PROCUREMENT PLAN (Textual Part) Project information: Burkina Faso-WAPP North Core Regional Interconnector Project- P162933 Project Implementation agency: SONABEL Date of the Procurement Plan: December 31st, 2018 Period covered by this Procurement Plan: from January 2019 – to June 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Décret N°2017-00049/PRES/PM/MINEFID du 01/02/2017 portant procédures de passation, d’exécution et de règlement des marchés publics et des délégations de service publics au Burkina Faso, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. The National Bidding Document clause allowed to reject all bid when arithmetic error is 15% on + or – of original bid is not applied to the project. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable Works: is not applicable. PROCUREMENT Western Africa : North Core/Dorsale Nord Regional Power Interconnector Project PLAN General Information Country: Western Africa Bank’s Approval Date of the Original Procurement Plan: 2019-06-20 2019-07-15 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162933 GPN Date: 2019-04-09 Project Name: North Core/Dorsale Nord Regional Power Interconnector Project Loan / Credit No: IDA / D3910, IDA / 63390, IDA / 63400, IDA / 63420 Executing Agency(ies): Project Management Unit for North Core / Dorsale Nord Regional Power Interconnector Project WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WAPP-NC-REF-1A-TL-002 / 697 Km of 330 kV Open - Single Stage - One En attente Transmission Lines in Niger IDA / 63390 A priori Appel d'offres 0.00 2019-07-10 2019-10-14 2019-11-04 2019-07-29 2020-01-27 2020-03-23 2020-06-03 2023-02-20 International Envelope d'exécution (316 Km),Burkina Faso (381 Km) and Benin (12 Km) WAPP-NC-REF-1B-SS-003 / Open - Single Stage - One En attente Substations and dispatching IDA / 63400 A priori Appel d'offres 0.00 2019-07-10 2019-10-14 2019-11-04 2019-07-29 2020-01-27 2020-03-23 2020-06-03 2023-02-20 International Envelope d'exécution centers in Niger and Benin WAPP-NC-REF-1A-TL-001 / Lot 1-A-TL: 330 kV Open - Single Stage - One En attente Transmission Lines IDA / 63420 A priori Appel d'offres 0.00 2019-07-10 2019-10-14 2019-11-04 2019-07-29 2020-01-27 2020-03-23 2020-06-03 2023-02-20 International Envelope d'exécution NIGERIA: Birnin- Nigeria/Niger Border (62 km) GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WAPP-NC-REF-3B-003 / Single Stage - One En attente Other Software licences & IDA / D3910 A posteriori Appel d'offres Open - National 0.00 2020-01-06 2020-01-11 2020-02-22 2020-03-08 2020-04-12 2020-07-11 Envelope d'exécution IT Services outsourcing WAPP-NC-REF-3B-004 / Supply of VOIP Communication, Single Stage - One En attente IDA / D3910 A posteriori Appel d'offres Open - National 0.00 2019-12-08 2019-12-13 2020-01-24 2020-02-08 2020-03-14 2020-06-12 Videoconference, Projectors, Envelope d'exécution media & Interpretation équipments WAPP-NC-REF-3B-001 / Supply of vehicles for Abuja Single Stage - One En attente IDA / D3910 A posteriori Appel d'offres Open - National 0.00 2019-07-15 2019-07-20 2019-08-31 2019-09-15 2019-10-20 2020-01-18 HQ First batch (07 SUV + Envelope d'exécution 01 Double Cabin Pickup) NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WAPP-NC-REF-4A2-002 / EX-NC1 Consultant Services Sélection fondée for the preparation and sur les Open - En attente Negotiation of PPAs (Power IDA / D3910 A posteriori 0.00 2019-06-14 2019-07-12 2019-09-22 2019-11-06 2019-12-04 2020-06-01 qualifications des International d'exécution Purchase Agreements) and consultants TSAs (Transmission Service Agreements) WAPP-NC-REF-3B-006 / EX- Sélection au Open - En cours IDA / D3910 A posteriori 0.00 2019-06-14 2019-07-05 2019-09-16 2019-10-16 2019-11-06 2019-11-28 2019-12-24 2022-06-30 NC2 External auditor moindre coût International d'exécution WAPP-NC-REF-C3B2-001 / OE-NC1 Recruitment Owner's Engineer for the Sélection fondée Open - En cours WAPP North Core Project IDA / D3910 A priori sur la qualité et 0.00 2019-05-19 2019-05-21 2019-05-25 2019-05-27 2019-05-29 2019-06-02 2019-06-05 2024-01-05 International d'exécution (Project Management, le coût Supervision of Works, Support ESMP). WAPP-NC-REF-4A2-001 / Line route , Environmental and Social Impact Sélection fondée Open - En cours Assessment (ESIA) Study for IDA / D3910 A priori sur la qualité et 0.00 2019-06-10 2019-07-08 2019-11-01 2019-12-31 2020-02-20 2020-05-17 2020-06-22 2021-09-25 International d'examen the 330 kV Double Circuit le coût Median Interconnector Project WAPP-NC-REF-A42-003 / Feasibility study and Sélection fondée preparation of bidding Open - En cours IDA / D3910 A priori sur la qualité et 0.00 2019-06-10 2019-07-08 2019-11-01 2019-12-31 2020-02-20 2020-05-17 2020-06-22 2021-11-24 documents of the 330 kV International d'examen le coût Double Circuit Median Interconnector Project. WAPP-NC-4A2-004 / Update Sélection fondée of the inventory of affected sur les En attente IDA / D3910 A posteriori Open - National 0.00 2019-06-14 2019-07-12 2019-09-09 2019-10-24 2019-11-21 2020-03-20 property and the list of qualifications des d'exécution affected persons in Nigeria consultants WAPP-NC-4A2-005 / Update Sélection fondée of the inventory of affected sur les En attente IDA / D3910 A posteriori Open - National 0.00 2019-06-14 2019-07-12 2019-09-09 2019-10-24 2019-11-21 2020-03-20 property and the list of qualifications des d'exécution affected persons in Benin consultants WAPP-NC-4A2-006 / Update Sélection fondée of the inventory of affected sur les En attente IDA / D3910 A posteriori Open - National 0.00 2019-06-14 2019-07-12 2019-09-09 2019-10-24 2019-11-21 2020-03-20 property and the list of qualifications des d'exécution affected persons in Niger consultants WAPP-NC-4A2-007 / Update Sélection fondée of the inventory of affected sur les En attente property and the list of IDA / D3910 A posteriori Open - National 0.00 2019-06-14 2019-07-12 2019-09-09 2019-10-24 2019-11-21 2020-03-20 qualifications des d'exécution affected persons in Burkina consultants Faso INDIVIDUAL CONSULTANTS Page 2