Summarized Procurement Plan Ho Chi Minh City Green Transport Development Project I. General 1. Bank’s approval Date of the procurement Plan: October 2018 2. Date of General Procurement Notice: 3. Period covered by this procurement plan: Project period II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. Works (including Turnkey, Supply From 10 million Procurement risk & Installation of Plant and rating of Substantial Equipment, and PPP 2. Goods, Information Technology and From 2 million Non-Consulting Services 2. Prequalification. Bidders shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines: Not applicable_ 3. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of 66.18 2 No Prior the ICB (Works) Summary of 24.98 4 No Prior the ICB (Goods) Summary of 2.5 2 No Post the NCB (Works) July 9, 2010 Summary of 2.3 6 No Post the NCB (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Consultants: Firms From 1 million Procurement risk 2. Consultants: Individual From 0.3 million rating of Substantial 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 22.93 11 Prior and number of Post contracts that will be let under QCBS Summary of 0.86 8 Post CQS, IC number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Vietnam : Ho Chi Minh City Green Transport Development PLAN General Information Country: Vietnam Bank’s Approval Date of the Original Procurement Plan: 2019-01-02 2020-03-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P126507 GPN Date: Project Name: Ho Chi Minh City Green Transport Development Loan / Credit No: IDA / 56540 Executing Agency(ies): Transportation Works Construction Investment Project Management Authority of HCMC WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BRT2-CS9 / Study on re- organization of the city-wide bus network and preparation Quality And Cost- Open - IDA / 56540 Institutional Strengthening Prior 1,500,000.00 0.00 Under Review 2019-03-19 2019-04-28 2019-06-27 2019-09-10 2019-10-20 2020-01-02 2020-02-13 2021-02-12 of an action plan to improve Based Selection International service efficiency and quality of the existing bus system. BRT1-CS4 / consulting Bus Rapid Transit Corridor Quality And Cost- Open - Under service for project IDA / 56540 Prior 2,000,000.00 0.00 2019-01-03 2019-01-04 2019-02-12 2019-03-28 2019-04-13 2019-06-27 2019-08-06 2019-10-19 2019-11-23 2023-07-20 Development Based Selection International Implementation implementation support BRT1-CS8 / consulting Bus Rapid Transit Corridor Quality And Cost- Open - Under service for marketing and IDA / 56540 Prior 1,000,000.00 0.00 2019-02-18 2019-08-16 2019-03-30 2019-10-13 2019-05-29 2019-08-12 2019-09-21 2019-12-04 2020-01-08 2022-03-08 Development Based Selection International Implementation public communication DD-CS1 / Consulting services for detailed design, cost estimates preparation, Bus Rapid Transit Corridor Quality And Cost- Open - Pending IDA / 56540 Prior 3,982,435.00 0.00 2013-12-30 2013-12-30 2014-08-25 2014-10-31 2015-02-05 2015-07-24 2015-07-27 2020-08-31 and procurement support for Development Based Selection International Implementation goods and civil works packages Page 1 INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2