The World Bank Implementation Status & Results Report Somalia - Water for Agro-pastoral Productivity and Resilience (P167826) Somalia - Water for Agro-pastoral Productivity and Resilience (P167826) AFRICA | Somalia | Water Global Practice | IBRD/IDA | Investment Project Financing | FY 2020 | Seq No: 1 | ARCHIVED on 06-Sep-2019 | ISR38319 | Implementing Agencies: Federal Republic of Somalia, Participating States and Somaliland Key Dates Key Project Dates Bank Approval Date: 01-Jul-2019 Effectiveness Date: Planned Mid Term Review Date: 16-Aug-2021 Actual Mid-Term Review Date: Original Closing Date: 28-Feb-2023 Revised Closing Date: 28-Feb-2023 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) Develop water and agricultural services among agro-pastoralist communities in dryland areas of Somalia. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Component 1: Support the Development of Multiple Use Water Sources:(Cost $15.00 M) Component 2. Institutional and Capacity Development:(Cost $6.00 M) Component 3: Supporting Sustainable Land Management and Livelihoods Development Around Water Points:(Cost $9.50 M) Component 4: Project Management, M & E, Knowledge Management and Learning:(Cost $9.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO -- Moderately Satisfactory Overall Implementation Progress (IP) -- Moderately Satisfactory Overall Risk Rating -- High Implementation Status and Key Decisions The project is yet to be declared effective. 9/6/2019 Page 1 of 5 The World Bank Implementation Status & Results Report Somalia - Water for Agro-pastoral Productivity and Resilience (P167826) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance High -- High Macroeconomic Substantial -- Substantial Sector Strategies and Policies Substantial -- Substantial Technical Design of Project or Program High -- High Institutional Capacity for Implementation and Sustainability High -- High Fiduciary High -- High Environment and Social Substantial -- Substantial Stakeholders Substantial -- Substantial Other Substantial -- Substantial Overall High -- High Results PDO Indicators by Objectives / Outcomes People provided with access to improved water sources under the project, of which 50 percent are fem IN00737030 ►People provided with access to improved water sources under the project, of which 50 percent are female (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 250,000.00 Date 01-Oct-2018 -- 04-Sep-2019 30-Dec-2022 This indicator measures the cumulative number of people who benefited from improved water supply Comments: services constructed under the project. Farmers/clients (number) adopting improved technology, share of which are female (percent) IN00737031 ►Farmers/clients (number) adopting improved technology, share of which are female (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 110,000.00 Date 01-Oct-2018 -- 04-Sep-2019 30-Dec-2022 The indicator evaluates the good agricultural practice transferred during technical assistance and number Comments: of the farmers who adopt it. 9/6/2019 Page 2 of 5 The World Bank Implementation Status & Results Report Somalia - Water for Agro-pastoral Productivity and Resilience (P167826) Target beneficiaries satisfied with project investments (percentage). IN00737032 ►Target beneficiaries satisfied with project investments. (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 60.00 Date 01-Oct-2018 -- 04-Sep-2019 30-Dec-2022 This indicator measures the percentage of clients who expressed satisfaction with the agricultural and rural advisory services provided in the project areas based on formal or informal surveys. The informal Comments: survey will be part of the project monitoring and the formal survey will be conducted during the project Mid term review. The feed back from these surveys will be used to update the design and refine the packages of the Agricultural advisory services. Overall Comments PDO There are no changes on the project development objective indicators from the base line as all activities under the project are not started yet. Intermediate Results Indicators by Components Component 1. Support the development of multiple use water sources IN00737033 ►Improved community water points constructed under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 75.00 Date 25-Sep-2018 -- 04-Sep-2019 30-Jun-2023 A community water point includes small sand and sub-surface dams in dry river beds (wadis), surface Comments: water storage infrastructure (e.g. berkads and hafir dams), area infiltration interventions such as semi- circular bunds or soil bunds, rock catchments and Shallow and boreholes for groundwater extraction. IN00737036 ►Improved community water points rehabilitated under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 25.00 Date 25-Sep-2018 -- 04-Sep-2019 30-Dec-2022 Community water points constructed before the project and damaged or out of service, rehabilitated under Comments: the project. This indicator measures those rehabilitation works. Component 2. Institutional and Capacity Development IN00737034 ►Number of PIUs established under the project and functioning, and of which female staff is 50 percent (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 9/6/2019 Page 3 of 5 The World Bank Implementation Status & Results Report Somalia - Water for Agro-pastoral Productivity and Resilience (P167826) Value 0.00 -- 0.00 4.00 Date 25-Sep-2018 -- 04-Sep-2019 30-Jun-2023 PIUs established and leading project interventions in surface and/or ground water development and Comments: management, agriculture and livestock IN00737037 ►Number of Community Management Systems Established (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 75.00 Date 25-Sep-2018 -- 04-Sep-2019 30-Jun-2023 This indicator will measure the existence and quality of organizations at the community level to organize demand for investments, set priorities, and oversee implementation with the community. This includes having VDCs with at least 40 percent of leadership roles being women. Based on a set of criteria, each Comments: village will be assessed at mid-term and end of project to assess the community organizations on a scale of A, B, C, or D with A being the strongest. Those communities with a A and B rating will be considered a good functioning community management system. IN00737038 ►Number of PIU members trained disaggregated by (male/female) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 40.00 Date 25-Sep-2018 -- 04-Sep-2019 30-Jun-2023 The number of project staffs working at federal and member state levels trained to implement the project. Comments: The training includes initial and periodic refresher and on the job trainings. Component 3. Supporting Sustainable Land Management and Livelihoods Development Around Water Points IN00737035 ►Farmers/clients reached with Agricutural serivices, of which women (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 80.00 Date 29-Oct-2018 -- 04-Sep-2019 30-Dec-2022 Overall Comments IR There are no changes on the project intermediate results indicators from the base line as all activities under the project are not started yet. Data on Financial Performance Disbursements (by loan) 9/6/2019 Page 4 of 5 The World Bank Implementation Status & Results Report Somalia - Water for Agro-pastoral Productivity and Resilience (P167826) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed Not P167826 IDA-D4970 USD 42.00 42.00 0.00 0.00 41.98 0% Effective Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date Not P167826 IDA-D4970 01-Jul-2019 -- -- 28-Feb-2023 28-Feb-2023 Effective Cumulative Disbursements Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 9/6/2019 Page 5 of 5