PROCUREMENT PLAN (Textual Part) Project information: Maldives [Maldives Clean Environment Project P 160739 Project Implementation agency: Ministry of Environment and Energy Date of the Procurement Plan: 23 August 2017 Period covered by this Procurement Plan: 23 August 2017 to 23 February 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables PROCUREMENT Maldives : Maldives Clean Environment Project PLAN General Information Country: Maldives Bank’s Approval Date of the Original Procurement Plan: 2017-08-23 2019-12-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160739 GPN Date: 2017-08-23 Project Name: Maldives Clean Environment Project Loan / Credit No: IDA / D1990 Executing Agency(ies): Ministry of Environment and Energy WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MV-MEE-60158-CW-RFB / Under Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 78,000.00 0.00 Implementati 2018-05-01 2018-05-03 2018-05-24 2018-06-07 2018-07-05 2018-11-02 Management Centre in Management Systems Envelope on M.Mulah MV-MEE-61003-CW-RFB / Under Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 78,000.00 0.00 Implementati 2018-05-01 2018-05-03 2018-05-24 2018-06-07 2018-07-05 2018-11-02 Management Centre in Management Systems Envelope on Madifushi, Meemu Atoll MV-MEE-61004-CW-RFB / Under Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 78,000.00 0.00 Implementati 2018-05-01 2018-05-03 2018-05-24 2018-06-07 2018-07-05 2018-11-02 Management Centre in Management Systems Envelope on Kinbidhoo, Thaa Atoll MV-MEE-91835-CW-RFB / Upgrading of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 60,000.00 54,165.59 Signed 2018-12-17 2018-12-18 2019-01-03 2019-01-08 2019-01-27 2019-05-27 Management Centre at Lh. Management Systems Envelope Kurendhoo MV-MEE-92436-CW-RFQ / Provision of Three Phase Component 3: Island Waste Request for Single Stage - One IDA / D1990 Post Open - National 35,000.00 31,625.16 Signed 2018-12-25 2019-01-27 2019-03-28 Electricity to IWMC of Management Systems Quotations Envelope B.Kihaadhoo & N.Maafaru MV-MEE-64624-CW-RFB / Pending Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Implementati 2019-05-01 2019-05-04 2019-05-25 2019-06-08 2019-07-06 2019-11-03 Management Centre in Management Systems Envelope on Thimarafushi, Thaa Atoll MV-MEE-64627-CW-RFB / Pending Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Implementati 2019-05-01 2019-05-04 2019-05-25 2019-06-08 2019-07-06 2019-11-03 Management Centre in Management Systems Envelope on Hirilandhoo, Thaa Atoll MV-MEE-64630-CW-RFB / Pending Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Implementati 2019-05-01 2019-05-04 2019-05-25 2019-06-08 2019-07-06 2019-11-03 Management Centre in Management Systems Envelope on Guraidhoo, Thaa Atoll MV-MEE-65143-CW-RFB / Pending Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Implementati 2019-05-01 2019-05-04 2019-05-25 2019-06-08 2019-07-06 2019-11-03 Management Centre in Management Systems Envelope on Maaenboodhoo, Dhaalu Atoll MV-MEE-65371-CW-RFB / Pending Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Implementati 2019-05-01 2019-05-04 2019-05-25 2019-06-08 2019-07-06 2019-11-03 Management Centre in Management Systems Envelope on Feeali, Faafu Atoll Page 1 MV-MEE-64620-CW-RFB / Pending Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Implementati 2019-05-01 2019-05-04 2019-05-25 2019-06-08 2019-07-06 2019-11-03 Management Centre in Management Systems Envelope on Buruni, Thaa Atoll MV-MEE-65373-CW-RFB / Pending Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Implementati 2019-05-01 2019-05-04 2019-05-25 2019-06-08 2019-07-06 2019-11-03 Management Centre in Management Systems Envelope on Kolhufushi, Meemu Atoll MV-MEE-65374-CW-RFB / Pending Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Implementati 2019-05-01 2019-05-04 2019-05-25 2019-06-08 2019-07-06 2019-11-03 Management Centre in Management Systems Envelope on Dhiggaru, Meemu Atoll MV-MEE-98538-CW-RFB / Component 2: Regional Single Stage - One Construction of RO Plant IDA / D1990 Post Request for Bids Open - National 90,000.00 57,949.94 Signed 2019-02-06 2019-02-10 2019-02-24 2019-03-10 2019-04-14 2019-06-28 Waste Management Systems Envelope Building at Vandhoo RWMF MV-MEE-98559-CW-RFB / Construction of a Store Component 2: Regional Single Stage - One IDA / D1990 Post Request for Bids Open - National 140,000.00 119,541.39 Signed 2019-02-06 2019-02-10 2019-02-24 2019-03-10 2019-04-14 2019-06-28 Room and Guard House in Waste Management Systems Envelope Vandhoo RWMF MV-MEE-106513-CW-RFB / Component 3: Island Waste Single Stage - One Upgrading of IWMC in IDA / D1990 Post Request for Bids Open - National 60,000.00 53,673.20 Signed 2019-03-18 2019-03-19 2019-04-04 2019-04-09 2019-04-28 2019-08-26 Management Systems Envelope Ungoofaaru, Raa Atoll MV-MEE-106522-CW-RFB / Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 135,000.00 135,036.52 Signed 2019-03-18 2019-03-19 2019-04-04 2019-04-18 2019-05-16 2019-10-13 Management Centre in B. Management Systems Envelope Dhonfanu MV-MEE-106524-CW-RFB / Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 135,000.00 112,173.96 Signed 2019-03-18 2019-03-19 2019-04-04 2019-04-18 2019-05-16 2019-09-13 Management Centre in B. Management Systems Envelope Hithaadhoo MV-MEE-84075-CW-RFB / Component 2: Regional Single Stage - One Extension of Existing Utility IDA / D1990 Post Request for Bids Open - National 100,000.00 105,952.78 Signed 2019-05-21 2019-05-22 2019-06-12 2019-06-19 2019-07-10 2019-09-08 Waste Management Systems Envelope Building at Vandhoo RWMF MV-MEE-101303-CW-RFB / Upgrading of Waste Storage Facilities and Extension Component 2: Regional Single Stage - One IDA / D1990 Post Request for Bids Open - National 620,000.00 791,314.01 Signed 2019-05-10 2019-05-13 2019-05-27 2019-06-03 2019-06-24 2019-10-22 Works of the Existing Waste Management Systems Envelope Vehicle Shed in Vandhoo RWMF MV-MEE-136387-CW-RFB / Re-location of Existing Fuel Tanks, construction of new Pending fuel storage tank and pump Component 2: Regional Single Stage - One IDA / D1990 Post Request for Bids Open - National 650,000.00 0.00 Implementati 2020-01-05 2020-01-11 2020-02-10 2020-03-11 2020-04-15 2020-10-12 room and construction of Waste Management Systems Envelope on 200 CBM Water storage Tank at R.Vandhoo and construction of fuel trench MV-MEE-84206-CW-RFQ / Pending Rehabilitation of the Component 2: Regional Request for Single Stage - One IDA / D1990 Post Limited 50,000.00 0.00 Implementati 2019-12-04 2020-01-22 2020-03-22 Existing Landfill and Waste Management Systems Quotations Envelope on Leachate Pond (with pumps) MV-MEE-64621-CW-RFB / Pending Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Implementati 2019-11-10 2019-11-13 2019-12-04 2019-12-18 2020-01-15 2020-05-14 management Centre in Management Systems Envelope on Omadhoo, Thaa Atoll Page 2 MV-MEE-121323-CW-RFB / Re-location of Existing Fuel Tanks, construction of new Component 2: Regional Single Stage - One fuel storage tank and pump IDA / D1990 Post Request for Bids Open - National 350,000.00 0.00 Canceled 2019-06-27 2019-06-30 2019-07-30 2019-08-29 2019-10-03 2020-03-31 Waste Management Systems Envelope room and construction of 200 CBM Water storage Tank at R.Vandhoo MV-MEE-148349-CW-RFB / Pending Component 3: Island Waste Single Stage - One Upgrading of IWMC in IDA / D1990 Post Request for Bids Open - National 110,000.00 0.00 Implementati 2019-12-15 2019-12-18 2020-01-08 2020-01-22 2020-02-19 2020-06-18 Management Systems Envelope Maakurathu, Raa Atoll on MV-MEE-148352-CW-RFB / Pending Component 3: Island Waste Single Stage - One Upgrading of IWMC in IDA / D1990 Post Request for Bids Open - National 130,000.00 0.00 Implementati 2019-12-15 2019-12-18 2020-01-08 2020-01-22 2020-02-19 2020-06-18 Management Systems Envelope Eydhafushi, Baa Atoll on MV-MEE-148353-CW-RFB / Pending Component 3: Island Waste Single Stage - One Upgrading of IWMC in IDA / D1990 Post Request for Bids Open - National 130,000.00 0.00 Implementati 2019-12-15 2019-12-18 2020-01-08 2020-01-22 2020-02-19 2020-06-18 Management Systems Envelope Holhudhoo, Noonu Atoll on GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MV-MEE-36104-GO-RFQ / Setting up Procurement and Under Component 4: Project Request for Single Stage - One Financial Management IDA / D1990 Post Limited 10,000.00 10,833.12 Implementati 2017-11-21 2017-12-26 2018-01-25 Management Quotations Envelope Systems including hardware on and software MV-MEE-31491-GO-RFB / Component 2: Regional Single Stage - One Procurement of an excavator IDA / D1990 Post Request for Bids Open - National 50,000.00 0.00 Canceled 2017-11-09 2017-11-14 2017-12-26 2018-01-16 2018-02-20 2018-05-21 Waste Management Systems Envelope for Vandhoo RWMF MV-MEE-31434-GO-RFB / Component 1: National Solid Open - Single Stage - One Monitoring and Research IDA / D1990 Waste Management Strategy Post Request for Bids 650,000.00 0.00 Canceled 2017-10-30 2017-11-02 2017-12-14 2018-01-13 2018-02-17 2018-10-15 International Envelope Vessel and Policy MV-MEE-37121-GO-RFB / Component 1: National Solid Under Open - Single Stage - One Monitoring and Research IDA / D1990 Waste Management Strategy Post Request for Bids 650,000.00 1,256,000.00 Implementati 2017-11-26 2017-12-03 2018-01-14 2018-02-04 2018-03-18 2019-03-18 International Envelope Vessel and Policy on MV-MEE-37101-GO-RFQ / Component 4: Project Request for Single Stage - One Procurement of computer IDA / D1990 Post Limited 15,000.00 0.00 Canceled 2017-11-24 2017-12-22 2018-01-05 Management Quotations Envelope systems for PMU MV-MEE-37101-GO-RFQ-2 / Component 4: Project Request for Single Stage - One Desktop and Laptop IDA / D1990 Post Limited 18,000.00 19,109.48 Completed 2018-02-15 2018-03-16 2018-04-30 Management Quotations Envelope Computers for PMU MV-MEE-48442-GO-RFB / Component 4: Project Single Stage - One Speedboat for Intra-zone IDA / D1990 Post Request for Bids Open - National 200,000.00 223,120.50 Signed 2018-02-28 2018-03-07 2018-04-04 2018-04-25 2018-05-23 2018-12-19 Management Envelope travel MV-MEE-83998-GO-RFB / Under Component 2: Regional Open - Single Stage - One Procurement of a Landing IDA / D1990 Post Request for Bids 750,000.00 0.00 Implementati 2018-11-06 2018-11-11 2018-12-23 2019-01-06 2019-02-10 2019-10-08 Waste Management Systems International Envelope Craft for Vandhoo RWMF on MV-MEE-88180-GO-DIR / Component 1: National Solid Mobile Stack Emission IDA / D1990 Waste Management Strategy Post Direct Selection Direct 25,000.00 25,149.23 Completed 2018-11-27 2018-11-29 2018-12-08 2019-01-22 Monitoring Equipment and Policy Page 3 MV-MEE-83258-GO-DIR / Component 1: National Solid Supply of Mobile Stack IDA / D1990 Waste Management Strategy Prior Direct Selection Direct 25,000.00 0.00 Canceled 2018-10-25 2018-10-28 2018-11-10 2018-12-10 Emission Monitoring and Policy Equipment MV-MEE-96293-GO-RFB / Pending Supply and Installation of Component 2: Regional Open - Single Stage - One IDA / D1990 Post Request for Bids 300,000.00 0.00 Implementati 2019-01-24 2019-01-31 2019-02-28 2019-03-14 2019-04-18 2019-07-17 Water and Fuel Storage Waste Management Systems International Envelope on Tanks at Vandhoo RWMF MV-MEE-81932-GO-RFB / Pending Component 2: Regional Open - Single Stage - One Procurement of 2 Excavators IDA / D1990 Post Request for Bids 140,000.00 0.00 Implementati 2019-02-15 2019-02-18 2019-03-18 2019-03-25 2019-04-22 2019-06-21 Waste Management Systems International Envelope for Vandhoo RWMF on MV-MEE-83996-GO-RFB / Pending Procurement of Reach Component 2: Regional Single Stage - One IDA / D1990 Post Request for Bids Open - National 250,000.00 0.00 Implementati 2019-02-15 2019-02-18 2019-03-11 2019-03-25 2019-04-22 2019-06-21 Stackers (2 nos) for Vandhoo Waste Management Systems Envelope on RWMF MV-MEE-81934-GO-RFB / Pending Component 2: Regional Single Stage - One Procurement of a tractor IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Implementati 2019-02-14 2019-02-17 2019-03-17 2019-03-24 2019-04-21 2019-06-20 Waste Management Systems Envelope and trailer on MV-MEE-83997-GO-RFB / Pending Procurement of Hooklift Component 2: Regional Single Stage - One IDA / D1990 Post Request for Bids Open - National 150,000.00 0.00 Implementati 2019-02-14 2019-02-19 2019-03-12 2019-03-26 2019-04-16 2019-06-15 Trucks (2 nos.) for Vandhoo Waste Management Systems Envelope on RWMF MV-MEE-83999-GO-RFB / Under Procurement of Generator Component 2: Regional Single Stage - One IDA / D1990 Post Request for Bids Open - National 75,000.00 0.00 Implementati 2019-02-15 2019-02-20 2019-03-13 2019-03-27 2019-04-24 2019-06-23 (300 KVA) for Vandhoo Waste Management Systems Envelope on RWMF MV-MEE-99932-GO-RFQ / Component 4: Project Request for Single Stage - One Procurement of Weighing IDA / D1990 Post Open - National 25,000.00 15,230.00 Signed 2019-02-11 2019-03-21 2019-04-25 Management Quotations Envelope Scales MV-MEE-110470-GO-RFQ / Component 3: Island Waste Request for Single Stage - One Purchase Glass Crusher N. IDA / D1990 Post Limited 6,500.00 6,449.27 Completed 2019-04-17 2019-05-07 2019-06-06 Management Systems Quotations Envelope Kudafari MV-MEE-106471-GO-RFB / Under Component 2: Regional Open - Single Stage - One Landing craft for waste IDA / D1990 Prior Request for Bids 750,000.00 0.00 Implementati 2019-05-13 2019-05-16 2019-06-13 2019-06-23 2019-07-21 2020-02-16 Waste Management Systems International Envelope transfer in zone II on MV-MEE-115522-GO-RFB / Vandhoo Fire Fighting Component 2: Regional Single Stage - One IDA / D1990 Post Request for Bids Open - National 50,000.00 0.00 Canceled 2019-05-20 2019-05-25 2019-06-15 2019-06-29 2019-07-27 2019-09-25 System - Immediate Waste Management Systems Envelope Requirement MV-MEE-60157-GO-RFQ / Component 4: Project Request for Single Stage - One Procurement of Tablet IDA / D1990 Post Limited 20,840.00 0.00 Canceled 2019-07-14 2019-09-01 2019-10-01 Management Quotations Envelope Computers Under MV-MEE-121944-GO-RFQ / Component 4: Project Request for Single Stage - One IDA / D1990 Post Open - National 25,000.00 0.00 Implementati 2019-07-19 2019-09-13 2019-10-13 Office Furniture Management Quotations Envelope on MV-MEE-121947-GO-RFQ / Component 4: Project Request for Single Stage - One Purchase of Photography / IDA / D1990 Post Open - National 20,000.00 19,700.13 Completed 2019-07-23 2019-09-17 2019-10-17 Management Quotations Envelope Videography equipment Under MV-MEE-121950-GO-RFQ / Component 4: Project Request for Single Stage - One IDA / D1990 Post Open - National 15,000.00 17,598.33 Implementati 2019-07-26 2019-09-20 2019-10-20 Software Management Quotations Envelope on Page 4 MV-MEE-124036-GO-RFB / Supply and Installation of Component 2: Regional Single Stage - One IDA / D1990 Post Request for Bids Open - National 50,000.00 64,366.10 Signed 2019-07-23 2019-07-28 2019-08-18 2019-09-01 2019-09-29 2019-11-28 Fire Fighting Equipment - Waste Management Systems Envelope Immediate Requirement MV-MEE-128581-GO-DIR / Upgrading of CEMS with Component 2: Regional IDA / D1990 Post Direct Selection 28,000.00 27,913.24 Completed 2019-08-22 2019-08-25 2019-09-08 2019-11-07 CO and NOx probes and Waste Management Systems larger analyzer control unit MV-MEE-128582-GO-RFQ / Component 4: Project Request for Single Stage - One Desktops and Computer IDA / D1990 Post Limited 15,000.00 19,961.39 Completed 2019-08-28 2019-10-16 2019-11-15 Management Quotations Envelope Accessories MV-MEE-128583-GO-RFQ / Under Component 4: Project Request for Single Stage - One Laptops and Tablet IDA / D1990 Post Limited 20,000.00 24,848.77 Implementati 2019-08-28 2019-10-16 2019-11-15 Management Quotations Envelope computers on MV-MEE-135475-GO-RFB / Pending Component 2: Regional Single Stage - One Supply and Installation of IDA / D1990 Post Request for Bids Open - National 75,000.00 0.00 Implementati 2019-09-24 2019-09-29 2019-11-10 2019-12-10 2020-01-14 2020-07-12 Waste Management Systems Envelope 300 KVA Generator on MV-MEE-84003-GO-RFB / Pending Waste Collection Vehicles Component 3: Island Waste Open - Single Stage - One IDA / D1990 Prior Request for Bids 703,500.00 0.00 Implementati 2019-12-30 2020-01-06 2020-02-03 2020-02-17 2020-03-09 2020-05-08 with Trailers for Islands of Management Systems International Envelope on Zone 2 (Batch 1) NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MV-MEE-25845-CS-QCBS / Feasibility Study for a Regional Waste Management Component 3: Island Waste Quality And Cost- Open - IDA / D1990 Prior 200,000.00 265,200.34 Signed 2017-08-23 2017-08-24 2017-09-21 2017-10-19 2017-11-02 2017-12-07 2018-01-04 2018-09-01 System in Zone IV (Meemu, Management Systems Based Selection International Faafu and Dhaalu Atoll) and V (Thaa and Laamu Atoll) MV-MEE-46609-CS-LCS / Component 4: Project Least Cost IDA / D1990 Post Open - National 15,000.00 0.00 Under Review 2018-02-12 2018-02-26 2018-03-12 2018-03-26 2018-04-02 2018-04-23 2018-05-14 2024-01-08 Services of Internal Auditor Management Selection MV-MEE-60156-CS-CQS / Institutional Needs Component 1: National Solid Consultant Assessment and Developing IDA / D1990 Waste Management Strategy Post Qualification Open - National 25,000.00 0.00 Canceled 2018-05-01 2018-05-15 2018-06-05 2018-06-12 2018-07-17 2018-10-15 a Capacity Building Plan for and Policy Selection Waste Management Corporation Ltd. MV-MEE-80796-CS-CQS / Preparation of Environmental and Social Impact Component 1: National Solid Consultant Assessment for the proposed IDA / D1990 Waste Management Strategy Post Qualification Limited 20,000.00 22,004.25 Signed 2018-10-04 2018-10-11 2018-10-17 2018-11-01 2018-12-25 upgrading of infrastructure and Policy Selection at Regional Waste Management Facility - Zone 2 Page 5 MV-MEE-110477-CS-QCBS / Revision of Waste Component 1: National Solid Quality And Cost- Management Policy and IDA / D1990 Waste Management Strategy Post Open - National 75,000.00 0.00 Under Review 2019-04-16 2019-04-30 2019-05-12 2019-06-02 2019-06-09 2019-06-19 2019-07-24 2019-12-21 Based Selection Preparation of Waste and Policy Management Strategy MV-MEE-136399-CS-CQS / Selection of Consultant to undertake the preparation of Environmental and Social Consultant Management Plans for the Component 3: Island Waste Pending IDA / D1990 Post Qualification Open - National 20,000.00 0.00 2020-01-05 2020-01-10 2020-02-23 2020-03-24 2020-04-28 2020-10-25 establishment of Island Management Systems Implementation Selection Waste Management Centre in F. Feeali, M. Kolhufushi, Th. Guraidhoo & Th. Hirilandhoo MV-MEE-136401-CS-CQS / Selection of Consultant to undertake the preparation of Environmental and Social Consultant Management Plans for the Component 3: Island Waste Pending IDA / D1990 Post Qualification Open - National 20,000.00 0.00 2020-01-05 2020-01-10 2020-02-23 2020-03-24 2020-04-28 2020-10-25 establishment of Island Management Systems Implementation Selection Waste Management Centre in Dh. Maaenboodhoo, M. Dhigarru, L. Gan & L. Dhanbidhoo MV-MEE-128592-CS-CQS / Selection of a Consultancy Consultant Firm to prepare the detailed Component 2: Regional IDA / D1990 Post Qualification Open - National 50,000.00 0.00 Canceled 2019-08-25 2019-09-15 2019-10-29 2019-11-28 2020-01-02 2020-06-30 design for Fire Protection Waste Management Systems Selection System in R. Vandhoo and Supervision Consultancy MV-MEE-142985-CS-CQS / Selection of a Consultant to Consultant prepare the detailed design Component 2: Regional Pending IDA / D1990 Post Qualification Open - National 50,000.00 0.00 2019-12-30 2020-01-20 2020-02-17 2020-03-02 2020-03-30 2020-06-28 for Fire Protection System Waste Management Systems Implementation Selection in R. Vandhoo and Supervision INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MV-MEE-37124-CS-INDV / Component 1: National Solid Individual Consultancy for Preparing IDA / D1990 Waste Management Strategy Prior Consultant Direct 24,000.00 29,350.00 Under Review 2017-11-26 2017-12-06 2017-12-13 2017-12-27 2018-02-10 the Operations Plan of and Policy Selection Vandhoo RWMF (Zone 2) MV-MEE-37110-CS-INDV / Individual Component 4: Project Financial Management IDA / D1990 Prior Consultant Direct 90,000.00 124,695.98 Signed 2017-11-21 2017-11-27 2017-12-04 2017-12-16 2020-12-15 Management Specialist for PMU Selection Individual MV-MEE-39091-CS-INDV / Component 4: Project IDA / D1990 Post Consultant Open 90,000.00 90,000.00 Signed 2017-12-28 2018-01-13 2018-01-15 2018-02-01 2021-01-17 Civil Engineer for PMU Management Selection MV-MEE-41149-CS-INDV / Individual Component 4: Project Monitoring and Evaluation IDA / D1990 Post Consultant Open 90,000.00 0.00 Under Review 2017-12-31 2018-01-17 2018-01-22 2018-02-15 2021-01-30 Management Specialist for PMU Selection MV-MEE-41150-CS-INDV / Individual Component 4: Project Communications Specialist IDA / D1990 Post Consultant Open 90,000.00 81,500.64 Signed 2018-01-04 2018-01-28 2018-01-31 2018-02-15 2021-01-30 Management for PMU Selection Page 6 MV-MEE-48404-CS-CDS / Component 4: Project Procurement Specialist for IDA / D1990 Prior Direct Selection Direct 90,000.00 0.00 Under Review 2018-02-14 2018-02-22 2018-02-28 2021-02-28 Management PMU MV-MEE-48407-CS-CDS / Environmental and Social Component 4: Project IDA / D1990 Prior Direct Selection Direct 90,000.00 0.00 Canceled 2018-02-15 2018-02-22 2018-02-28 2021-02-28 Safeguards Specialist for Management PMU MV-MEE-53309-CS-INDV / Component 1: National Solid Individual Preparation of EMPs for 6 IDA / D1990 Waste Management Strategy Post Consultant Open 15,000.00 11,966.36 Signed 2018-03-18 2018-04-04 2018-04-11 2018-05-09 2018-07-08 Selected Island Waste and Policy Selection Management Centres MV-MEE-53794-CS-INDV / Component 5: Contingent Individual Assistant Project Coordinator IDA / D1990 Emergency Response Post Consultant Open 54,000.00 46,944.37 Signed 2018-03-19 2018-04-16 2018-04-23 2018-05-14 2021-08-16 for PMU Component Selection MV-MEE-54013-CS-INDV / Component 5: Contingent Individual Assistant Project Coordinator IDA / D1990 Emergency Response Post Consultant Open 54,000.00 46,944.37 Signed 2018-03-19 2018-04-07 2018-04-14 2018-05-12 2021-08-14 for PMU Component Selection MV-MEE-64614-CS-INDV / Institutional Needs Component 1: National Solid Individual Assessment of Waste IDA / D1990 Waste Management Strategy Post Consultant Open 25,000.00 0.00 Under Review 2018-06-03 2018-07-02 2018-07-16 2018-08-13 2018-10-12 Management Corporation and Policy Selection Ltd. MV-MEE-79643-CS-INDV / Services of a Naval Individual Architect/Engineer for the Component 4: Project IDA / D1990 Post Consultant Limited 35,000.00 29,922.38 Signed 2018-09-28 2018-09-30 2018-10-15 2018-11-01 2019-12-31 supervision of marine vessel Management Selection construction projects under MCEP MV-MEE-81147-CS-INDV / Individual Component 4: Project Financial Management IDA / D1990 Post Consultant Open 54,000.00 46,944.37 Signed 2018-10-08 2018-10-14 2018-10-21 2018-11-01 2021-10-31 Management Assistant Selection MV-MEE-81381-CS-INDV / Preparation of the detailed master plan layout and Individual detailed design of required Component 2: Regional IDA / D1990 Post Consultant Limited 20,000.00 24,655.90 Signed 2018-10-18 2018-10-21 2018-10-28 2018-11-18 2019-01-02 additional infrastructure for Waste Management Systems Selection the Regional Waste Management Facility of Zone- 2 MV-MEE-87721-CS-INDV / Component 5: Contingent Individual Assistant Project Coordinator IDA / D1990 Emergency Response Post Consultant Open 54,000.00 46,944.37 Signed 2018-11-22 2018-11-22 2018-12-10 2018-12-16 2022-03-20 for PMU Component Selection MV-MEE-48421-CS-CDS / Component 4: Project IDA / D1990 Prior Direct Selection Direct 108,000.00 0.00 Canceled 2018-02-15 2018-02-23 2018-02-28 2021-02-28 Project Manager for PMU Management Individual MV-MEE-93341-CS-INDV / Component 4: Project Under IDA / D1990 Post Consultant Open 48,000.00 0.00 2019-02-10 2019-03-08 2019-03-22 2019-04-19 2021-04-19 Project Coordinator (Zone 2) Management Implementation Selection MV-MEE-80820-CS-INDV / Individual Component 4: Project Project Coordinator (Zone IDA / D1990 Post Consultant Open 90,000.00 81,500.64 Signed 2019-05-17 2019-05-30 2019-06-02 2019-06-19 2022-06-18 Management 4&5) for PMU Selection MV-MEE-83452-CS-CDS / Operations Specialist for Component 2: Regional IDA / D1990 Prior Direct Selection Direct 120,000.00 98,530.04 Signed 2019-05-10 2019-05-15 2019-06-01 2020-05-31 Vandhoo RWMF (12 month Waste Management Systems assignment) Page 7 MV-MEE-83995-CS-CDS / Incinerator Specialist for Component 2: Regional Pending IDA / D1990 Prior Direct Selection Direct 90,000.00 0.00 2019-05-15 2019-05-25 2019-06-15 2020-04-10 Vandhoo RWMF (10 months Waste Management Systems Implementation period) MV-MEE-113875-CS-INDV / Development of a Component 1: National Solid Individual Under Management Information IDA / D1990 Waste Management Strategy Post Consultant Limited 7,500.00 0.00 2019-05-10 2019-05-13 2019-05-16 2019-06-01 2019-07-01 Implementation System (MIS) Database for and Policy Selection Solid Waste Management MV-MEE-113891-CS-INDV / Individual Consultancy Services for Component 4: Project IDA / D1990 Post Consultant Limited 15,000.00 14,961.19 Signed 2019-05-10 2019-05-13 2019-05-16 2019-06-02 2019-07-02 Undertaking an Independent Management Selection Evaluation of MCEP MV-MEE-115528-CS-INDV / Individual Component 2: Regional Fire Fighting Design and IDA / D1990 Post Consultant Limited 50,000.00 0.00 Canceled 2019-05-26 2019-05-29 2019-06-01 2019-06-18 2019-08-17 Waste Management Systems Supervision Consultant Selection MV-MEE-126235-CS-INDV / Component 1: National Solid Individual Consultancy for Strategic IDA / D1990 Waste Management Strategy Post Consultant Open 4,000.00 4,527.81 Signed 2019-08-06 2019-08-27 2019-09-01 2019-10-06 2019-10-12 planning of Single use and Policy Selection plastic phase-out Plan MV-MEE-133400-CS-INDV / Preparation of ESMP for Component 1: National Solid Individual upgrading of IWMCs in 2 Pending IDA / D1990 Waste Management Strategy Post Consultant Open 10,000.00 0.00 2019-12-15 2020-01-01 2020-01-08 2020-02-05 2020-04-05 selected islands of Zone 2 - Implementation and Policy Selection (B. Eydhafushi & R. Maakurathu) MV-MEE-48441-CS-INDV / Augmentation of Curriculum Component 1: National Solid Individual Pending for Environmental IDA / D1990 Waste Management Strategy Post Consultant Open 25,000.00 0.00 2019-12-30 2020-02-10 2020-02-24 2020-03-23 2020-06-21 Implementation Management Diploma/Degree and Policy Selection Program of MNU Page 8