Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan [Original: December 2007]: Revision 15 of Updated Procurement Plan, June 2010] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by July 9, 2010 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of 82 5 No Prior the ICB (Works) Summary of 43.77 15 No Prior the ICB (Goods) Summary of 64.53 18 No Post 1st the NCB contract (Works) for Prior Review Summary of 1.86 4 No Post 1st the NCB contract (Goods) for Prior Review Summary of 0.45 1 No Prior the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise July 9, 2010 entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 4.17 7 Prior number of contracts that will be let under QCBS Summary of 0.83 1 Prior CQS number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Senegal : Senegal Tourism and Enterprise Development Project PLAN General Information Country: Senegal Bank’s Approval Date of the Original Procurement Plan: 2017-08-14 2019-10-09 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P146469 GPN Date: Project Name: Senegal Tourism and Enterprise Development Project Loan / Credit No: IDA / 60190, IDA / Q9590, IDA / Q9940 Executing Agency(ies): WORKS AND INVESTMENTS AGENCY WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual T1 / Sélection d'une entreprise pour la réalisation des travaux physiques de Sustainable Tourism Open - Single Stage - One protection, de restauration et IDA / Q9590 A priori Appel d'offres 35,800,000.00 29,833,700.01 Signé 2018-09-07 2018-10-07 2018-11-27 2018-12-27 2019-01-31 2021-01-20 Development International Envelope d'entretien des plages de la station balnéaire de Saly Portudal T10 / sélection d'une entreprise pour la réalisation des Travaux physiques de Sustainable Tourism Open - Single Stage - One IDA / Q9940 A posteriori Appel d'offres 3,240,000.00 0.00 Annulé 2018-05-16 2018-05-21 2018-07-02 2018-08-01 2018-09-05 2019-03-04 protection et entretien des Development International Envelope plages de Saly Niakh Niakhal GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual F5 / Acquisition de goodies, Supporting Enterprise Single Stage - One En attente matériels de communication IDA / 60190 A posteriori Demande de prix Limited 70,000.00 0.00 2018-02-27 2018-04-24 2018-07-23 Creation and Growth Envelope d'exécution dans le cadre du BPC F2 / Acquisition de produits d'entretien pour les Single Stage - One En attente IDA / 60190 Project implementation A posteriori Demande de prix Limited 10,000.00 0.00 2017-11-27 2018-01-19 2018-03-20 locaux devant abriter l'Unité Envelope d'exécution de Gestion du Projet F1 / Acquisition de Single Stage - One En attente IDA / Q9590 Project implementation A posteriori Demande de prix Limited 30,000.00 0.00 2017-12-04 2018-01-30 2018-03-31 fournitures de bureaux Envelope d'exécution F8 / Acquisition de Supporting Enterprise Single Stage - One Matériels et consommables IDA / 60190 A posteriori Appel d'offres Open - National 210,000.00 0.00 Annulé 2018-01-30 2018-02-04 2018-03-18 2018-04-17 2018-05-22 2018-07-21 Creation and Growth Envelope informatiques F20 / Acquisition de Single Stage - One En attente matériels de vidéo-conférence IDA / 60190 Project implementation A posteriori Demande de prix Limited 21,000.00 0.00 2019-03-30 2019-05-25 2019-11-21 Envelope d'exécution au profit de l'UGP F11 / Acquisition d'un Single Stage - One En attente logiciel de gestion de projet IDA / 60190 Project implementation A posteriori Demande de prix Limited 64,000.00 0.00 2019-01-01 2019-02-26 2019-08-25 Envelope d'exécution pour l'UGP Page 1 F12 / Solution matérielle et équipement complémentaire du Datacenter DGID (Lot1: Fourniture & install. de modules onduleurs, câbles Supporting Enterprise Single Stage - One IDA / 60190 A posteriori Appel d'offres Open - National 550,000.00 429,630.29 Signé 2018-12-21 2018-12-26 2019-02-06 2019-03-08 2019-04-12 2019-10-09 réseau- lot 2: Fourniture & Creation and Growth Envelope install d'une solution dédiée à SIGTAS et ETAX et mise à niveau de la plateforme virtuelle serveurs) F15 / Acquisition d'une Single Stage - One En attente IDA / 60190 Project implementation A posteriori Demande de prix Limited 40,000.00 0.00 2019-06-08 2019-08-04 2020-01-31 ERP pour l'UGP Envelope d'exécution F3 / Acquisition de Supporting Enterprise Single Stage - One IDA / 60190 A posteriori Appel d'offres Open - National 154,000.00 0.00 Annulé 2018-12-14 2018-12-19 2019-01-30 2019-03-01 2019-04-05 2019-10-02 véhicules en deux (02) lots Creation and Growth Envelope F9 / Acquisition de Supporting Enterprise Single Stage - One En cours mobiliers de bureau en trois IDA / 60190 A posteriori Demande de prix Limited 24,500.00 0.00 2019-06-15 2019-08-10 2020-02-06 Creation and Growth Envelope d'exécution lots F4 / Réalisation de supports de communication Sustainable Tourism Single Stage - One En cours (support promotionel, IDA / 60190 A posteriori Demande de prix Limited 24,200.00 0.00 2019-08-10 2019-10-05 2020-04-02 Development Envelope d'exécution plaquettes…) au profit de l'ASPT F17 / Acquisition de Supporting Enterprise Single Stage - One En attente matériels et consommables IDA / 60190 A posteriori Demande de prix Limited 30,900.00 0.00 2019-09-15 2019-11-10 2020-05-08 Creation and Growth Envelope d'exécution informatiques en 4 lots F30 / Réalisation et Sustainable Tourism Single Stage - One En attente installation de panneaux IDA / 60190 A posteriori Demande de prix Limited 80,800.00 0.00 2019-10-27 2019-12-22 2020-06-19 Development Envelope d'exécution signalétiques F7 / Acquisition de véhicules en deux (02) lots pour DEA/APIX : lot 1 Supporting Enterprise Single Stage - One En attente IDA / 60190 A posteriori Appel d'offres Open - National 143,000.00 0.00 2019-07-10 2019-07-15 2019-08-26 2019-09-25 2019-10-30 2020-01-28 (Deux véhicules : modèle 1 ) Creation and Growth Envelope d'exécution et FFP/ADEMPE: lot 2 (1 véhicule: modèle 2) F10 / Acquisition de Sustainable Tourism Single Stage - One matériels audiovisuels pour IDA / 60190 A posteriori Demande de prix Limited 78,000.00 0.00 Annulé 2018-11-20 2019-01-15 2019-07-14 Development Envelope le Ministère du Tourisme S27 / Conception et installation de panneaux Sustainable Tourism Single Stage - One signalétiques dans les sites IDA / 60190 A posteriori Demande de prix Limited 80,000.00 0.00 Annulé 2019-11-05 2019-12-31 2020-06-28 Development Envelope et circuits touristiques au profit du MTTA NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual S6 / Réalisation de reportages vidéo sur les Supporting Enterprise Single Stage - One En attente IDA / 60190 A posteriori Demande de prix Limited 60,000.00 0.00 2017-09-27 2017-11-22 2019-11-12 projets et le concours de Creation and Growth Envelope d'exécution business plans Page 2 S1 / Sélection d'une agence de communication pour la Single Stage - One En cours Cérémonie de lancement du IDA / Q9590 Project implementation A posteriori Demande de prix Limited 40,000.00 0.00 2017-11-20 2018-01-15 2018-03-16 Envelope d'exécution projet de protection et restauration des plages S4 / Sélection d'une agence chargée de de la communication Fonds à Frais Partagé (LOT1) et de Supporting Enterprise Single Stage - One En attente IDA / 60190 A posteriori Appel d'offres Open - National 445,000.00 0.00 2017-11-03 2017-11-08 2017-12-20 2018-01-19 2018-02-23 2020-02-13 la communication du Creation and Growth Envelope d'exécution concours de business plans et de cérémonie de remise des prix (LOT2) S7 / Sélection d'une agence chargée de de la Supporting Enterprise Single Stage - One IDA / 60190 A posteriori Appel d'offres Open - National 225,000.00 0.00 Annulé 2017-09-15 2017-09-20 2017-11-02 2017-12-02 2018-01-06 2019-06-30 communication Fonds à Creation and Growth Envelope Frais Partagés S20 / Campagne d'affichage pour la deuxième édition du Supporting Enterprise Single Stage - One En attente IDA / 60190 A posteriori Demande de prix Limited 90,000.00 0.00 2018-02-28 2018-04-25 2018-10-22 concours national de Creation and Growth Envelope d'exécution business plan S21 / Acquisition de Single Stage - One En attente supports de promotion pour IDA / 60190 Project implementation A posteriori Demande de prix Limited 33,000.00 0.00 2018-02-20 2018-04-17 2018-06-16 Envelope d'exécution le Projet S30 / SÉLECTION D'UNE AGENCE CHARGÉE DE LA COMMUNICATION DU CONCOURS DE BUSINESS Supporting Enterprise Single Stage - One En cours IDA / 60190 A posteriori Appel d'offres Open - National 225,000.00 0.00 2018-07-02 2018-07-07 2018-08-18 2018-09-17 2018-10-22 2020-04-14 PLANS ET DE Creation and Growth Envelope d'exécution L'ORGANISATION DE LA CÉRÉMONIE DE REMISE DES PRIX ( RELANCE) S28 / Sélection d'une agence de Voyage et de Sustainable Tourism Single Stage - One En cours Tourisme pour l'organisation IDA / 60190 A posteriori Demande de prix Limited 80,000.00 0.00 2018-10-31 2018-12-26 2019-06-24 Development Envelope d'exécution d'Eductours combinés à un voyage de presse S12 / Sélection d'une agence pour la réalisation de Sustainable Tourism Single Stage - One En attente supports de communication IDA / 60190 A posteriori Demande de prix Limited 96,000.00 0.00 2018-10-30 2018-12-25 2019-06-23 Development Envelope d'exécution pour le Ministère du Tourisme S26 / Élaboration de supports audio-visuels pour Supporting Enterprise Single Stage - One En attente les projets des éditions IDA / 60190 A posteriori Demande de prix Limited 16,000.00 0.00 2018-11-12 2019-01-07 2019-07-06 Creation and Growth Envelope d'exécution précédentes du Concours Business plan S3 / Création et production des supports de communication et Réalisation Single Stage - One En attente IDA / 60190 Project implementation A posteriori Demande de prix Limited 47,000.00 0.00 2019-03-03 2019-04-28 2019-10-25 de publi-reportages pour Envelope d'exécution l'Unité de Gestion du Projet en deux (02) lots S25 / Création de banque d'images et Conception de films et vidéos promotionnels Sustainable Tourism Single Stage - One En attente IDA / 60190 A posteriori Appel d'offres Open - National 241,000.00 0.00 2019-01-30 2019-02-04 2019-03-18 2019-04-17 2019-05-22 2019-11-18 au profit de la destination Development Envelope d'exécution en deux (02) lots pour le Ministère du Tourisme Page 3 S13 / Sélection d'une agence de communication Supporting Enterprise Single Stage - One En cours IDA / 60190 A posteriori Demande de prix Limited 73,000.00 0.00 2018-11-03 2018-12-29 2019-06-27 pour l'organisation du forum Creation and Growth Envelope d'exécution de la PME S15 / Selection d'une agence de communication Supporting Enterprise Single Stage - One En attente pour la vulgarisation des IDA / 60190 A posteriori Demande de prix Limited 73,000.00 0.00 2018-12-05 2019-01-30 2019-07-29 Creation and Growth Envelope d'exécution activités du Tribunal de Commerce de Dakar S14 / Renouvellement du Supporting Enterprise Single Stage - One En cours système de sécurité réseau IDA / 60190 A posteriori Demande de prix Limited 97,000.00 0.00 2019-01-01 2019-02-26 2019-08-25 Creation and Growth Envelope d'exécution du Datacenter de la DGID S18 / Sélection d'un prestataire en charge de la Supporting Enterprise Single Stage - One En attente IDA / 60190 A posteriori Demande de prix Limited 74,000.00 0.00 2019-05-05 2019-06-30 2019-12-27 notation des candidats du Creation and Growth Envelope d'exécution Concours Business plan S16 / Organisation atelier sur l'entrepreneuriat et Supporting Enterprise Single Stage - One En cours IDA / 60190 A posteriori Demande de prix Limited 37,500.00 0.00 2019-04-20 2019-06-15 2019-12-12 organisation des CRD (Pré- Creation and Growth Envelope d'exécution campagne) S29 / Sélection d'une agence chargée d'accompagner le Ministère Sustainable Tourism Open - Single Stage - One IDA / 60190 A posteriori Appel d'offres 323,283.00 0.00 Annulé 2018-10-17 2018-10-22 2018-12-03 2019-01-02 2019-02-06 2019-08-05 du Tourisme pour Development International Envelope l'organisation de TERANGA DAYS (workshop) S17 / Sélection d'un prestataire pour la formation Supporting Enterprise Single Stage - One En attente IDA / 60190 A posteriori Demande de prix Limited 89,000.00 0.00 2019-07-15 2019-09-09 2020-03-07 des candidats du concours Creation and Growth Envelope d'exécution national de plan d'affaires S22 / Sélection d'une agence chargée d'accompagner le Ministère Sustainable Tourism Single Stage - One En attente du Tourisme pour IDA / 60190 A posteriori Appel d'offres Open - National 162,000.00 0.00 2019-10-24 2019-10-29 2019-12-10 2020-01-09 2020-02-13 2020-08-11 Development Envelope d'exécution l'organisation de TERANGA DAYS en France, Belgique et Espagne S10 / Conception et Sustainable Tourism Single Stage - One installation des signalétiques IDA / 60190 A posteriori Appel d'offres Open - National 200,000.00 0.00 Annulé 2017-10-12 2017-10-17 2017-11-28 2017-12-28 2018-02-01 2018-04-02 Development Envelope dans les sites touristiques S9 / Conception et impression de manuels de Sustainable Tourism Single Stage - One IDA / 60190 A posteriori Appel d'offres Open - National 90,000.00 0.00 Annulé 2018-01-12 2018-01-17 2018-02-28 2018-03-30 2018-05-04 2018-09-01 vente à destination des Development Envelope professionnels du Tourisme F21 / CAMPAGNE DE COMMUNICATION POUR LA DESTINATION Sustainable Tourism Single Stage - One IDA / 60190 A posteriori Appel d'offres Open - National 200,000.00 0.00 Annulé 2018-02-23 2018-02-28 2018-04-11 2018-05-11 2018-06-15 2018-12-12 SENEGAL SUR SES Development Envelope MARCHES PRIORITAIRES EN EUROPE S11 / Sélection d'un cabinet pour l'organisation d'ateliers Supporting Enterprise Single Stage - One d'informations et de IDA / 60190 A posteriori Demande de prix Limited 70,000.00 0.00 Annulé 2018-01-10 2018-03-07 2019-03-03 Creation and Growth Envelope communication sur l'entreprenariat S5 / Location de panneaux Supporting Enterprise Single Stage - One IDA / 60190 A posteriori Appel d'offres Open - National 180,000.00 0.00 Annulé 2017-12-20 2017-12-25 2018-02-05 2018-03-07 2018-04-11 2020-03-31 numériques et traditionnels Creation and Growth Envelope Page 4 S32 / Sélection d'une agence chargée d'accompagner le Ministère Sustainable Tourism Single Stage - One du Tourisme pour IDA / 60190 A posteriori Demande de prix Limited 78,400.00 0.00 Annulé 2019-06-22 2019-08-17 2019-10-16 Development Envelope l'organisation de TERANGA DAYS en France, Belgique et Espagne S33 / Sélection de prestataires pour l’animation Supporting Enterprise Single Stage - One d’une série d’ateliers sur les IDA / 60190 A posteriori Appel d'offres Open - National 113,000.00 0.00 Annulé 2019-10-15 2019-10-20 2019-12-01 2019-12-31 2020-02-04 2020-08-02 Creation and Growth Envelope techniques du commerce international CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C1 / Recrutement d'un Sélection fondée cabinet en charge de la IDA / 60190 Project implementation A posteriori sur la qualité et Open - National 240,000.00 130,608.46 Signé 2017-06-22 2017-07-12 2017-08-25 2017-09-22 2017-10-22 2017-11-26 2017-12-31 2020-09-16 facilitation et de la le coût communication sociales C2 / Sélection d'un cabinet Sélection fondée pour l'Etude d'impact Sustainable Tourism sur les En attente IDA / 60190 A posteriori Open - National 120,000.00 0.00 2018-01-16 2018-02-06 2018-03-22 2018-04-21 2018-05-26 2018-08-24 environnemental et social Development qualifications des d'exécution pour le dragage consultants Sélection fondée C8 / Sélection d'un cabinet IDA / 60190 Project implementation A priori sur la qualité et Open - National 60,000.00 0.00 Annulé 2017-10-12 2017-11-02 2017-12-16 2018-01-13 2018-02-12 2018-03-19 2018-04-23 2021-04-07 chargé de l'Audit financier le coût C9 / Etat des lieux sur l'environnement ces affaires Sélection fondée locales (cartographie sur les En attente IDA / 60190 Project implementation A posteriori Open - National 60,000.00 0.00 2017-10-18 2017-11-08 2017-12-22 2018-01-21 2018-02-25 2018-05-26 investissements privés qualifications des d'exécution tourisme...) à Saly, consultants Ziguinchor et Saint Louis F13 / Recrutement d'un Sélection fondée Supporting Enterprise Open - assistant technique (firme) IDA / 60190 A posteriori sur la qualité et 200,000.00 0.00 Annulé 2017-10-31 2017-11-21 2018-01-01 2018-01-29 2018-02-28 2018-04-04 2018-05-09 2019-05-09 Creation and Growth International internationale : télépaiement le coût C32 / Mise à jour du logiciel de gestion des Supporting Enterprise Sélection au IDA / 60190 A posteriori Open - National 40,000.00 40,040.65 Signé 2017-09-27 2017-10-18 2017-12-01 2017-12-29 2018-01-28 2018-03-04 2018-04-08 2018-10-05 projets et du système de Creation and Growth moindre coût suivi évaluation C25 / Sélection d'une entité Sélection fondée Supporting Enterprise en charge de la formation et IDA / 60190 A posteriori sur la qualité et Open - National 350,000.00 0.00 Annulé 2017-11-07 2017-11-28 2018-01-11 2018-02-08 2018-03-10 2018-04-14 2018-05-19 2020-05-08 Creation and Growth de la notation des candidats le coût C46 / SELECTION D'UN CABINET CHARGE DE L'ETUDE D'IMPACT Sélection fondée Sustainable Tourism En cours ENVIRONNEMENTAL ET IDA / Q9940 A posteriori sur la qualité et Open - National 162,000.00 179,667.89 2017-09-20 2017-10-11 2017-11-24 2017-12-22 2018-01-21 2018-02-25 2018-04-01 2018-06-30 Development d'exécution SOCIAL DU DRAGAGE le coût POUR LA RESTAURATION DES PLAGES DE SALY C45 / Sélection d'un cabinet pour une mission Sélection fondée Sustainable Tourism Open - d'assistance technique des IDA / Q9940 A posteriori sur la qualité et 325,000.00 0.00 Annulé 2017-10-04 2017-10-25 2017-12-08 2018-01-05 2018-02-04 2018-03-11 2018-04-15 2019-04-15 Development International travaux de Saly Niakh le coût Niakhal Page 5 C47 / Sélection d'un cabinet pour la réalisation Sélection fondée de l'étude d'impact Sustainable Tourism sur les En cours IDA / Q9940 A posteriori Open - National 48,500.00 0.00 2017-10-27 2017-11-17 2017-12-31 2018-01-30 2018-03-06 2018-06-04 environnemental et social Development qualifications des d'exécution pour les travaux de Saly consultants Niakh Niakhal C35 / Etudes de faisabilité Sélection fondée Sustainable Tourism Open - En cours des projets de Kafountine- IDA / 60190 A posteriori sur la qualité et 400,000.00 299,574.58 2017-11-23 2017-12-14 2018-01-27 2018-02-24 2018-03-26 2018-04-30 2018-06-04 2018-09-02 Development International d'exécution Abéné le coût C63 / Sélection d'un Sélection fondée En attente cabinet chargé de l'Audit IDA / 60190 Project implementation A posteriori sur la qualité et Open - National 60,000.00 0.00 2018-10-09 2018-10-30 2018-12-13 2019-01-10 2019-02-09 2019-03-16 2019-04-20 2020-04-19 d'exécution financier le coût C66 / Sélection d'un bureau de contrôle technique pour Sélection fondée les ouvrages fixes des Sustainable Tourism sur les Open - En cours IDA / 60190 A posteriori 242,000.00 0.00 2018-09-12 2018-10-03 2018-11-16 2018-12-16 2019-01-20 2019-07-19 travaux physiques de Development qualifications des International d'exécution protection restauration et consultants entretien des plages de Saly C16 / Sélection d'un bureau d'études pour le diagnostic sur l'état des locaux, les études architecturales et d'aménagement et Supporting Enterprise Sélection au En attente IDA / 60190 A posteriori Open - National 135,000.00 0.00 2019-05-28 2019-06-18 2019-07-31 2019-08-28 2019-09-27 2019-11-01 2019-12-06 2020-06-03 supervision des travaux de Creation and Growth moindre coût d'exécution réhabilitation des locaux abritant les plateformes de Saly et Ziguinchor (en deux missions) Sélection fondée C10 / Elaboration du Plan sur les IDA / 60190 Project implementation A posteriori Open - National 20,000.00 0.00 Annulé 2018-01-17 2018-02-07 2018-04-29 2018-05-29 2018-07-03 2018-10-01 de formation du projet qualifications des consultants Sélection fondée C5 / Sélection d'un cabinet sur les pour l'Audit technique pour IDA / 60190 Project implementation A posteriori Open - National 90,000.00 0.00 Annulé 2017-11-20 2017-12-12 2018-01-25 2018-02-24 2018-03-31 2018-06-29 qualifications des les ouvrages consultants C50 / Etude sur le mode Sélection fondée de gestion, entretien et Sustainable Tourism sur les En cours maintenance des ouvrages IDA / 60190 A posteriori Open - National 24,200.00 0.00 2019-06-03 2019-06-24 2019-08-07 2019-09-06 2019-10-11 2020-04-08 Development qualifications des d'exécution réalisés à Saly dans le consultants cadre du PDTE C15 / Sélection d'un bureau d'études pour le diagnostic sur l'état des locaux, les Sélection fondée études architecturales et Supporting Enterprise sur les En attente d'aménagement et IDA / 60190 A posteriori Open - National 35,500.00 0.00 2019-07-25 2019-08-15 2019-09-28 2019-10-28 2019-12-02 2020-05-30 Creation and Growth qualifications des d'exécution supervision des travaux de consultants réhabilitation des locaux abritant la plateforme de Saint Louis C69 / Etudes de faisabilité Sélection fondée et d'exécution et mise à Sustainable Tourism Open - IDA / 60190 A posteriori sur la qualité et 484,000.00 0.00 Annulé 2018-12-20 2019-01-10 2019-02-23 2019-03-23 2019-04-22 2019-05-27 2019-07-01 2020-06-30 niveau du pôle touristique Development International le coût du Lac Rose C34 / Elaboration d'un Sélection fondée master plan d'aménagement Sustainable Tourism Open - IDA / 60190 A posteriori sur la qualité et 500,000.00 0.00 Annulé 2017-09-11 2017-10-02 2017-11-15 2017-12-13 2018-01-12 2018-02-16 2018-03-23 2018-09-19 touristique de la petite côte Development International le coût et du littoral sud Page 6 C33 / Sélection d'un Sélection fondée cabinet pour le renforcement Supporting Enterprise sur les IDA / 60190 A posteriori Open - National 46,500.00 0.00 Annulé 2017-11-17 2017-12-12 2018-02-15 2018-02-25 2018-03-28 2020-03-17 de capacités des PME en Creation and Growth qualifications des matière d'exportation. consultants C40 / Etude diagnostic et Sélection fondée de mise à niveau Sustainable Tourism sur les IDA / 60190 A posteriori Open - National 70,000.00 0.00 Annulé 2018-01-19 2018-01-19 2018-01-19 2018-01-19 2018-02-09 2018-05-10 environnemental au profit de Development qualifications des la SAPCO consultants C76 / Coaching des Sélection fondée lauréats du Concours Supporting Enterprise En attente IDA / 60190 A posteriori sur la qualité et Open - National 197,000.00 0.00 2019-11-04 2019-11-25 2020-01-08 2020-02-05 2020-03-06 2020-04-10 2020-05-15 2021-05-15 national de Plan d'affaires - Creation and Growth d'exécution le coût Seconde édition S19 / Sélection d'un Consultant pour l'animation Sélection fondée d'une série d'ateliers de Supporting Enterprise sur les En attente IDA / 60190 A posteriori Open - National 115,000.00 0.00 2019-11-20 2019-12-11 2020-01-24 2020-02-23 2020-03-29 2020-09-25 formation sur les techniques Creation and Growth qualifications des d'exécution du Commerce international consultants pour le FFP. F14 / Services de consultant pour l'étude Sélection fondée filières et investissement, et Supporting Enterprise sur les élaboration du profil IDA / 60190 A posteriori Open - National 180,000.00 0.00 Annulé 2017-11-23 2017-12-14 2018-01-29 2018-02-28 2018-04-04 2020-04-03 Creation and Growth qualifications des d'attractivité des régions et consultants de la cartographie des produits exports INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C4 / Recrutement en En cours Spécialiste en passation de IDA / 60190 Project implementation A priori Individuel Open 108,000.00 0.00 2017-06-27 2017-08-15 2017-09-05 2017-10-10 2018-04-08 d'exécution marchés C7 / Recrutement d'un En cours spécialiste en ingénierie IDA / 60190 Project implementation A priori Individuel Limited 72,000.00 0.00 2017-07-13 2017-07-18 2017-08-08 2017-09-12 2020-08-27 d'exécution sociale C11 / Audit technique des IDA / 60190 Project implementation A priori Individuel Limited 20,000.00 0.00 Annulé 2018-04-30 2018-05-05 2018-05-26 2018-06-30 2018-09-28 bénéficiaires du FFP et BPC C37 / Recrutement d'un Sustainable Tourism IDA / 60190 A priori Individuel Open 180,000.00 0.00 Annulé 2017-06-22 2017-08-10 2017-08-31 2017-10-05 2022-09-09 PMO (Project Mgmt Offcer). Development C6 / Sélection d'un Chargé de mission Environnement IDA / 60190 Project implementation A priori Individuel Limited 72,000.00 0.00 Annulé 2017-10-28 2017-11-02 2017-11-23 2017-12-28 2020-12-12 pour le fonds à frais partagés et l'ADEPME C27 / Sélection d'un Sélection de cabinet pour la mise à Supporting Enterprise IDA / 60190 A priori consultants par Direct 190,000.00 0.00 Annulé 2017-11-23 2017-12-03 2018-02-06 2020-01-27 niveau et maintenance de la Creation and Growth entente directe plateforme IT C39 / Recrutement d'un Sustainable Tourism expert environnementaliste IDA / 60190 A priori Individuel Open 108,000.00 0.00 Annulé 2017-12-20 2018-02-07 2018-02-28 2018-04-04 2023-03-09 Development au profit de la SAPCO Page 7 C30 / Recrutement d'un Supporting Enterprise expert international pour le IDA / 60190 A priori Individuel Open 120,000.00 0.00 Annulé 2017-10-16 2017-12-15 2017-12-25 2018-01-25 2019-01-25 Creation and Growth FFP C3 / Recrutement Ingénieur IDA / 60190 Project implementation A priori Individuel Open 216,000.00 0.00 Annulé 2017-10-03 2017-11-21 2017-12-12 2018-01-16 2020-12-31 côtier Senior C48 / RECRUTEMENT D'UN COORDONNATEUR Sélection de POUR LE PROJET DE IDA / Q9940 Project implementation A priori consultants par Direct 312,000.00 0.00 Annulé 2017-09-15 2017-09-25 2017-11-29 2022-11-03 DÉVELOPPEMENT DU entente directe TOURISME ET DES ENTREPRISES REGC1 / MISSION D'ASSISTANCE A MAITRISE D'OEUVRE DANS LE CADRE DE LA Sélection de REALISATION DES Sustainable Tourism En cours IDA / Q9940 A priori consultants par Direct 1,800,000.00 0.00 2015-01-19 2015-01-27 2016-05-07 2018-04-27 TRAVAUX PHYSIQUES DE Development d'examen entente directe RESTAURATION, PROTECTION ET ENTRETIEN DES PLAGES DE SALY C43 / Enquêtes statistiques Sélection de Sustainable Tourism En cours sur l'offre et la demande IDA / 60190 A posteriori consultants par Direct 34,000.00 0.00 2017-10-27 2017-11-04 2018-01-08 2018-02-07 Development d'exécution touristiques 2016 et 2017 entente directe C55 / QUANTIFICATION ET CARACTERISATION PHYSICO CHIMIQUE ET BACTERIOLOGIQUE DES SEDIMENTS, DES Sélection de HABITATS ET DES Sustainable Tourism En cours IDA / 60190 A posteriori consultants par Direct 65,000.00 0.00 2017-12-27 2018-03-12 2018-05-16 2018-05-25 ESPECES MARINES AU Development d'exécution entente directe NIVEAU DES ZONES DE DRAGAGE ET D'AMENAGEMENT DES OUVRAGES DE LA ZONE DE SALY C57 / Recrutement d'un expert national en Supporting Enterprise En cours IDA / 60190 A posteriori Individuel Open 54,000.00 0.00 2018-01-30 2018-03-20 2018-04-10 2018-05-15 2019-05-10 développement des Creation and Growth d'exécution exportations C56 / Recrutement d'un Sustainable Tourism assistant technique en génie IDA / 60190 A posteriori Individuel Open 216,000.00 106,305.99 Signé 2018-01-30 2018-03-20 2018-04-10 2018-05-15 2018-11-11 Development côtier C58 / Recrutement d'un En attente IDA / 60190 Project implementation A posteriori Individuel Open 180,000.00 0.00 2018-01-31 2018-03-21 2018-04-11 2018-05-16 2018-11-12 PMO (Project Mgmt Officer) d'exécution C60 / RECRUTEMENT D'UN COORDONNATEUR Sélection de POUR LE PROJET DE En attente IDA / 60190 Project implementation A posteriori consultants par Direct 312,000.00 0.00 2018-02-15 2018-02-25 2018-05-01 2018-10-28 DÉVELOPPEMENT DU d'exécution entente directe TOURISME ET DES ENTREPRISES C61 / Sélection d'un Sélection de cabinet pour la mise à Supporting Enterprise IDA / 60190 A posteriori consultants par Direct 190,000.00 81,417.20 Signé 2018-03-30 2018-04-09 2018-06-13 2018-12-10 niveau et maintenance de la Creation and Growth entente directe plateforme IT C62 / Audit technique des En attente IDA / 60190 Project implementation A posteriori Individuel Limited 20,000.00 0.00 2018-06-22 2018-06-27 2018-07-18 2018-08-22 2019-02-18 bénéficiaires du FFP et BPC d'exécution Page 8 C64 / Sélection d'un Expert Sustainable Tourism En attente Environnementaliste au IDA / 60190 A posteriori Individuel Open 108,000.00 0.00 2018-03-20 2018-05-08 2018-05-29 2018-07-03 2018-12-30 Development d'exécution profit de la SAPCO C65 / Recrutement d'un Supporting Enterprise expert international pour le IDA / 60190 A posteriori Individuel Open 120,000.00 173,640.00 Signé 2018-02-28 2018-04-18 2018-05-09 2018-06-13 2018-12-10 Creation and Growth FFP C70 / Sélection d'un Project Manager Office Sustainable Tourism En attente IDA / 60190 A posteriori Individuel Limited 192,000.00 0.00 2018-04-20 2018-04-25 2018-05-05 2018-05-15 2019-05-15 (PMO) pour le Ministère du Development d'exécution Tourisme C71 / Sélection d'un expert Sustainable Tourism En attente en tourisme pour le IDA / 60190 A posteriori Individuel Limited 96,000.00 0.00 2018-07-16 2018-07-21 2018-08-11 2018-09-15 2020-09-14 Development d'exécution Ministère du Tourisme C72 / Recrutement d'un cabinet de consultant pour le coaching et le suivi de Sélection de Supporting Enterprise manière personnalisée des IDA / 60190 A posteriori consultants par Direct 180,000.00 190,819.20 Signé 2018-05-25 2018-06-04 2018-08-08 2019-02-04 Creation and Growth lauréats du Concours entente directe National de Business édition 2016 C29 / Recrutement d'un Supporting Enterprise juriste (huissier ou avocat) IDA / 60190 A priori Individuel Limited 36,000.00 0.00 Annulé 2017-06-15 2017-06-20 2017-07-11 2017-08-15 2018-02-11 Creation and Growth pour les prix C68 / Recrutement d'un agent pour le suivi- Supporting Enterprise En attente IDA / 60190 A posteriori Individuel Limited 16,000.00 0.00 2018-10-18 2018-10-23 2018-11-13 2018-12-18 2019-06-16 évaluation du Concours Creation and Growth d'exécution national de Plan d'affaires C77 / Mise à jour des Sélection de Sustainable Tourism statistiques 2016-2017 du IDA / 60190 A posteriori consultants par Direct 64,000.00 67,973.60 Signé 2018-11-30 2018-12-10 2019-02-13 2019-08-12 Development Ministère du Tourisme entente directe C73 / Sélection d'un expert pour l'élaboration d'un plan IDA / 60190 Project implementation A posteriori Individuel Limited 8,080.00 0.00 Annulé 2019-05-30 2019-06-04 2019-06-25 2019-07-30 2020-01-26 de formation pour l'ensemble du personnel du Projet C59 / Sélection d'un Chargé de mission Environnement Supporting Enterprise IDA / 60190 A posteriori Individuel Open 72,000.00 0.00 Annulé 2018-02-15 2018-04-05 2018-04-26 2018-05-31 2018-11-27 pour le fonds à frais Creation and Growth partagés et l'ADEPME C42 / Sélection d'un Sélection de cabinet pour la formation Sustainable Tourism IDA / 60190 A posteriori consultants par Direct 120,000.00 0.00 Annulé 2018-01-01 2018-01-11 2018-03-17 2018-06-15 des guides et acteurs Development entente directe touristiques au Sénégal Page 9