PROCUREMENT PLAN (Textual Part) Project information: Sao Tome and Principe - WACA Resilience Investment Project - P162337 Project Implementation agency: Ministry of Public Works and Natural Resources, Directorate General of Environment Date of the Procurement Plan: July 2017 Period covered by this Procurement Plan: July 1st 2017 to June 30th, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Regulamento de Licitação e Contratações Publicas such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information.: Not Applicable PROCUREMENT Western Africa : Investments towards Resilient Management of GCLME PLAN General Information Country: Western Africa Bank’s Approval Date of the Original Procurement Plan: 2018-01-08 2020-01-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162337 GPN Date: 2017-12-29 Project Name: Investments towards Resilient Management of GCLME Loan / Credit No: IDA / V1160, IDA / 62140, TF / A7131, IDA / D2870 Executing Agency(ies): GENERAL DIRECTORATE FOR ENVIRONMENT AND CLIMATE WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-WACA -44429-CW-RFQ / Travaux d'amenagement, de Component 4: National Single Stage - One En cours cloisonnement de bureaux et IDA / V1160 A posteriori Demande de prix Limited 140,000.00 0.00 2018-02-10 2018-04-05 2018-05-20 Coordination Envelope d'exécution de realisation de plaquettes d'identification des bureaux BJ-WACA -103686-CW-RFQ Component 3: Strengthening / Réhabiliter/aménager la Single Stage - One En attente TF / A7131 National Physical and Social A posteriori Demande de prix Limited 50,000.00 0.00 2019-04-20 2019-06-15 2019-12-12 mare aux crocodiles de Envelope d'exécution Investments Tannou (Aplahoué) BJ-WACA -95485-CW-RFQ / Réaliser les travaux de Component 3: Strengthening Single Stage - One En attente matérialisation naturelle TF / A7131 National Physical and Social A posteriori Demande de prix Limited 120,000.00 0.00 2019-05-07 2019-07-02 2019-08-31 Envelope d'exécution (plantation de haies) des Investments limites des ACCB BJ-WACA -95488-CW-RFQ / Travaux de construction Component 3: Strengthening d'infrastructures (bâtiments Single Stage - One En attente TF / A7131 National Physical and Social A posteriori Demande de prix Limited 140,000.00 0.00 2019-06-22 2019-08-17 2020-02-13 servant de siège) au profit Envelope d'exécution Investments des associations de gestion des ACCB BJ-WACA -117475-CW-DIR / Travaux d'urgence de Component 3: Strengthening Passation de dragage et du refoulement En attente IDA / 62140 National Physical and Social A posteriori marché de gré à Direct 800,000.00 0.00 2019-06-05 2019-06-10 2019-07-15 2020-01-11 des sédiments dans la berge d'exécution Investments gré sud du fleuve Mono à Grand Popo BJ-WACA -125526-CW-RFQ Component 3: Strengthening / Travaux de sécurisation de Single Stage - One En attente TF / A7131 National Physical and Social A posteriori Demande de prix Limited 40,000.00 0.00 2019-08-17 2019-10-12 2020-04-09 la mare aux crocodiles de Envelope d'exécution Investments Tannou BJ-WACA -125527-CW-RFQ Component 3: Strengthening / Travaux de réalisation de Single Stage - One En attente TF / A7131 National Physical and Social A posteriori Demande de prix Limited 80,000.00 0.00 2019-08-17 2019-10-12 2020-04-09 cinq (05) forages aux profits Envelope d'exécution Investments des populations de Tannou GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 BJ-WACA -35451-GO-RFQ / Acquisition de fourniture de Component 6: National Single Stage - One En cours IDA / V1160 A posteriori Demande de prix Limited 20,000.00 0.00 2017-11-15 2018-01-08 2018-01-28 bureaux et de consommables Coordination Envelope d'exécution informatiques BJ-WACA -35464-GO-RFQ / Acquisition d'un logiciel de gestion comptable, financière Component 6: National Single Stage - One En attente IDA / V1160 A posteriori Demande de prix Limited 25,000.00 0.00 2017-11-15 2017-12-28 2018-12-28 et de passation de marché Coordination Envelope d'exécution et assistance à l'utilisation du logiciel BJ-WACA -44426-GO-RFQ / Acquisition d'un vehicule Component 4: National Single Stage - One En attente IDA / V1160 A posteriori Demande de prix Limited 54,000.00 0.00 2018-03-01 2018-04-26 2018-07-25 pick up 4x4 double cabine Coordination Envelope d'exécution au profit du projet BJ-WACA -44423-GO-RFQ / Fourniture, installation et Component 4: National Single Stage - One En attente mise en service d'un groupe IDA / V1160 A posteriori Demande de prix Limited 30,000.00 0.00 2018-02-08 2018-04-05 2018-05-05 Coordination Envelope d'exécution electrogene insonorise de 100KVA avec inverseur BJ-WACA -44425-GO-RFQ / Component 4: National Single Stage - One En attente Acquisition de mobiliers de IDA / V1160 A posteriori Demande de prix Limited 40,000.00 0.00 2018-02-09 2018-04-04 2018-05-04 Coordination Envelope d'exécution bureau au profit du projet BJ-WACA -44424-GO-RFQ / Acquisition d'équipements et de logiciel pour Component 2: Strengthening Single Stage - One En cours l'opérationnalisation du IDA / V1160 the Policy and Institutional A posteriori Demande de prix Limited 76,000.00 0.00 2018-02-26 2018-04-23 2018-10-20 Envelope d'exécution système géographique de Framework l'information environnementale BJ-WACA -52702-GO-RFQ / Acquisition de matériels Component 4: National Single Stage - One IDA / V1160 A posteriori Demande de prix Limited 40,000.00 35,234.93 Signé 2018-03-13 2018-05-08 2018-06-07 informatiques au profit du Coordination Envelope projet BJ-WACA -83177-GO-RFQ / Acquisition de fournitures de Component 4: National Single Stage - One En attente bureau et de consommables IDA / D2870 A posteriori Demande de prix Limited 30,000.00 0.00 2018-12-02 2019-01-27 2019-02-26 Coordination Envelope d'exécution informatiques au profit du projet BJ-WACA -83182-GO-RFQ / Acquisition de matériels et équipements (Audio Component 4: National Single Stage - One En attente Visioconférence, Copieur, IDA / D2870 A posteriori Demande de prix Limited 30,000.00 0.00 2018-12-02 2019-01-27 2019-02-26 Coordination Envelope d'exécution Digital Sender, armoires de rangement) de bureau au profit du projet BJ-WACA -83163-GO-RFQ / Acquisition d'équipements techniques (Serveur, Drônes, Component 2: Strengthening Passation de GPD,...) pour En attente IDA / 62140 the Policy and Institutional A posteriori marché de gré à Direct 80,000.00 0.00 2018-12-09 2018-12-14 2019-01-18 2019-07-17 l'opérationnalisation du d'exécution Framework gré système géographique de l'information environnementale BJ-WACA -83189-GO-RFQ / Passation de Acquisition et mise en Component 4: National En attente IDA / D2870 A posteriori marché de gré à Direct 20,000.00 0.00 2018-12-16 2018-12-21 2019-01-25 2019-03-26 service d'un logiciel de suivi Coordination d'exécution gré & Evaluation Page 2 BJ-WACA -83175-GO-RFQ / Acquisition de matériels Component 2: Strengthening Single Stage - One En attente roulants (véhicules et motos) IDA / D2870 the Policy and Institutional A posteriori Demande de prix Limited 480,000.00 0.00 2018-12-21 2019-02-15 2019-08-14 Envelope d'exécution au profit du Projet Waca et Framework de l'ABE BJ-WACA -83180-GO-RFQ / Acquisition de barques motorisées, et des pirogues Component 2: Strengthening Single Stage - One En attente pour appuyer la mise en TF / A7131 the Policy and Institutional A posteriori Demande de prix Limited 95,000.00 0.00 2018-12-14 2019-02-08 2019-05-09 Envelope d'exécution œuvre du projet à Grand- Framework Popo, Avlo, Djègbadji et Toho. BJ-WACA -95500-GO-RFQ / Edition et multiplication de documents (lignes directrices pour les EIE, la planification Component 2: Strengthening spatiale de la zone côtière et Single Stage - One En attente IDA / 62140 the Policy and Institutional A posteriori Demande de prix Limited 60,000.00 0.00 2019-02-25 2019-04-22 2019-06-21 les infrastructures, document Envelope d'exécution Framework de stratégie sectorielle relative à la zone côtière et les textes d'application de la loi littorale) BJ-WACA -83174-GO-RFQ / Acquisition de logiciel pour Component 2: Strengthening Passation de l'opérationnalisation du En attente IDA / 62140 the Policy and Institutional A posteriori marché de gré à Direct 20,000.00 0.00 2019-05-02 2019-05-07 2019-06-11 2019-08-10 système géographique de d'exécution Framework gré l'information environnementale BJ-WACA -83176-GO-RFQ / Acquisition d'équipements techniques de suivi des indicateurs biologiques et de Component 2: Strengthening Passation de pollution (Indicateurs En attente IDA / 62140 the Policy and Institutional A priori marché de gré à Direct 360,000.00 0.00 2019-05-15 2019-05-20 2019-06-24 2019-12-21 chimiques et biologiques, d'exécution Framework gré mallettes d'indicateurs, indicateurs de stérilisation, ...) au profit de l'observation de suivi de l'environnement BJ-WACA -95501-GO-RFB / Acquisition d'équipements informatiques (ordinateurs, imprimantes, photocopieurs, etc.) au profit de l'ABE pour Component 2: Strengthening Single Stage - One En attente assurer un suivi des impacts IDA / 62140 the Policy and Institutional A posteriori Appel d'offres Open - National 420,000.00 0.00 2019-05-06 2019-05-11 2019-06-22 2019-07-22 2019-08-26 2020-02-22 Envelope d'exécution environnementaux et le suivi Framework de la mise en œuvre des plans d'aménagement des ACCB et des AaGRs par les communes BJ-WACA -129162-GO-RFQ / Fourniture et installation Component 4: National Single Stage - One En attente de bureaux incubateurs IDA / 62140 A posteriori Demande de prix Limited 14,000.00 0.00 2019-09-04 2019-10-28 2019-11-12 Coordination Envelope d'exécution (Cubecles) dans les deux bâtiments de l'UIGP BJ-WACA -129254-GO-RFQ / Fourniture et installation Component 4: National En attente IDA / 62140 A posteriori Demande de prix 19,500.00 0.00 2019-09-11 2019-11-04 2019-11-19 de mobiliers de bureau au Coordination d'exécution profit de l'UIGP NON CONSULTING SERVICES Page 3 Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-WACA -44428-NC-RFQ / Acquisition d'equipement pour le cablage internet, Component 4: National Single Stage - One En cours IDA / V1160 A posteriori Demande de prix Limited 65,000.00 0.00 2018-02-20 2018-04-17 2018-06-01 abonnement et mise en Coordination Envelope d'exécution place du reseau intranet dans les locaux de l'UGP BJ-WACA -82969-NC-RFQ / Recrutement d'une agence de Component 4: National Single Stage - One En attente gardiennage pour la IDA / D2870 A posteriori Demande de prix Limited 12,000.00 0.00 2018-12-14 2019-02-08 2020-02-08 Coordination Envelope d'exécution surveillance des bureaux du siège du projet WACA BJ-WACA -95492-NC-RFQ / Sélection d'un prestataire Component 4: National Single Stage - One En attente IDA / 62140 A posteriori Demande de prix Limited 5,000.00 0.00 2019-02-09 2019-04-06 2020-04-05 pour la maintenance des Coordination Envelope d'exécution climatiseurs BJ-WACA -95494-NC-RFQ / Assurance Santé du Component 4: National Single Stage - One En attente IDA / 62140 A posteriori Demande de prix Limited 40,000.00 0.00 2019-02-16 2019-04-13 2020-04-12 personnel du projet WACA Coordination Envelope d'exécution ResIP-Bénin BJ-WACA -95498-NC-RFQ / Component 4: National Single Stage - One En attente Maintenance des matériels IDA / 62140 A posteriori Demande de prix Limited 10,000.00 0.00 2019-02-25 2019-04-22 2020-04-21 Coordination Envelope d'exécution informatiques et électriques BJ-WACA -95496-NC-RFQ / Assurance santé du Component 4: National Single Stage - One En attente personnel et assurance des IDA / 62140 A posteriori Demande de prix Limited 32,000.00 0.00 2019-04-20 2019-06-15 2020-06-14 Coordination Envelope d'exécution matériels roulants du projet WACA ResIP-Bénin BJ-WACA -82869-NC-RFQ / Recruter une agence événementielle et de communication pour la mise en place de la logistique Component 3: Strengthening (bâches, stands, chaises, Single Stage - One En attente TF / A7131 National Physical and Social A posteriori Demande de prix Limited 60,000.00 0.00 2019-06-17 2019-08-12 2019-08-22 podium, sonorisation, Envelope d'exécution Investments reportage, etc.) dans le cadre du lancement technique du volet AaGRs sous-financement GEF du projet WACA-Bénin BJ-WACA -114367-NC-RFQ / conception des maquettes des projets WACA et PFCB (Posters, Kakémonos, Component 4: National Single Stage - One En attente IDA / 62140 A posteriori Demande de prix Limited 3,600.00 0.00 2019-05-17 2019-07-12 2020-07-11 prospectus, flyers cartables) Coordination Envelope d'exécution pour la journée porte ouverte de la Banque Mondiale. BJ-WACA -114368-NC-RFQ / Impression des support de communication des projets WACA et PFCB (Posters, Component 4: National Single Stage - One En attente IDA / 62140 A posteriori Demande de prix Limited 3,900.00 0.00 2019-05-17 2019-07-12 2020-07-11 Kakémonos, prospectus, Coordination Envelope d'exécution flyers cartables) pour les journées porte ouverte de la Banque mondiale. Page 4 BJ-WACA -151438-CS-CDS / Inspection approfondie sous- Component 3: Strengthening Passation de marine et de surface des En attente TF / A7131 National Physical and Social A posteriori marché de gré à Direct 600,000.00 0.00 2020-01-03 2020-01-08 2020-02-17 2020-03-18 installations abandonnées sur d'exécution Investments gré le champ pétrolifère de Sèmè au large du Bénin CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-WACA -44408-CS-CQS / Sélection fondée Selection d'un cabinet pour Component 4: National sur les En cours IDA / V1160 A posteriori Open - National 16,000.00 0.00 2018-01-30 2018-02-06 2018-03-03 2018-04-02 2018-05-07 2018-06-06 le recrutement du personnel Coordination qualifications des d'examen cle du projet consultants BJ-WACA -82873-CS-LCS / Sélection d'un consultant pour la réalisation de l'audit Component 4: National Sélection au En attente financier et comptable de la IDA / 62140 A posteriori Open - National 60,000.00 0.00 2018-11-15 2018-12-06 2019-01-19 2019-02-16 2019-03-18 2019-04-22 2019-05-27 2019-06-26 Coordination moindre coût d'exécution phase de préparation et des exercices 2018 et 2019 du projet (4,3,1) BJ-WACA -82880-CS-CQS / Sélection d'un consultant pour l'élaboration de lignes Sélection fondée Component 2: Strengthening directrices pour des EIE sur les En attente IDA / 62140 the Policy and Institutional A posteriori Open - National 95,000.00 0.00 2018-11-20 2018-12-11 2019-01-24 2019-02-23 2019-03-30 2019-05-29 sectorielles (planification qualifications des d'exécution Framework spatiale de la zone côtière, consultants ouvrage de protection du littoral etc) BJ-WACA -82882-CS-CQS / Sélection fondée Recrutement d'un consultant Component 2: Strengthening sur les En attente pour l'élaboration des projets IDA / 62140 the Policy and Institutional A posteriori Open - National 80,000.00 0.00 2018-11-19 2018-12-10 2019-01-23 2019-02-22 2019-03-29 2019-06-27 qualifications des d'exécution des textes d'application de la Framework consultants loi sur le littoral BJ-WACA -82891-CS-CQS / Recrutement d'un consultant pour la réalisation de l'étude Sélection fondée Component 3: Strengthening pour identifier les sites sur les En attente TF / A7131 National Physical and Social A posteriori Open - National 95,000.00 0.00 2018-11-20 2018-12-11 2019-01-24 2019-02-23 2019-03-30 2019-04-29 d'intervention du GEF et la qualifications des d'exécution Investments faisabilité technique et consultants environnementale des investissements à réaliser BJ-WACA -82899-CS-CQS / Recrutement d'un consultant Sélection fondée Component 3: Strengthening pour la réalisation de l'étude sur les En attente TF / A7131 National Physical and Social A posteriori Open - National 95,000.00 0.00 2018-11-19 2018-12-10 2019-01-23 2019-02-22 2019-03-29 2019-04-28 d'état des lieux de la plate qualifications des d'exécution Investments forme pétrolière de Sèmè- consultants Kpodji BJ-WACA -82978-CS-QCBS / Sélection d'un consultant pour l'assistance technique Component 2: Strengthening Sélection fondée Open - En attente pour l'élaboration des TF / A7131 the Policy and Institutional A posteriori sur la qualité et 291,000.00 0.00 2018-11-20 2018-12-11 2019-01-24 2019-02-21 2019-03-23 2019-04-27 2019-06-01 2019-08-30 International d'exécution curicula et la mise en Framework le coût œuvre du programme de recherche sur la zone côtière Page 5 BJ-WACA -83015-CS-QCBS / Sélection d'un consultant pour la réalisation de l'étude Component 3: Strengthening Sélection fondée de faisabilité pour la Open - En cours TF / A7131 National Physical and Social A priori sur la qualité et 2,000,000.00 0.00 2018-12-03 2018-12-24 2019-02-06 2019-03-06 2019-04-05 2019-05-10 2019-06-14 2019-12-11 protection à long termes de International d'exécution Investments le coût la zone côtière transfrontalière entre le Bénin et le Togo BJ-WACA -83025-CS-CQS / Sélection fondée Component 3: Strengthening Étude de référence socio sur les En attente TF / A7131 National Physical and Social A posteriori Open - National 40,000.00 0.00 2018-10-30 2018-11-20 2019-01-03 2019-02-02 2019-03-09 2019-06-07 économique des ménages qualifications des d'exécution Investments bénéficiaires des AaGRs consultants BJ-WACA -83322-CS-QCBS / Sélection d'un cabinet pour la réalisation de l'EIES pour Component 3: Strengthening Sélection fondée Open - En attente la protection à long termes IDA / D2870 National Physical and Social A posteriori sur la qualité et 640,000.00 0.00 2019-04-15 2019-05-06 2019-06-19 2019-07-17 2019-08-16 2019-09-20 2019-10-25 2020-02-22 International d'exécution de la zone côtière Investments le coût transfrontalière entre le Bénin et le Togo BJ-WACA -95368-CS-QCBS / Recrutement de consultants Component 2: Strengthening Sélection fondée pour la réalisation de Open - En attente IDA / 62140 the Policy and Institutional A posteriori sur la qualité et 250,000.00 0.00 2019-02-04 2019-02-25 2019-04-10 2019-04-20 2019-05-05 2019-05-30 2019-07-04 2019-10-02 l'évaluation environnementale International d'exécution Framework le coût stratégique pour la zone côtière BJ-WACA -95377-CS-QCBS / Recrutement d'un Consultant pour le Component 2: Strengthening Sélection fondée renforcement du système Open - En attente IDA / 62140 the Policy and Institutional A posteriori sur la qualité et 300,000.00 0.00 2019-02-11 2019-02-26 2019-03-18 2019-03-23 2019-04-02 2019-04-17 2019-05-16 2019-08-14 informatisé de suivi des International d'exécution Framework le coût évaluations environnementales (Manuel suivi PGES, Dr-PGES) BJ-WACA -95420-CS-CQS / Recrutement d'un cabinet Sélection fondée Component 2: Strengthening pour la réalisation d'une sur les En attente TF / A7131 the Policy and Institutional A posteriori Open - National 50,000.00 0.00 2019-02-14 2019-03-01 2019-03-23 2019-04-04 2019-05-09 2019-07-08 étude monographique des qualifications des d'exécution Framework ACCB de Djègbadji-Avlékété consultants et du Chenal Gbaga BJ-WACA -95430-CS-CQS / Recrutement d'un cabinet Sélection fondée Component 2: Strengthening pour l'élaboration des plans sur les En attente TF / A7131 the Policy and Institutional A posteriori Open - National 40,000.00 0.00 2019-02-11 2019-02-26 2019-03-13 2019-03-23 2019-04-27 2019-06-26 de gestion des nouvelles qualifications des d'exécution Framework ACCB de Djègbadji-Avlékété consultants et Chenal Gbaga BJ-WACA -95467-CS-CQS / Recrutement d'un Cabinet pour la réalisation de l'étude Sélection fondée Component 3: Strengthening de cartographie des sites de sur les En attente TF / A7131 National Physical and Social A posteriori Open - National 40,000.00 0.00 2019-02-20 2019-03-07 2019-03-22 2019-04-06 2019-05-05 2019-08-03 carrières de sable et de qualifications des d'exécution Investments graviers abandonnés dans la consultants Réserve de Biosphère Transfrontalière BJ-WACA -83024-CS-CQS / Sélection des consultants Component 3: Strengthening Sélection dans le En attente (ONG) pour le TF / A7131 National Physical and Social A posteriori cadre d'un budget Open - National 60,000.00 0.00 2019-03-10 2019-03-31 2019-05-14 2019-06-11 2019-07-11 2019-08-15 2019-09-19 2020-09-18 d'exécution développement et la mise en Investments déterminé place des AaGRs Page 6 BJ-WACA -103678-CS-CQS / Recrutement d'un cabinet (firme) pour la Sélection fondée Component 3: Strengthening reconnaissance et sur les En attente IDA / 62140 National Physical and Social A posteriori Open - National 60,000.00 0.00 2019-03-24 2019-04-14 2019-05-28 2019-06-27 2019-08-01 2020-01-28 délimitation sommaire de qualifications des d'exécution Investments l'emprise de la zone consultants d'intervention physiques et verts du projet BJ-WACA -103682-CS-CQS / Recrutement d'un Sélection fondée Consultant chargé de Component 2: Strengthening sur les En attente l'élaboration du document de IDA / 62140 the Policy and Institutional A posteriori Open - National 20,000.00 0.00 2019-04-08 2019-04-29 2019-06-12 2019-07-12 2019-08-16 2020-02-12 qualifications des d'exécution stratégie sectorielle relative Framework consultants à la gestion durable de la zone côtière BJ-WACA -103674-CS-CQS / Recrutement d'un consultant pour l'élaboration Sélection fondée Component 2: Strengthening d'un plan de formation des sur les En attente IDA / 62140 the Policy and Institutional A posteriori Open - National 30,000.00 0.00 2019-08-19 2019-09-09 2019-10-23 2019-11-22 2019-12-27 2020-06-24 cadres techniques de l'ABE qualifications des d'exécution Framework (formations techniques sur consultants les EIE, modélisation, suivi des polluants) BJ-WACA -95414-CS-CQS / Sélection fondée Sélection d'un consultant Component 2: Strengthening sur les En attente pour l'actualisation du TF / A7131 the Policy and Institutional A posteriori Open - National 95,000.00 0.00 2019-04-29 2019-05-14 2019-06-03 2019-06-13 2019-07-07 2019-10-05 qualifications des d'exécution Schéma directeur Framework consultants d'aménagement du littoral BJ-WACA -95426-CS-CQS / Recrutement d'un cabinet Sélection fondée pour actualiser les plans de Component 2: Strengthening sur les En attente gestion du site Ramsar 1017 TF / A7131 the Policy and Institutional A posteriori Open - National 80,000.00 0.00 2019-04-15 2019-04-30 2019-05-15 2019-05-25 2019-06-14 2019-09-12 qualifications des d'exécution (fleuve Couffo, Lac Ahémé, Framework consultants Chenal Aho et lagune côtière) BJ-WACA -108269-CS-QCBS / Etude d'inspection de Component 2: Strengthening Sélection fondée Open - En attente surface des infrastructures TF / A7131 the Policy and Institutional A posteriori sur la qualité et 400,000.00 0.00 2019-06-03 2019-06-24 2019-08-07 2019-09-04 2019-10-04 2019-11-08 2019-12-13 2020-12-12 International d'exécution abandonnées sur le champ Framework le coût pétrolifère de Sèmè BJ-WACA -149245-CS-CQS / Etude de faisabilité technico-économique et Sélection fondée Component 3: Strengthening contrôle de la réhabilitation sur les En attente TF / A7131 National Physical and Social A posteriori Open - National 19,000.00 0.00 2019-12-11 2019-12-21 2020-01-11 2020-01-21 2020-02-14 2020-08-12 de la mare aux crocodiles et qualifications des d'exécution Investments la réalisation de 5 forages à consultants Tannou dans la commune d’Aplahoué INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-WACA -35471-CS-INDV / Sélection d'un Consultant pour la réalisation de l'étude Component 3: Strengthening En cours d'impact environnementale IDA / V1160 National Physical and Social A posteriori Individuel Limited 17,000.00 0.00 2017-11-13 2017-11-18 2017-12-09 2018-01-13 2018-02-12 d'exécution relative à l'ouverture souple Investments de l'embouchure du fleuve Mono Page 7 BJ-WACA -35482-CS-INDV / Sélection d'un Consultant pour l'élaboration du cadre procédural de gestion Component 4: National En cours IDA / V1160 A posteriori Individuel Limited 17,000.00 0.00 2017-11-13 2017-11-18 2017-12-09 2018-01-13 2018-02-12 durable des ressources Coordination d'exécution naturelles des Aires de Conservation Communautaire de la Biodiversité (ACCB) BJ-WACA -35483-CS-INDV / Sélection d'un consultant Component 6: National En cours IDA / V1160 A posteriori Individuel Limited 17,000.00 0.00 2017-11-20 2017-11-23 2017-12-14 2018-01-18 2018-01-21 pour l'élaboration du manuel Coordination d'exécution d'exécution du projet BJ-WACA -35487-CS-INDV / Sélection d'un consultant Component 6: National En cours IDA / V1160 A posteriori Individuel Limited 16,000.00 0.00 2017-11-15 2017-11-18 2017-12-09 2018-01-13 2018-02-12 pour l'élaboration du manuel Coordination d'exécution de suivi évaluation du projet BJ-WACA -35491-CS-INDV / Recrutement d'un Component 6: National En attente IDA / V1160 A posteriori Individuel Limited 10,000.00 0.00 2017-11-13 2017-11-18 2017-12-09 2018-01-13 2018-07-12 consultant spécialiste en Coordination d'exécution gestion financière BJ-WACA -44416-CS-INDV / Selection d'un consultant pour l'elaboration du manuel Component 4: National En cours IDA / V1160 A posteriori Individuel Limited 16,000.00 0.00 2018-02-05 2018-02-10 2018-03-03 2018-04-07 2018-05-07 de procedures administrative Coordination d'exécution comptable et financiere,du projet BJ-WACA -43452-CS-INDV / Recrutement du personnel cle du projet: Coordonnateur, Chef projet GEF, Specialiste Component 4: National En cours en Passation des Marches, IDA / V1160 A priori Individuel Open 220,000.00 0.00 2018-02-20 2018-04-10 2018-05-01 2018-06-05 2018-08-04 Coordination d'exécution Specialiste en Gestion Financiere, Assistante de Direction, Un Conducteur de Vehicule Adminstratif BJ-WACA -44418-CS-INDV / Selection d'un consultant Component 4: National pour l'elaboration du manuel IDA / V1160 A posteriori Individuel Limited 16,000.00 15,945.98 Signé 2018-02-08 2018-02-13 2018-03-06 2018-04-10 2018-05-10 Coordination de procedures de passation des marches du projet BJ-WACA -44412-CS-INDV / Selection d'un cabinet pour Component 3: Strengthening la determination des valeurs IDA / V1160 National Physical and Social A posteriori Individuel Limited 19,000.00 0.00 Annulé 2018-02-04 2018-02-09 2018-03-02 2018-04-06 2018-05-06 de reference des indicateurs Investments du cadre de resultat du projet WACA BJ-WACA -82878-CS-CQS / Recrutement d'un expert pour l'élaboration du manuel de procédures et d'opérationnalisation de la Component 2: Strengthening En attente Cellule Nationale de Gestion IDA / 62140 the Policy and Institutional A posteriori Individuel Limited 35,000.00 0.00 2018-11-15 2018-11-20 2018-12-11 2019-01-15 2019-07-14 d'exécution du Littoral (Comité Framework intersectoriel sur la gestion intégrée de la zone côtière) et la formation de ses membres Page 8 BJ-WACA -82887-CS-INDV / Sélection d'un consultant Component 3: Strengthening pour l'élaboration du manuel En attente IDA / 62140 National Physical and Social A posteriori Individuel Limited 19,000.00 0.00 2018-11-19 2018-11-24 2018-12-15 2019-01-19 2019-02-18 de procédure technique pour d'exécution Investments l'ouverture de la bouche du Roy BJ-WACA -82975-CS-INDV / Recrutement de 5 chargés de mission (consultants Component 2: Strengthening individuels) pour la création En attente TF / A7131 the Policy and Institutional A posteriori Individuel Limited 120,000.00 0.00 2018-11-19 2018-11-24 2018-12-15 2019-01-19 2019-07-18 des ACCB, le suivi des d'exécution Framework AaGRs et l'appui à la mise en œuvre des plans de gestion du projet BJ-WACA -82976-CS-INDV / Sélection d'un consultant Component 2: Strengthening pour la réalisation de En attente TF / A7131 the Policy and Institutional A posteriori Individuel Open 60,000.00 0.00 2018-10-30 2018-12-18 2019-01-08 2019-02-12 2019-03-14 l'étude de référence des d'exécution Framework indicateurs du cadre de résultats du projet BJ-WACA -83521-CS-QCBS / Recrutement d'un Component 2: Strengthening Consultant pour la En attente IDA / 62140 the Policy and Institutional A posteriori Individuel Limited 95,000.00 0.00 2018-12-16 2018-12-21 2019-01-11 2019-02-15 2019-08-14 réalisation de l'étude de d'exécution Framework préparation du projet WACA- GCF BJ-WACA -82901-CS-CQS / Recrutement d'un consultant Component 4: National En attente pour l'élaboration de la IDA / 62140 A posteriori Individuel Limited 25,000.00 0.00 2018-12-09 2018-12-14 2019-01-04 2019-02-08 2019-04-09 Coordination d'exécution stratégie et du plan de communication du projet BJ-WACA -95384-CS-INDV / Recrutement d'un consultant pour la réalisation du diagnostic des Component 2: Strengthening plateformes des conventions En attente TF / A7131 the Policy and Institutional A posteriori Individuel Limited 40,000.00 0.00 2019-02-11 2019-02-16 2019-03-09 2019-04-13 2019-06-12 internationales relatives à d'exécution Framework l'environnement signées par le Bénin et élaboration un document pour leur opérationnalisation BJ-WACA -95470-CS-INDV / Recruter des conseillers Component 3: Strengthening En attente spécialisés en production TF / A7131 National Physical and Social A posteriori Individuel Limited 70,000.00 0.00 2019-03-29 2019-04-03 2019-04-18 2019-05-23 2020-05-22 d'exécution pour la mise en oeuvre des Investments plans de gestion des AaGR BJ-WACA -95397-CS-INDV / Recruter une assistance Component 2: Strengthening technique pour l'élaboration En attente TF / A7131 the Policy and Institutional A posteriori Individuel Limited 60,000.00 0.00 2019-04-08 2019-04-13 2019-05-04 2019-06-08 2019-08-07 des curricula pour le Master d'exécution Framework en Ingénierie Environnementale et Marine BJ-WACA -95468-CS-INDV / Recrutement d'un Component 2: Strengthening consultant pour En attente IDA / 62140 the Policy and Institutional A posteriori Individuel Limited 50,000.00 0.00 2019-06-17 2019-06-22 2019-07-07 2019-08-11 2019-11-09 l'actualisation des plans de d'exécution Framework gestion des ACCB Vodountô et Togbin - Adounko BJ-WACA -95493-CS-CQS / Sélection de Sélection d'un cabinet pour Component 4: National En attente IDA / 62140 A posteriori consultants par Direct 24,000.00 0.00 2019-03-07 2019-03-17 2019-05-21 2019-11-17 le recutement du personnel Coordination d'exécution entente directe complémentaire Page 9 BJ-WACA -95463-CS-CDS / Assistance tecchnique de WWF pour l'acquisition des Component 2: Strengthening Sélection de équipements, des logiciels, la En attente IDA / 62140 the Policy and Institutional A posteriori consultants par Direct 306,500.00 0.00 2019-05-02 2019-05-12 2019-06-26 2020-06-25 mise en place, la formation d'exécution Framework entente directe du personnel à l'utilisation et l'opérationnalisation du SGGIE BJ-WACA -95407-CS-INDV / Recrutement d'un Consultant Individuel pour Component 2: Strengthening En attente l'Assistance Technique à la TF / A7131 the Policy and Institutional A posteriori Individuel Limited 6,000.00 0.00 2019-05-15 2019-05-20 2019-06-10 2019-07-15 2020-01-11 d'exécution mise en œuvre des activités Framework du projet en lien avec le programme MAB-UNESCO BJ-WACA -109146-CS-INDV / Recrutement du personnel dédié au projet FC (SGF, SPM) et de spécialistes de l'UIGP (Spécialiste en Suivi- Component 4: National En cours Evaluation, Spécialiste en IDA / V1160 A priori Individuel Open 412,000.00 0.00 2019-04-15 2019-06-03 2019-06-24 2019-07-29 2019-09-27 Coordination d'exécution Communication, Spécialiste Sauvegarde Environnement, SSS, CG de l'UIGP, RTGIFC) et Agents d'app (ass. sécrétariat, 3 CVA) BJ-WACA -117472-CS-INDV / Recrutement Component 4: National En cours complémentaire du personnel IDA / 62140 A priori Individuel Open 33,600.00 0.00 2019-05-31 2019-07-19 2019-08-09 2019-09-13 2019-11-12 Coordination d'examen : Assistant du Responsable GEF BJ-WACA -117473-CS-INDV / Recrutement du personnel Component 4: National En cours IDA / 62140 A priori Individuel Open 52,800.00 0.00 2019-06-05 2019-07-24 2019-08-14 2019-09-18 2019-11-17 complémentaire de l'UIGP: Coordination d'exécution Chargée d'Administration BJ-WACA -114366-CS-INDV / Recrutement du personnel Component 4: National En cours complémentaire de l'UIGP: IDA / 62140 A priori Individuel Direct 62,400.00 0.00 2019-06-04 2019-06-14 2019-07-05 2019-08-09 2020-02-05 Coordination d'exécution Spécialiste du Littoral Point focal technique BJ-WACA -114365-CS-INDV / Recrutement d'un Component 4: National En cours IDA / 62140 A posteriori Individuel Direct 96,000.00 0.00 2019-05-14 2019-05-24 2019-06-14 2019-07-19 2021-07-18 consultant Assistant Coordination d'exécution technique en gestion BJ-WACA -117706-CS-INDV / Recrutement d'un Component 4: National En attente IDA / 62140 A priori Individuel Open 28,800.00 0.00 2019-06-17 2019-08-05 2019-08-26 2019-09-30 2019-11-29 spécialiste en développement Coordination d'exécution social au profit de l'ABE BJ-WACA -117710-CS-INDV / Sélection d'un consultant Component 4: National En attente IDA / 62140 A posteriori Individuel Limited 16,800.00 0.00 2019-06-06 2019-06-11 2019-07-02 2019-08-06 2020-02-02 assistant en passation de Coordination d'exécution marchés BJ-WACA -117715-CS-INDV Component 3: Strengthening / Elaboration du Plan En attente TF / A7131 National Physical and Social A posteriori Individuel Limited 15,000.00 0.00 2019-06-10 2019-06-15 2019-07-06 2019-08-10 2020-02-06 d'Actions de Réinstallation d'exécution Investments des 5 forages à Tannou BJ-WACA -125443-CS-INDV / Recruter un consultant Component 4: National En cours pour appuyer dans les IDA / 62140 A posteriori Individuel Direct 96,000.00 0.00 2019-08-05 2019-08-15 2019-09-05 2019-10-10 2020-04-07 Coordination d'exécution activités de passation des marchés de l’UIGP Page 10 BJ-WACA -125483-CS-CDS / Contrôle et surveillance des travaux d'urgence de Component 3: Strengthening Sélection de En attente dragage et de refoulement IDA / 62140 National Physical and Social A posteriori consultants par Direct 40,000.00 0.00 2019-08-02 2019-08-12 2019-10-16 2020-04-13 d'exécution de sédiments dans la berge Investments entente directe sud du fleuve Mono à Grand Popo BJ-WACA -125524-CS-INDV / Etudes d'impact environnemental et social de Component 3: Strengthening En attente la sécurisation de la mare TF / A7131 National Physical and Social A posteriori Individuel Limited 20,000.00 0.00 2019-08-12 2019-08-17 2019-09-07 2019-10-12 2020-04-09 d'exécution aux crocodiles et de la Investments réalisation des 5 forages à Tannou BJ-WACA -125532-CS-INDV / Recrutement d'un chargé de mission (EKPANGBO G Component 3: Strengthening Gildas) pour la création des En attente TF / A7131 National Physical and Social A posteriori Individuel Direct 7,200.00 0.00 2019-08-02 2019-08-12 2019-09-02 2019-10-07 2020-01-05 ACCB, le suivi des AaGRs d'exécution Investments et l'appui à la mise en œuvre des plans de gestion du projet BJ-WACA -125533-CS-INDV / Recrutement d'un chargé de mission (BOUKARI Component 3: Strengthening Saliou) pour la création des En attente TF / A7131 National Physical and Social A posteriori Individuel Direct 7,200.00 0.00 2019-08-02 2019-08-12 2019-09-02 2019-10-07 2020-01-05 ACCB, le suivi des AaGRs d'exécution Investments et l'appui à la mise en œuvre des plans de gestion du projet BJ-WACA -125534-CS-INDV / Recrutement d'un chargé de mission (BIAOU O. Component 3: Strengthening Oraly) pour la création des En attente TF / A7131 National Physical and Social A posteriori Individuel Direct 7,200.00 0.00 2019-08-02 2019-08-12 2019-09-02 2019-10-07 2020-01-05 ACCB, le suivi des AaGRs d'exécution Investments et l'appui à la mise en œuvre des plans de gestion du projet BJ-WACA -125535-CS-INDV / Recrutement d'un chargé de mission (SONOU Component 3: Strengthening AGOUSSOU Sabas) pour la En attente TF / A7131 National Physical and Social A posteriori Individuel Direct 7,200.00 0.00 2019-08-02 2019-08-12 2019-09-02 2019-10-07 2020-01-05 création des ACCB, le suivi d'exécution Investments des AaGRs et l'appui à la mise en œuvre des plans de gestion du projet BJ-WACA -128756-CS-INDV / Recrutement d'un Assistant Technique international (ATi) Component 4: National En cours IDA / 62140 A priori Individuel Open 462,000.00 0.00 2019-08-27 2019-10-15 2019-11-05 2019-12-10 2022-12-09 pour Unité Intégrée de Coordination d'exécution Gestions des Projets du Secteur Environnement BJ-WACA -129049-CS-INDV / Recrutement du personnel complémentaire: Assistant Component 4: National En cours IDA / 62140 A priori Individuel Open 52,800.00 0.00 2019-09-02 2019-10-21 2019-11-11 2019-12-16 2021-12-15 Technique National - Coordination d'exécution Spécialiste en Développement Institutionnel BJ-WACA -129337-CS-INDV / Recrutement d’un assistant technique pour le suivi et la Component 2: Strengthening En attente mise en œuvre de projets IDA / 62140 the Policy and Institutional A posteriori Individuel Limited 19,000.00 0.00 2019-09-12 2019-09-17 2019-10-08 2019-11-12 2019-12-03 d'exécution sur les zones humides, les Framework aires protégées et le changement climatique Page 11 BJ-WACA -129364-CS-INDV / Recrutement du Coordonnateur Général de Component 4: National En cours IDA / 62140 A priori Individuel Open 72,000.00 0.00 2019-08-30 2019-10-18 2019-11-08 2019-12-13 2021-12-12 l'Unité Intégrée de Gestion Coordination d'exécution des Projets (UIGP) du secteur environnement Page 12