-19 2018-10-16 2019-01-09 2019-07-01 El Handassah, Nazih Taleb Selection & Partners. FC002 / Design consultant No 2, Lot 2=165KM, Dar El Least Cost IBRD / 87050 Post Open - National 264,125.00 Signed 2018-03-15 2018-03-15 2018-06-13 2018-09-05 2018-09-19 2018-10-16 2019-01-09 2019-07-01 Handassah Nazih Taleb & Selection Partners INDIVIDUAL CONSULTANTS Page 2