Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: September 24, 2013] 2. Date of General Procurement Notice: July 12, 2013 3. Period covered by this procurement plan: The procurement period of project covered from year September 2013 to May 2018. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 1,500,000 All 2. NCB (Goods) Above US$ 1,500,000 All 3. ICB (Works) Above US$ 5 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 500,000 All [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Summary of the Procurement Packages planned during the first 18 months after project effectiveness [See Procurement Plan] III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) All 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Consultancy Assignments with Selection Methods and Time Schedule [See Procurement Plan] PROCUREMENT Iraq : Transport Corridors Project PLAN General Information Country: Iraq Bank’s Approval Date of the Original Procurement Plan: 2017-09-11 2019-04-16 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P131550 GPN Date: Project Name: Transport Corridors Project Loan / Credit No: IBRD / 83220 Executing Agency(ies): Ministry of Construction and Housing of KRG WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TCP.W.KRG.B.1 / Construction of the road Open - Single Stage - One IBRD / 83220 Prior Request for Bids 53,648,662.10 Signed between Gursheen and International Envelope Suheila intersection GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TCP-CON-QCBS-KRG-A7 / Engineering Supervision Quality And Cost- Open - Under IBRD / 83220 Prior 0.00 2015-02-01 2016-05-29 2016-07-24 2016-10-10 2016-10-10 2017-01-11 2017-04-25 2019-12-31 Services - Road section Based Selection International Implementation between Girshen & Suheila TCP-CON-QCBS-KRG-B2-D Consultant / Technical Assistance - Open - Under IBRD / 83220 Post Qualification 0.00 2018-06-28 2018-07-19 2018-09-01 2018-10-01 2018-11-05 2019-05-04 Information and International Implementation Selection Communication System TCP-CON-QCBS-KRG-B2-E- Consultant H / Training and Study Open - Under IBRD / 83220 Post Qualification 0.00 2018-07-28 2018-08-18 2018-10-01 2018-10-31 2018-12-05 2019-06-03 Tours for managerial and International Implementation Selection technical staff of GDRB TCP-CON-C2-A / Technical Quality And Cost- Open - IBRD / 83220 Prior 0.00 Canceled 2017-05-13 2017-09-05 2018-05-07 2018-08-01 2018-08-31 2018-10-05 2018-11-09 2019-11-09 Audit Based Selection International Page 1 TCP-CON-C2-B / FInancial Least Cost Open - Under IBRD / 83220 Post 0.00 2017-10-01 2017-10-22 2017-12-05 2018-01-02 2018-02-01 2018-03-08 2018-04-12 2018-10-09 Audit Selection International Implementation TCP-CON-QCBS-KRG-B2-A- C / Technical Assistance for Quality And Cost- Open - the development of a Service IBRD / 83220 Post 0.00 Canceled 2018-07-01 2018-07-22 2018-09-04 2018-10-02 2018-11-01 2018-12-06 2019-01-10 2020-01-10 Based Selection International Manual for Road Maintenance TCP-CON-C2-AA / Quality And Cost- Open - Pending Technical Audit ( of the IBRD / 83220 Prior 0.00 2019-04-04 2019-04-25 2019-06-08 2019-07-06 2019-08-05 2019-09-09 2019-10-14 2020-10-13 Based Selection International Implementation project ) INDIVIDUAL CONSULTANTS Page 2