Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: 2. Date of General Procurement Notice: June 06, 2014 3. Period covered by this procurement plan: The procurement period of project covered from year July 8, 2016 to July 7, 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 1.5 Million 2. NCB (Goods) N/A 3. ICB (Works) Above US$ 5 million All 4. NCB (Works) N/A All 5. (Non-Consultant Services) Above US$ 1.5 Million 6 Individual Consultants for procurement All regardless of the and legal services contract amount 2. Prequalification: N/A 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: N/A 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for GEQIP II Volume 1: Institutional Arrangements, Planning and Monitoring and Evaluation Volume 2: Financial Management Volume 3: Procurement Management Volume 4: School Grant Guidelines 5. Any Other Special Procurement Arrangements: No 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domestic Review Comments No. Cost Preferenc by Bank US$ e (Prior / million (yes/no) Post) Summary of No - - - There is no works the ICB component in this (Works) project Summary of 140.67 20 Yes Prior the ICB (Goods) Summary of No - - - There is no works the NCB component in this (Works) project Summary of 2.51 8 No Post the NCB (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) All 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 3.10 7 Prior number of contracts that 1.61 31 Post will be let under QCBS Summary of 0.26 6 Prior SSS and number of Selection of IC contracts that will be let 1.28 40 Post under other methods PROCUREMENT Ethiopia : Ethiopia General Education Quality Improvement Project II PLAN General Information Country: Ethiopia Bank’s Approval Date of the Original Procurement Plan: 2017-03-31 2019-03-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P129828 GPN Date: Project Name: Ethiopia General Education Quality Improvement Project II Loan / Credit No: IDA / 53150 Executing Agency(ies): Ministry of Education WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOE/GEQIP-2/NCB/G-88/16 Pending / Procure locally available Request for Single Stage - One IDA / 53150 Post Limited 0.00 Implementati 2017-04-04 2017-05-30 2017-11-26 Montossori materials for O Quotations Envelope on class pilot program MOE/GEQIP-2/ICB/G-06/13 / Development, Printing and Under Open - Single Stage - One Distribution of IDA / 53150 Prior Request for Bids 0.00 Implementati 2016-07-25 2016-07-30 2016-09-10 2016-10-10 2016-11-14 2017-05-13 International Envelope supplementary materials for on Grade 7-10 MOE/GEQIP-2/ICB/G-63/15 / Printing and Distribution of Open - Single Stage - One IDA / 53150 Prior Request for Bids 3,373,375.22 Signed 2016-03-15 2016-03-20 2016-05-01 2016-05-31 2016-07-05 2017-01-01 Grade G1-8 Adapted Mother International Envelope Tongue MOE/GEQIP-2/ICB/G-61/14 / Printing and Distribution of Open - Single Stage - One Grade 3-8 Amharic IDA / 53150 Prior Request for Bids 4,055,371.63 Signed 2016-03-30 2016-04-04 2016-05-16 2016-06-15 2016-07-20 2017-01-16 International Envelope Textbooks and Teachers Guide MOE/GEQIP-2/NCB/G-86/16 / Supply, Implementation Pending Single Stage - One and Commissioning of 500 IDA / 53150 Prior Request for Bids Open - National 0.00 Implementati 2017-04-10 2017-04-15 2017-05-27 2017-06-26 2017-07-31 2018-01-27 Envelope audio reader for 200 on Secondary Schools MOE/GEQIP-2/NCB/G-106/16 / Supply 480 tablets with Pending educational application Single Stage - One IDA / 53150 Post Request for Bids Open - National 0.00 Implementati 2017-04-27 2017-05-02 2017-06-13 2017-07-13 2017-08-17 2018-02-13 (platform) to Six(6) Envelope on secondary school of two(2) emerging regions MOE/GEQIP-2/NCB/G-108/16 / Supply of Computers for Pending Single Stage - One BOFEDs' and ZOFEDs' to IDA / 53150 Post Request for Bids Open - National 0.00 Implementati 2017-04-03 2017-04-08 2017-05-20 2017-06-19 2017-07-24 2018-01-20 Envelope implement the IBEX roll out on for GEQIP II Page 1 MOE/GEQIP-2/SH/G-110/16 Pending Single Stage - One / Procurement of vehicles for IDA / 53150 Post Request for Bids Open - National 0.00 Implementati 2017-05-01 2017-05-06 2017-06-17 2017-07-17 2017-08-21 2018-02-17 Envelope MOE on MOE/GEQIP-2/SH/G-92/16 / Translation, Printing and Pending distribution of 0- class Request for Single Stage - One IDA / 53150 Post Limited 0.00 Implementati 2017-04-18 2017-06-13 2017-12-10 curriculum materials in 4 Quotations Envelope on local languages of Benishanguel Gumuze region AFAR/GEQIP-2/NCB/G-1/09 Pending / Provision of student Single Stage - One IDA / 53150 Post Request for Bids Open - National 0.00 Implementati 2017-04-10 2017-04-15 2017-05-27 2017-06-26 2017-07-31 2018-01-27 desk,shelves,blackboards and Envelope on tables and chairs. AFAR/GEQIP-2/SH/G-1/09 / For up-grading level one Pending schools in afar Provision of Request for Single Stage - One IDA / 53150 Post Limited 0.00 Implementati 2017-04-16 2017-06-11 2017-12-08 science kits and educational Quotations Envelope on materials for the targeted 40 schools. AFAR/GEQIP-2/SH/G-2/09 / Pending For up-grading level one Request for Single Stage - One IDA / 53150 Post Limited 0.00 Implementati 2017-04-13 2017-05-04 2017-10-31 schools in afar Provision of Quotations Envelope on water tanks. AFAR/GEQIP-2/SH/G-4/09 / Printing and distribution of Training material including syllabus,school based management (SBM) Pending Request for Single Stage - One guideline,school improvement IDA / 53150 Post Limited 0.00 Implementati 2017-04-18 2017-06-13 2017-12-10 Quotations Envelope framework and guideline, on reading club guideline, Printing of written tests for primary school teachers and school leaders. AFAR/GEQIP-2/SH/G-5/09 / For up-grading level one schools in afar supply Pending reference books and Request for Single Stage - One IDA / 53150 Post Limited 0.00 Implementati 2017-04-17 2017-06-12 2017-12-09 supplementary reading Quotations Envelope on materials to establish a reading center or reading corner. AFAR/GEQIP-2/SH/G-6/09 / Pending Procurment of various Request for Single Stage - One IDA / 53150 Post Limited 0.00 Implementati 2017-04-18 2017-06-13 2017-12-10 equipment for Quotations Envelope on communications AFAR/GEQIP-2/SH/G-7/09 / Pending Request for Single Stage - One Printing of booklets, IDA / 53150 Post Limited 0.00 Implementati 2017-04-18 2017-06-13 2017-12-10 Quotations Envelope brochures and leaflets/fliers on MOE/GEQIP-2/ICB/G-142/16 / Printing and Distribution Open - Single Stage - One of English Textbooks and IDA / 53150 Prior Request for Bids 30,454,799.27 Signed 2017-05-08 2017-05-13 2017-06-24 2017-07-24 2017-08-28 2018-02-24 International Envelope Teachers Guide for Grade 1- 8 MOE/GEQIP-2/NCB/G-94/16 Pending / Purchase and supply of 5 Single Stage - One IDA / 53150 Post Request for Bids Open - National 0.00 Implementati 2017-04-13 2017-04-18 2017-05-30 2017-06-29 2017-08-03 2018-01-30 Computers for each 200 Envelope on secondary schools. Page 2 MOE/GEQIP-2/ICB/G-96/16 / Developing, printing, and Open - Single Stage - One distributing G5-8, textbooks IDA / 53150 Prior Request for Bids 3,026,364.28 Signed 2017-04-04 2017-04-09 2017-05-21 2017-06-20 2017-07-25 2018-01-21 International Envelope and teachers guide for Oromiya Region MOE/GEQIP-2/NCB/G-70/15 / Printing and distribution of licensing guideline and regulation documents, Pending Single Stage - One English version teachers IDA / 53150 Post Request for Bids Open - National 0.00 Implementati 2017-04-12 2017-04-17 2017-05-29 2017-06-28 2017-08-02 2018-01-29 Envelope and educational leaders on generic standardes and (Amharic) content and pedagogic standareds MOE/GEQIP-2/NCB/G-15- 1/13 / Printing and Pending Distribution of Grade 1- Single Stage - One IDA / 53150 Post Request for Bids Open - National 0.00 Implementati 2017-04-28 2017-05-03 2017-06-14 2017-07-14 2017-08-18 2018-02-14 8Arts, Visual Arts and Envelope on Physical Education Teachers Guide MOE/GEQIP-2/ICB/G-24/13 R / Supply, installation and Open - Single Stage - One commissioning of Educational IDA / 53150 Prior Request for Bids 26,400,000.00 Signed 2016-10-18 2016-10-23 2016-12-04 2017-01-03 2017-02-07 2018-03-04 International Envelope Private Cloud Infrastructure and services MOE/GEQIP-2/ICB/G-02/13 / Adaptation and Transcription Open - Single Stage - One of Textbooks and Teachers IDA / 53150 Prior Request for Bids 4,818,165.27 Signed 2016-09-26 2016-10-01 2016-11-12 2016-12-12 2017-01-16 2017-07-15 International Envelope Guide in to Braille and Distribution MOE/GEQIP-2/ICB/G-04/13 / Development, Printing and Open - Single Stage - One Distribution of Grade 1- 4 IDA / 53150 Prior Request for Bids 4,372,427.85 Signed 2015-11-18 2015-11-18 2015-11-18 2015-11-18 2015-12-09 2016-06-06 International Envelope Mother Tongue Supplementary materials MOE/GEQIP-2/ICB/G-85/13 / Development, Printing, and Distribution of Grade 1- 4 Open - Single Stage - One IDA / 53150 Prior Request for Bids 2,335,011.92 Signed 2016-03-02 2016-03-07 2016-04-18 2016-05-18 2016-06-22 2016-12-19 Supplementary Materials International Envelope Environmental science and Mathematics MOE/GEQIP-2/ICB/G-60/14 / Pending Development, Printing and Single Stage - One IDA / 53150 Post Request for Bids Open - National 0.00 Implementati 2016-06-05 2016-06-10 2016-07-22 2016-08-21 2016-09-25 2017-03-24 Distribution of Grade 9-12 Envelope on Somaligna AAC/GEQIP-2/SH/G-1/09 / Printing of written test for Pending Request for Single Stage - One primary school teachers and IDA / 53150 Post Limited 0.00 Implementati 2017-05-27 2017-07-22 2018-01-18 Quotations Envelope school leaders 3 times a on year AAC/GEQIP-2/SH/G-4/09 / Pending Request for Single Stage - One Printing of 1. Magazines 2. IDA / 53150 Post Limited 0.00 Implementati 2017-05-20 2017-07-15 2018-01-11 Quotations Envelope Brochures 3. Booklets on AAC/GEQIP-2/SH/G-5/09 / Pending Request for Single Stage - One Printing of leaflets/fliers and IDA / 53150 Post Limited 0.00 Implementati 2017-05-23 2017-07-18 2018-01-14 Quotations Envelope various sizes on AAC/GEQIP-2/SH/G-6/09 / Pending Procurment of various Request for Single Stage - One IDA / 53150 Post Limited 0.00 Implementati 2017-05-23 2017-07-18 2018-01-14 equipment for Quotations Envelope on communications Page 3 BEN-G/GEQIP-2/SH/G-2/09 / Pending Request for Single Stage - One Purchasing of training IDA / 53150 Post Limited 0.00 Implementati 2017-05-21 2017-07-16 2018-01-12 Quotations Envelope materials and equipments on BEN-G/GEQIP-2/SH/G-5/09 / Pending Request for Single Stage - One Printing of 1. Magazines IDA / 53150 Post Limited 0.00 Implementati 2017-05-29 2017-07-24 2018-01-20 Quotations Envelope 2. Booklets 3. Brochures on BEN-G/GEQIP-2/SH/G-7/09 / Pending Procurment of various Request for Single Stage - One IDA / 53150 Post Limited 0.00 Implementati 2017-05-30 2017-07-25 2018-01-21 equipment for Quotations Envelope on communications DIRED/GEQIP-2/SH/G-3/09 / Pending Printing of 1. Magazine Request for Single Stage - One IDA / 53150 Post Limited 0.00 Implementati 2017-06-03 2017-07-29 2018-01-25 2. Brochures and 3. Quotations Envelope on Booklets DIRED/GEQIP-2/SH/G-4/09 / Pending Request for Single Stage - One Printing of leaflets/fliers and IDA / 53150 Post Limited 0.00 Implementati 2017-06-04 2017-07-30 2018-01-26 Quotations Envelope various sizes on DIRED/GEQIP-2/SH/G-5/09 / Pending Procurment of various Request for Single Stage - One IDA / 53150 Post Limited 0.00 Implementati 2017-06-05 2017-07-31 2018-01-27 equipment for Quotations Envelope on communications ASAITA/GEQIP-2/SH/G-1/09 Pending Request for Single Stage - One / Printing entrance exam for IDA / 53150 Post Limited 0.00 Implementati 2017-06-04 2017-07-30 2018-01-26 Quotations Envelope the selection of new entrants on MOE/GEQIP-2/NCB/G-80/15 / Procurement of Computer, Pending Single Stage - One printer, Laptop, Photocopy IDA / 53150 Post Request for Bids Open - National 0.00 Implementati 2017-05-26 2017-05-31 2017-07-12 2017-08-11 2017-09-15 2018-03-14 Envelope Machine and other Office on Equipment MOE/GEQIP-2/SH/G-114/16 Pending / Printing of newsletters on Request for Single Stage - One IDA / 53150 Post Limited 0.00 Implementati 2017-05-27 2017-07-22 2018-01-18 various general education Quotations Envelope on topics MOE/GEQIP-2/SH/G-54/15 / Pending Procurement of Offfice Request for Single Stage - One IDA / 53150 Post Limited 0.00 Implementati 2017-02-19 2017-04-16 2017-10-13 Supplies (Stationery Quotations Envelope on Materials) MOE/GEQIP-2/ICB/G-07/13 / Development, Printing and Open - Single Stage - One Distribution of IDA / 53150 Prior Request for Bids 5,415,478.02 Signed 2016-07-25 2016-07-30 2016-09-10 2016-10-10 2016-11-14 2017-05-13 International Envelope supplementary materials for Grade 7-10 BEN-G/GEQIP-2/SH/G-6/09 / Pending Request for Single Stage - One Printing of leaflets/fliers and IDA / 53150 Post Limited 0.00 Implementati 2017-05-30 2017-07-25 2018-01-21 Quotations Envelope various sizes on MOE/GEQIP-2/SH/G-55/14 / Pending Printing and distribution of Request for Single Stage - One IDA / 53150 Post Limited 0.00 Implementati 2017-05-28 2017-07-23 2018-01-19 Magazines, Brochures, Quotations Envelope on Leaflets Pending MOE/GEQIP-2/NCB/G-112/16 Request for Single Stage - One IDA / 53150 Post Limited 0.00 Implementati 2017-05-29 2017-07-24 2018-01-20 / Printing of posters Quotations Envelope on Page 4 MOE/GEQIP-2/SH/G-119/16 Pending Request for Single Stage - One / Printing of Promotional IDA / 53150 Post Limited 0.00 Implementati 2017-05-30 2017-07-25 2018-01-21 Quotations Envelope Year Planners on MOE/GEQIP-2/SH/G-118/16 Pending / Printing of promotional Request for Single Stage - One IDA / 53150 Post Limited 0.00 Implementati 2017-05-30 2017-07-25 2018-01-21 items for the annual Quotations Envelope on education conference MOE/GEQIP-2/SH/G-122/16 Pending / Procurement of various Request for Single Stage - One IDA / 53150 Post Limited 0.00 Implementati 2017-06-03 2017-07-29 2018-01-25 communications work related Quotations Envelope on hardware and software MOE/GEQIP-2/NCB/G-111/16 Pending Request for Single Stage - One / Printing of booklets and IDA / 53150 Post Limited 0.00 Implementati 2017-06-07 2017-08-02 2018-01-29 Quotations Envelope magazines on MOE/GEQIP-2/SH/G-143/16 Pending / Printing the Assessment Request for Single Stage - One IDA / 53150 Post Limited 0.00 Implementati 2017-06-21 2017-08-16 2018-02-12 impact of previous Quotations Envelope on Curriculum changes report. MOE/GEQIP-2/SH/G-116/16 Pending / Procurement of web server, Request for Single Stage - One IDA / 53150 Post Limited 0.00 Implementati 2017-05-28 2017-07-23 2018-01-19 computers, UPS, racks, Quotations Envelope on cables, ORO/GEQIP-2/SH/G-1/09 / Pending Procurement of training Request for Single Stage - One IDA / 53150 Post Limited 0.00 Implementati 2017-09-06 2017-11-01 2018-04-30 materials and equipment s Quotations Envelope on for the integrated pilot CPD. SNNP/GEQIP-2/NCB/G-1/17 / procurement of braille Pending Single Stage - One embosser printing machine IDA / 53150 Post Request for Bids Open - National 0.00 Implementati 2017-09-04 2017-09-09 2017-10-21 2017-11-20 2017-12-25 2018-06-23 Envelope as well as other educational on materials MOE/GEQIP-2/SH/G-162/18 Pending / Sample print and Request for Single Stage - One IDA / 53150 Post Limited 0.00 Implementati 2018-08-22 2018-10-17 2019-04-15 distribute the new school Quotations Envelope on grant guide line MOE/GEQIP-2/SH/G-149/17 / Transcribe the generic Pending Single Stage - One standard operational manual IDA / 53150 Post Request for Bids Limited 0.00 Implementati 2018-08-09 2018-08-14 2018-09-25 2018-10-25 2018-11-29 2018-12-29 Envelope and portfolio assessment tool on into Brails MOE/GEQIP-2/NCB/G- 86/16_1 / Supply, Pending Single Stage - One Implementation and IDA / 53150 Post Request for Bids Open - National 0.00 Implementati 2017-05-18 2017-05-23 2017-07-04 2017-08-03 2017-09-07 2018-03-06 Envelope Commissioning of 500 audio on reader MOE/GEQIP-2/ICB/G-141- 1/16 / Reprinting and IDA / 53150 Prior Direct Selection Direct 0.00 Canceled 2017-05-15 2017-05-20 2017-06-24 2017-12-21 Distribution of grade 9-12 MOE/GEQIP-2/ICB/G-141- 3/16 / Reprinting and IDA / 53150 Prior Direct Selection Direct 0.00 Canceled 2017-05-15 2017-05-20 2017-06-24 2017-12-21 Distribution of Grade 9-12 MOE/GEQIP-2/ICB/G-141- 2/16 / Reprinting and IDA / 53150 Prior Direct Selection Direct 0.00 Canceled 2017-05-15 2017-05-20 2017-06-24 2017-12-21 Distribution of Grade 9-12 Page 5 MOE/GEQIP-2/ICB/G-141- 4/16 / Reprinting and IDA / 53150 Prior Direct Selection Direct 0.00 Canceled 2017-05-15 2017-05-20 2017-06-24 2017-12-21 Distribution of Grade 9-12 MOE/GEQIP-2/ICB/G-141- 5/16 / Reprinting and IDA / 53150 Prior Direct Selection Direct 0.00 Canceled 2017-05-15 2017-05-20 2017-06-24 2017-12-21 Distribution of Grade 9-12 MOE/GEQIP-2/ICB/G-95/16 / Reprinting and Distribution Open - Single Stage - One IDA / 53150 Prior Request for Bids 0.00 Canceled 2017-04-20 2017-04-25 2017-06-06 2017-07-06 2017-08-10 2018-02-06 of-Grade 10 Civics and International Envelope Ethical Education Textbooks MOE/GEQIP-2/ICB/G-141/16 / Re-Printing and Distribution of Grade 9-12 IDA / 53150 Prior Direct Selection Direct 0.00 Canceled 2017-04-17 2017-04-22 2017-05-27 2017-11-23 TBs and TGs for 13 Subjects AFAR/GEQIP-2/SH/G-3/09 / For up-grading level one Request for Single Stage - One schools in afar Transport of IDA / 53150 Post Limited 0.00 Canceled 2017-04-17 2017-06-12 2017-12-09 Quotations Envelope the procured items to beneficiary schools. NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DIRED/GEQIP-2/SH/G-1/09 / Pending TV spots/programs/adverts IDA / 53150 Post Direct Selection Direct 0.00 Implementati 2017-05-22 2017-05-27 2017-07-01 2017-12-28 PSAs Placement on Pending AAC/GEQIP-2/SH/G-2/09 / IDA / 53150 Post Direct Selection Direct 0.00 Implementati 2017-05-17 2017-05-22 2017-06-26 2017-12-23 TV programs/spots Placement on AAC/GEQIP-2/SH/G-3/09 / Pending Radio - Production and IDA / 53150 Post Direct Selection Direct 0.00 Implementati 2017-05-18 2017-05-23 2017-06-27 2017-12-24 Placement on BEN-G/GEQIP-2/SH/G-3/09 / Pending TV spots/programs/adverts IDA / 53150 Post Direct Selection Direct 0.00 Implementati 2017-05-22 2017-05-27 2017-07-01 2017-12-28 PSAs Placement on MOE/GEQIP-2/SH/G-123/16 Pending / TV Spots IDA / 53150 Post Direct Selection Direct 0.00 Implementati 2017-05-24 2017-05-29 2017-07-03 2017-12-30 Placement/broadcast for on media-1 DIRED/GEQIP-2/D/G-2/17 / Pending Radio Programs Production IDA / 53150 Post Direct Selection Direct 0.00 Implementati 2017-10-06 2017-10-11 2017-11-15 2018-05-14 and Placement on MOE/GEQIP-2/SH/G-159/17 Pending Request for Single Stage - One / TV Programs Production IDA / 53150 Post Limited 0.00 Implementati 2018-08-20 2018-10-15 2018-11-14 Quotations Envelope and Placement on MOE/GEQIP-2/SH/G-161/17 Pending Request for Single Stage - One / Radio Spots IDA / 53150 Post Limited 0.00 Implementati 2018-08-22 2018-10-17 2018-11-16 Quotations Envelope Placement/broadcast on Page 6 AFA/GEQIP-2/SH/G-3/09 / Pending Transport of the procured Request for Single Stage - One IDA / 53150 Post Limited 0.00 Implementati 2017-04-17 2017-06-12 2017-12-09 items to Afar upgrading Quotations Envelope on schools CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOE/GEQIP-2/QCBS/C- 103/16 / Procurement of consultancy Service for Quality And Cost- Open - Under IDA / 53150 Prior 0.00 2017-03-14 2017-04-04 2017-05-18 2017-06-15 2017-07-15 2017-08-19 2017-09-23 2018-09-23 GEQIP-2 Comprehensive Based Selection International Implementation Evaluation (Mid and Exit Evaluation) MOE/GEQIP-2/ QCBS /C- 102/16 / Consultancy service Quality And Cost- Open - Under to develop an Ethiopian- IDA / 53150 Post 0.00 2017-03-28 2017-04-18 2017-06-01 2017-06-29 2017-07-29 2017-09-02 2017-10-07 2018-10-07 Based Selection International Implementation relevant ICT competency framework for teachers MOE/GEQIP-2/QCBS/C-90/16 / Consulting Firm for Adaptation and Translation Quality And Cost- Pending IDA / 53150 Post Open - National 0.00 2017-04-28 2017-05-19 2017-07-02 2017-07-30 2017-08-29 2017-10-03 2017-11-07 2018-11-07 of Grade 1-8 Arts, Visual Based Selection Implementation Arts and Physical Education Teachers Guide MOE/GEQIP-2/ CQS/C- Consultant 111/16 / Development of Under IDA / 53150 Post Qualification Open - National 0.00 2017-04-19 2017-05-10 2017-06-23 2017-07-23 2017-08-27 2018-02-23 Inspection data utilization Implementation Selection software MOE/GEQIP-2/ QCBS /C- 102/17 / Consultancy service Quality And Cost- Pending to develop an Ethiopian- IDA / 53150 Post Open - National 0.00 2017-05-24 2017-06-14 2017-07-28 2017-08-25 2017-09-24 2017-10-29 2017-12-03 2018-12-03 Based Selection Implementation relevant ICT competency framework MOE/GEQIP-2/QCBS/C-40/13 / GEQIP II Annual Quality And Cost- Open - Under IDA / 53150 Prior 0.00 2016-03-22 2016-04-12 2016-05-26 2016-06-23 2016-07-23 2016-08-27 2016-10-01 2017-10-01 Independent Procurement Based Selection International Implementation Audit BEN-G/GEQIP-2/QCBS/C- 1/09 / Selection of consulting Consultant Pending firm for the preparation of IDA / 53150 Post Qualification Open - National 0.00 2017-05-16 2017-06-06 2017-07-20 2017-08-19 2017-09-23 2018-03-22 Implementation TV programs/spots Selection production DIRED/GEQIP-2/QCBS/C- Consultant 1/09 / Selection of consulting Pending IDA / 53150 Post Qualification Open - National 0.00 2017-05-15 2017-06-05 2017-07-19 2017-08-18 2017-09-22 2018-03-21 firm for perparation of TV Implementation Selection programs/spots production AAC/GEQIP-2/QCBS/C-1/09 / Consultant Selection of consulting firm Pending IDA / 53150 Post Qualification Open - National 0.00 2017-05-19 2017-06-09 2017-07-23 2017-08-22 2017-09-26 2018-03-25 for preparation of TV Implementation Selection programs/spots production BEN-G/GEQIP-2/SH/G-4/09 / Consultant Radio - Production and Pending IDA / 53150 Post Qualification Open - National 0.00 2017-05-22 2017-06-12 2017-07-26 2017-08-25 2017-09-29 2018-03-28 Placement of short Implementation Selection messages/programs/spots Page 7 MOE/GEQIP-2/SH/G-126/16 / Selection of consulting firm Consultant Pending for preparation of TV IDA / 53150 Post Qualification Open - National 0.00 2017-05-24 2017-06-14 2017-07-28 2017-08-27 2017-10-01 2018-03-30 Implementation Programs Production and Selection Placement for media-1 MOE/GEQIP-2/QCBS/C-99/16 / Procurement of consultancy Consultant firm to upgrade the teacher Under IDA / 53150 Post Qualification Open - National 0.00 2017-06-23 2017-07-14 2017-08-27 2017-09-24 2017-10-24 2017-11-28 2018-01-02 2019-01-02 and educational leaders Implementation Selection Licensing Information System (LIS) database MOE/GEQIP-2/ QCBS /C- 101/16 / Consulting service Quality And Cost- Open - Pending to develop a learning IDA / 53150 Prior 0.00 2017-06-23 2017-07-14 2017-08-27 2017-09-24 2017-10-24 2017-11-28 2018-01-02 2019-01-02 Based Selection International Implementation management system(LMS/LCMS) MOE/GEQIP-2/QCBS/C- 108/16 / Hiring firm to record and Monitor the Consultant Pending actual placement of TV and IDA / 53150 Post Qualification Open - National 0.00 2017-06-26 2017-07-17 2017-08-30 2017-09-27 2017-10-27 2017-12-01 2018-01-05 2019-01-05 Implementation Radio spots and programs Selection from the various national and regional broadcasters. TG/GEQIP-2/QCBS/C-1/09 / Consultant Selection of consulting firm Pending IDA / 53150 Post Qualification Open - National 0.00 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2018-07-27 for preparation of TV Implementation Selection programs/spots production. MOE/GEQIP-2/QCS/C-130/17 / Consultancy Services for Consultant Under Development of Inspection IDA / 53150 Post Qualification Open - National 0.00 2018-02-07 2018-02-28 2018-04-13 2018-05-13 2018-06-17 2018-12-14 Implementation Data Base management Selection Software MOE/GEQIP-2/QCBS/C-89/16 / A consulting firm for assessing the status of Quality And Cost- Open - textbook student ratio by IDA / 53150 Prior 0.00 Canceled 2017-04-25 2017-05-16 2017-06-29 2017-07-27 2017-08-26 2017-09-30 2017-11-04 2018-11-04 Based Selection International regions ,subject grade level and textbook utlization in REBs MOE/GEQIP-2/QCBS/C-89- 1/16 / Consultancy Service Quality And Cost- Open - Pending IDA / 53150 Post 0.00 2017-04-25 2017-05-16 2017-06-29 2017-07-27 2017-08-26 2017-09-30 2017-11-04 2018-11-04 for assessing the status of Based Selection International Implementation textbook student ratio CBS/C-95/16 / Consultancy services for SIP Quality And Cost- Open - Pending IDA / 53150 Post 0.00 2017-04-17 2017-05-08 2017-06-21 2017-07-19 2017-08-18 2017-09-22 2017-10-27 2018-10-27 implementation and school Based Selection International Implementation grant utilization evaluation INDIVIDUAL CONSULTANTS Page 8