Solomon Islands Community Access & Urban Services Enhancement (CAUSE) Project PROCUREMENT PLAN 2018 - 2019 Project Information : Solomon Islands Government CAUSE (P161320) Implementing Agencies : Honiara City Council and Ministry of Infrastructure Development Procurement/Selection Methods Applicability Prior Review Thresholds Goods Shopping =US$1,000,000 All Works Shopping =US$5,000,000 All Consultants QCBS >=US$500,000 CQS FBS In accordance with Consultant’s SSS Guidelines Individuals – Competitive Individuals – Sole Source PLAN ACTUAL Cost Review Contract Proc. Expected Expected Bid Bank’s Contract Contract Contract No. Estimate Method by Expecte Description (USD) Bank d date of Date of Date of Receipt NOL Award Value Remarks Bid Contract (SBD); Bid Issue Opening Signing (Est’d USD) HONIARA CITY COUNCIL Component 1 : Urban Works and Services Works Contracts Goods Contracts HCC-GO-01 Vehicle: Pick-Up US$120,00 RFQ Post 2 April 16 April 23 April Truck (4 units): Auki – 0 2018 2018 2018 1; Honiara - 3 HCC.GO-02 Office Computers & US$25,000 RFQ Post 9 April 16 April 23 April Printers 2018 2018 2018 HCC-GO-03 Office Equipment & US$10,000 RFQ Post 9 April 16 April 23 April Furniture 2018 2018 2018 HCC-GO-04 Safety Equipment, US$20,000 RFQ Post 14 May 25 May 31 May clothing, and tools 2018 2018 2018 HCC-GO-05 Timber, Cement, US$145,09 RFQ Post 16 July 30 July 6 Aug Rebar, and other 4 2018 2018 2018 materials (Hon/Guadalcanal) HCC-GO-06 Timber, Cement, US$145,33 RFQ Post 11 Feb 25 Feb 4 Mar Rebar, and other 8 2019 2019 2019 materials (Western/Malaita) Consulting Services HCC-CS-01 1 – PW Engineer – US$405,00 CDS Prior 16 April 30 April 7 May Proj. Mgr. (Int’l) – 0 2018 2018 2018 HCC HCC-CS-02 2 - Works US$50,400 CDS Post 16 April 30 April 7 May Coordinators 2018 2018 2018 (Honiara) – HCC HCC-CS-03 2 – Community US$50,400 CDS Post 16 April 30 April 7 May Liaison Officers 2018 2018 2018 (Honiara) – HCC HCC-CS-04 3 – Resident Works US$197,58 INDV Post 14 May 21 May 28 May Supervisors (PIU) – 0 2018 2018 2018 HCC HCC-CS-05 3 – Community US$94,200 INDV Post 14 May 21 May 28 May Liaison Officers (PIU) 2018 2018 2018 – HCC HCC-CS-06 3 - Admin/Proc US$50,280 INDV Post 14 May 21 May 28 May Officers (PIU) – HCC 2018 2018 2018 HCC-CS-07 1 – Engineer US$161,68 INDV Post 14 May 21 May 28 May (National) - HCC 2 2018 2018 2018 MINISTRY OF INFRASTRUCTURE DEVELOPMENT Component 2: Road Repair and Maintenance Works Contracts 2a. Road Maintenance MID-CW- Maintenance of US$82,894 RFQ Post 18 June 2 16 July RM.HON.01 X1 Hon. Rd. (3.5 2018 July 2018 km) 2018 MID-CW- Maintenance of US$94,736 RFQ Post 16 July 30 July 13 Aug RM.HON.02 X2 Hon. Rd. (4 2018 2018 2018 km) MID-CW- Maintenance of US$94,736 RFQ Post 13 Aug 27 Aug 10 Sept RM.HON.03 X3 Hon. Rd. (4 2018 2018 2018 km) MID-CW- Maintenance of US$94,736 RFQ Post 13 Aug 27 Aug 10 Sept RM.HON.04 X4 Hon. Rd. (4 2018 2018 2018 km) MID-CW- Maintenance of US$94,736 RFQ Post 8 Oct 22 Oct 5 Nov RM.HON.05 X5 Hon. Rd. (4 2018 2018 2018 km) MID-CW- Maintenance of US$94,736 RFQ Post 8 Oct 22 Oct 5 Nov RM.HON.06 X6 Hon. Rd. (4 2018 2018 2018 km) MID-CW- Maintenance of US$94,736 RFQ Post 18 June 2 16 July RM.GP.01 X1 Guadalcanal 2018 July 2018 Rd. (4 km) 2018 Works Contracts 2b. Road Improvement & Rehabilitation MID-CW- Climate Resilient US$114,45 RFQ Post 11 Feb 25 Feb 11 Mar RR.HON.01 Spot 0 2019 2019 2019 Improvement- Drains, X7 Honiara Road MID-CW- Road Rehab- US$361,22 RFQ Post 8 April 22 Apr 6 May RR.HON.02 Upgrading, X8 8 2019 2019 2019 Honiara Road Goods Contracts MID-GO-01 Compaction Eqpt. US$25,000 RFQ Post 4 June 18 June 25 June (HCC, Guadalcanal) 2018 2018 2018 – 1 unit MID-GO-02 Compaction Eqpt. US$50,000 RFQ Post 4 Mar 18 Mar 25 Mar (Auki, Gizo) – 2 units 2019 2019 2019 MID-GO-03 Vehicle: Pick-Up US$75,000 RFQ Post 12 Nov 26 Nov 3 Dec Truck (3 units): Gizo 2018 2018 2018 – 1; Honiara - 2 MID-GO-04 Safety Eqpt & Tools - US$20,000 RFQ Post 11 June 25 June 2 July MID 2018 2018 2018 MID-GO-05 Survey-Soil Testing US$20,000 RFQ Post 9 July 23 July 30 July Eqpt – MID 2018 2018 2018 MID-GO-06 Computing, Office US$30,000 RFQ Post 16 April 30 April 7 May Eqpt, Furniture - MID 2018 2018 2018 Consulting Services MID-CS-01 Works Engineer US$405,00 CDS Prior 16 April 30 April 7 May (International) – MID 0 2018 2018 2018 MID-CS-02 Senior Works Officer US$46,080 CDS Post 16 April 30 April 7 May – MID 2018 2018 2018 MID-CS-03 Works Supervisor – US$25,200 CDS Post 16 April 30 April 7 May MID 2018 2018 2018 MID-CS-04 Community Liaison US$25,200 CDS Post 16 April 30 April 7 May Officer – MID 2018 2018 2018 MID-CS-05 Engineer – MID US$84,000 INDV Post 16 April 30 April 7 May 2018 2018 2018 Component 3 : Infrastructure & Service Delivery Training Consulting Services HCC-CS-08 PET Team Leader US$97,680 CDS Post 23 April 7 May 14 May 2018 2018 2018 HCC-CS-09 Social Service Coach US$25,080 CDS Post 23 April 7 May 14 May / Counsellor 2018 2018 2018 HCC-CS-10 Curriculum US$37,500 INDV Post 23 April 7 May 14 May Development Expert 2018 2018 2018 (International) HCC-CS-11 Trainers – Life Skills US$77,682 CDS Post 23 April 7 May 14 May (3 existing) 2018 2018 2018 HCC-CS-12 Trainers – Life Skills US$94,160 INDV Post 11 June 25 June 2 July (4 new) 2018 2018 2018 Component 4 : Project Management Goods Contracts HCC-GO-07 MIS Hardware US$13,000 RFQ Post 14 May 25 May 31 May Resources 2018 2018 2018 Consulting Services HCC-NC-01 Waste Mgt US$23,400 CDS Post 17 Sept 1 Oct 8 Oct Community Group 2018 2018 2018 Training HCC-NC-02 Baseline, Tracer, US$43,750 CQS Post 7 May 28 May 11 June Annual Surveys 2018 2018 2018 (M&E) HCC-NC-03 Audit Services – US$12,000 CQS Post 1 April 15 April 29 April FY2018 2019 2019 2019 HCC-CS-13 Deputy Project US$84,000 CDS Post 16 April 30 April 7 May Manager/Finance 2018 2018 2018 Officer MID-CS-06 Sr. Finance Officer US$45,600 CDS Post 16 April 30 April 7 May 2018 2018 2018 HCC-CS-14 Accounting Clerk US$31,200 CDS Post 16 April 30 April 7 May 2018 2018 2018 HCC-CS-15 Procurement Officer US$67,200 INDV Post 16 April 30 April 7 May (2 No.) – MID & HCC 2018 2018 2018 HCC-CS-16 Data Entry Operator US$13,680 CDS Post 16 April 30 April 7 May 2018 2018 2018 HCC-CS-17 Filing Clerk US$13,200 CDS Post 16 April 30 April 7 May 2018 2018 2018 HCC-CS-18 Payroll Clerk US$13,680 INDV Post 16 April 30 April 7 May 2018 2018 2018 HCC-CS-19 Safeguards Specialist US$45,600 INDV Post 16 April 30 April 7 May 2018 2018 2018 HCC-CS-20 Media & US$45,600 INDV Post 16 April 30 April 7 May Communications 2018 2018 2018 Specialist HCC-CS-21 MIS Software/e- US$62,500 INDV Post 14 May 4 June 18 June Banking Systems TA 2018 2018 2018 HCC-CS-22 Mid-Term Reviewer US$37,500 INDV Post MID-CS-07 Project-end Reviewer US$37,500 INDV Post PROCUREMENT Solomon Islands : Community Access and Urban Services Enhancement Project PLAN General Information Country: Solomon Islands Banks Approval Date of the Original Procurement Plan: 2018-05-16 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-08-15 Project ID: P161320 GPN Date: 2018-06-19 Project Name: Community Access and Urban Services Enhancement Project Loan / Credit No: IDA / D2920 Executing Agency(ies): Ministry of Infrastructure Development, Honiara City Council WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SB-MID-61277-CW-RFQ / Request for Single Stage - One Pending Maintenance of X1 Hon. Rd. (3.5 IDA / D2920 Road Maintenance and Repair Post Open - National 82,894.00 0.00 2018-07-23 2018-09-17 2019-09-12 Quotations Envelope Implementation km) SB-MID-61278-CW-RFQ / Request for Single Stage - One Pending Maintenance of X2 Hon. Rd. (4 IDA / D2920 Road Maintenance and Repair Post Open - National 94,736.00 0.00 2018-08-21 2018-10-16 2019-10-11 Quotations Envelope Implementation km) SB-MID-61281-CW-RFQ / Request for Single Stage - One Pending Maintenance of X3 Hon. Rd. (4 IDA / D2920 Road Maintenance and Repair Post Open - National 94,736.00 0.00 2018-08-18 2018-10-13 2019-10-08 Quotations Envelope Implementation km) SB-MID-61280-CW-RFQ / Request for Single Stage - One Pending Maintenance of X4 Hon. Rd. (4 IDA / D2920 Road Maintenance and Repair Post Open - National 94,736.00 0.00 2018-08-18 2018-10-13 2019-10-08 Quotations Envelope Implementation km) SB-MID-61283-CW-RFQ / Request for Single Stage - One Pending Maintenance of X5 Hon. Rd. (4 IDA / D2920 Road Maintenance and Repair Post Open - National 94,736.00 0.00 2018-10-13 2018-12-08 2019-12-03 Quotations Envelope Implementation km) SB-MID-61276-CW-RFQ / Request for Single Stage - One Pending Maintenance of X6 Hon. Rd. (4 IDA / D2920 Road Maintenance and Repair Post Open - National 94,736.00 0.00 2018-10-13 2018-12-08 2019-12-03 Quotations Envelope Implementation km) SB-MID-61282-CW-RFQ / Request for Single Stage - One Pending Maintenance of X1 Guadalcanal IDA / D2920 Road Maintenance and Repair Post Open - National 94,736.00 0.00 2018-08-25 2018-10-20 2019-10-15 Quotations Envelope Implementation Rd. (4 km) SB-MID-61274-CW-RFQ / Climate Resilient Spot Request for Single Stage - One Pending IDA / D2920 Road Maintenance and Repair Post Open - National 114,450.00 0.00 2019-02-16 2019-04-13 2020-04-07 Improvement-Drains, X7 Honiara Quotations Envelope Implementation Road SB-MID-61275-CW-RFQ / Road Request for Single Stage - One Pending Rehab-Upgrading, X8 Honiara IDA / D2920 Road Maintenance and Repair Post Open - National 361,228.00 0.00 2019-04-13 2019-06-08 2020-08-31 Quotations Envelope Implementation Road GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SB-MID-61272-GO-RFQ / Request for Single Stage - One Pending Compaction Eqpt. (HCC, IDA / D2920 Road Maintenance and Repair Post Open - National 25,000.00 0.00 2018-08-11 2018-10-06 2019-04-04 Quotations Envelope Implementation Guadalcanal) 1 unit SB-MID-61191-GO-RFQ / Request for Single Stage - One Pending Compaction Eqpt. (Auki, Gizo) IDA / D2920 Road Maintenance and Repair Post Open - National 50,000.00 0.00 2019-03-09 2019-05-04 2019-10-31 Quotations Envelope Implementation 2 units SB-MID-61183-GO-RFQ / Request for Single Stage - One Pending Vehicle: Pick-Up Truck (3 units): IDA / D2920 Road Maintenance and Repair Post Open - National 75,000.00 0.00 2018-06-17 2018-08-12 2019-02-08 Quotations Envelope Implementation Gizo 1; Honiara - 2 SB-MID-61273-GO-RFQ / Safety Request for Single Stage - One Pending IDA / D2920 Road Maintenance and Repair Post Open - National 20,000.00 0.00 2018-08-16 2018-10-11 2019-01-09 Eqpt & Tools - MID Quotations Envelope Implementation SB-MID-61180-GO-RFQ / Request for Single Stage - One Pending IDA / D2920 Road Maintenance and Repair Post Open - National 20,000.00 0.00 2018-07-14 2018-09-08 2018-12-07 Survey-Soil Testing Eqpt MID Quotations Envelope Implementation SB-HCC-61287-GO-RFQ / Request for Single Stage - One Vehicle: Pick-up truck (4 units): IDA / D2920 Urban Works and Services Post Open - National 120,000.00 0.00 Canceled 2018-06-17 2018-08-12 2018-11-10 Quotations Envelope Auki=1 and Honiara=3 SB-HCC-61300-GO-RFQ / Office Request for Single Stage - One IDA / D2920 Urban Works and Services Post Open - National 25,000.00 0.00 Canceled 2018-06-17 2018-08-12 2018-11-10 Computers & Printers Quotations Envelope SB-HCC-61302-GO-RFQ / Office Request for Single Stage - One IDA / D2920 Urban Works and Services Post Open - National 10,000.00 0.00 Canceled 2018-06-17 2018-08-12 2018-11-10 Equipment & Furniture Quotations Envelope SB-HCC-61289-GO-RFQ / Request for Single Stage - One Pending Safety Equipment, clothing, and IDA / D2920 Urban Works and Services Post Open - National 20,000.00 0.00 2018-07-21 2018-09-15 2018-12-14 Quotations Envelope Implementation tools SB-HCC-61290-GO-RFQ / Timber, Cement, Rebar, and Request for Single Stage - One IDA / D2920 Urban Works and Services Post Open - National 145,094.00 0.00 Canceled 2018-07-21 2018-09-15 2019-03-14 other materials Quotations Envelope (Hon/Guadalcanal) SB-HCC-61303-GO-RFQ / Request for Single Stage - One Timber, Cement, Rebar, and IDA / D2920 Urban Works and Services Post Open - National 145,338.00 0.00 Canceled 2019-02-16 2019-04-13 2019-10-10 Quotations Envelope other materials (Western/Malaita) SB-HCC-61415-GO-RFQ / MIS Request for Single Stage - One Pending IDA / D2920 Project Management Post Open - National 13,000.00 0.00 2018-06-23 2018-08-18 2018-11-16 Hardware Resources Quotations Envelope Implementation Page 1 SB-MID-61172-GO-RFQ / Request for Single Stage - One Under Computing, Office Eqpt, Furniture IDA / D2920 Road Maintenance and Repair Post Open - National 30,000.00 0.00 2018-06-02 2018-07-28 2019-01-24 Quotations Envelope Implementation - MID SB-HCC-72962-GO-RFQ / Request for Single Stage - One Pending Timber, Form-works IDA / D2920 Urban Works and Services Post Limited 50,000.00 0.00 2018-09-22 2018-11-17 2019-05-16 Quotations Envelope Implementation (Honiara/Guadalcanal) SB-HCC-72965-GO-RFQ / Cement, ready-mixed concrete, Request for Single Stage - One Pending IDA / D2920 Urban Works and Services Post Limited 50,000.00 0.00 2018-09-22 2018-11-17 2019-05-16 aggregates Quotations Envelope Implementation (Honiara/Guadalcanal) SB-HCC-72966-GO-RFQ / Request for Single Stage - One Pending Rebars & Hardware IDA / D2920 Urban Works and Services Post Limited 45,000.00 0.00 2018-09-22 2018-11-17 2019-05-16 Quotations Envelope Implementation (Honiara/Guadalcanal) SB-HCC-72967-GO-RFQ / Request for Single Stage - One Pending IDA / D2920 Urban Works and Services Post Limited 45,000.00 0.00 2018-10-20 2018-12-15 2019-06-13 Construction materials (Auki) Quotations Envelope Implementation SB-HCC-72968-GO-RFQ / Request for Single Stage - One Pending IDA / D2920 Urban Works and Services Post Limited 50,000.00 0.00 2018-10-20 2018-12-15 2019-06-13 Construction Materials (Noro) Quotations Envelope Implementation SB-HCC-72969-GO-RFQ / Request for Single Stage - One Pending IDA / D2920 Urban Works and Services Post Limited 50,000.00 0.00 2018-10-27 2018-12-22 2019-06-20 Construction Materials (Gizo) Quotations Envelope Implementation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SB-HCC-61419-CS-CQS / Consultant Pending Waste Mgt Community Group IDA / D2920 Project Management Post Qualification Open - National 23,400.00 0.00 2018-09-17 2018-10-08 2018-11-21 2018-12-21 2019-01-25 2019-07-24 Implementation Training Selection Consultant SB-HCC-61010-CS-CQS / Audit Pending IDA / D2920 Project Management Post Qualification Open - National 12,000.00 0.00 2019-04-01 2019-04-22 2019-06-05 2019-07-05 2019-08-09 2020-02-05 Services FY2018 Implementation Selection SB-HCC-61301-CS-CQS / Consultant Under Baseline, Tracer, Annual Surveys IDA / D2920 Project Management Post Qualification Open - National 175,000.00 0.00 2018-06-25 2018-07-16 2018-08-29 2018-09-28 2018-11-02 2019-05-01 Implementation (M&E) Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SB-MID-61174-CS-INDV / Individual Consultant Pending IDA / D2920 Road Maintenance and Repair Post Open 84,000.00 0.00 2018-08-13 2018-10-01 2018-10-22 2018-11-26 2020-11-25 Engineer MID Selection Implementation SB-HCC-61311-CS-INDV / 1 Individual Consultant Under IDA / D2920 Urban Works and Services Post Open 84,000.00 0.00 2018-06-14 2018-05-22 2018-08-02 2018-08-07 2018-08-23 2018-09-27 2020-09-26 Engineer (National) - HCC Selection Implementation SB-HCC-61425-CS-CDS / PET Infrastructure and Service IDA / D2920 Post Direct Selection Direct 97,680.00 89,142.92 Signed 2018-05-23 2018-05-30 2018-06-02 2018-06-05 2018-08-06 2018-06-27 2020-08-05 Team Leader Delivery Training SB-HCC-61413-CS-CDS / Social Infrastructure and Service IDA / D2920 Post Direct Selection Direct 25,080.00 26,957.02 Signed 2018-05-23 2018-05-22 2018-06-02 2018-06-04 2018-08-06 2018-06-25 2020-08-05 Service Coach / Counsellor Delivery Training SB-HCC-61424-CS-INDV / Infrastructure and Service Individual Consultant Curriculum Development Expert IDA / D2920 Post Open 37,500.00 23,640.00 Signed 2018-05-23 2018-05-29 2018-07-11 2018-07-29 2018-08-01 2018-08-01 2018-09-05 2018-08-03 2018-11-04 Delivery Training Selection (International) SB-MID-63000-CS-CDS / 1- IDA / D2920 Road Maintenance and Repair Post Direct Selection Direct 25,200.00 23,161.92 Signed 2018-05-17 2018-05-27 2018-05-30 2018-07-31 2018-06-25 2020-07-30 Works Supervisor - MID SB-HCC-61307-CS-INDV / 1 - Individual Consultant Under Resident Works Supervisors IDA / D2920 Urban Works and Services Post Open 44,467.00 0.00 2018-06-14 2018-05-22 2018-08-02 2018-08-23 2018-09-27 2020-09-26 Selection Implementation (PIU) - HCC SB-HCC-61420-CS-INDV / 1 - Individual Consultant Under IDA / D2920 Urban Works and Services Post Open 25,200.00 0.00 2018-06-14 2018-05-29 2018-08-02 2018-08-23 2018-09-27 2020-09-26 Admin/Proc Officers (PIU) - HCC Selection Implementation SB-HCC-61421-CS-CDS / Infrastructure and Service Under IDA / D2920 Post Direct Selection Direct 28,248.00 0.00 2018-05-23 2018-06-02 2018-08-06 2020-08-05 Trainers - Life Skills (1 existing) Delivery Training Implementation SB-HCC-61417-CS-INDV / Infrastructure and Service Individual Consultant Under IDA / D2920 Post Open 28,248.00 0.00 2018-06-18 2018-08-06 2018-08-27 2018-10-01 2020-09-30 Trainers - Life Skills (1 new) Delivery Training Selection Implementation SB-HCC-63008-CS-INDV / Infrastructure and Service Individual Consultant Under IDA / D2920 Post Open 28,248.00 0.00 2018-06-18 2018-08-06 2018-08-27 2018-10-01 2020-09-30 Trainers - Life Skills (1 new) Delivery Training Selection Implementation SB-HCC-63009-CS-INDV / Infrastructure and Service Individual Consultant Under IDA / D2920 Post Open 28,248.00 0.00 2018-06-18 2018-08-06 2018-08-27 2018-10-01 2020-09-30 Trainers - Life Skills (1 new) Delivery Training Selection Implementation SB-HCC-63010-CS-INDV / Infrastructure and Service Individual Consultant Under IDA / D2920 Post Open 28,248.00 0.00 2018-06-18 2018-08-06 2018-08-27 2018-10-01 2020-09-30 Trainers - Life Skills (1 new) Delivery Training Selection Implementation Page 2 SB-HCC-63011-CS-INDV / 1 - Individual Consultant Under IDA / D2920 Urban Works and Services Post Open 25,200.00 0.00 2018-06-14 2018-05-29 2018-08-02 2018-08-23 2018-09-27 2020-09-26 Admin/Proc Officers (PIU) - HCC Selection Implementation SB-HCC-63012-CS-INDV / 1 - Individual Consultant Under IDA / D2920 Urban Works and Services Post Open 25,200.00 0.00 2018-06-14 2018-05-29 2018-08-02 2018-08-23 2018-09-27 2020-09-26 Admin/Proc Officers (PIU) - HCC Selection Implementation SB-HCC-63013-CS-CDS / Infrastructure and Service IDA / D2920 Post Direct Selection Direct 28,248.00 27,852.80 Signed 2018-05-23 2018-05-22 2018-06-02 2018-06-25 2018-08-06 2018-08-06 2020-08-05 Trainers - Life Skills (1 existing) Delivery Training SB-HCC-63014-CS-CDS / Infrastructure and Service IDA / D2920 Post Direct Selection Direct 28,248.00 28,097.02 Signed 2018-05-23 2018-05-22 2018-06-02 2018-06-25 2018-08-06 2018-08-08 2020-08-05 Trainers - Life Skills (1 existing) Delivery Training SB-MID-61016-CS-CDS / IDA / D2920 Project Management Post Direct Selection Direct 33,600.00 39,582.22 Signed 2018-05-18 2018-05-28 2018-05-30 2018-08-01 2018-06-25 2020-07-31 Procurement Officer MID SB-MID-61178-CS-CDS / Works IDA / D2920 Road Maintenance and Repair Prior Direct Selection Direct 405,000.00 349,807.90 Signed 2018-05-16 2018-05-28 2018-05-26 2018-05-30 2018-07-30 2018-06-11 2020-07-29 Engineer (International) MID SB-MID-61176-CS-CDS / 1- IDA / D2920 Road Maintenance and Repair Post Direct Selection Direct 25,200.00 26,943.29 Signed 2018-05-16 2018-05-26 2018-05-30 2018-07-30 2018-06-25 2020-07-29 Works Supervisor - MID SB-MID-61175-CS-CDS / IDA / D2920 Road Maintenance and Repair Post Direct Selection Direct 25,200.00 25,338.40 Signed 2018-05-16 2018-05-23 2018-05-26 2018-05-30 2018-07-30 2018-06-25 2020-07-29 Community Liaison Officer MID SB-MID-61179-CS-CDS / Senior Pending IDA / D2920 Road Maintenance and Repair Post Direct Selection Direct 46,080.00 0.00 2018-06-11 2018-06-21 2018-08-25 2020-08-24 Works Officer MID Implementation SB-MID-61173-CS-CDS / Sr. IDA / D2920 Project Management Post Direct Selection Direct 45,600.00 50,169.68 Signed 2018-05-16 2018-05-26 2018-05-30 2018-07-30 2018-06-25 2020-07-29 Finance Officer SB-HCC-61015-CS-CDS / 1 PW Engineer Proj. Mgr. (Intl) IDA / D2920 Urban Works and Services Prior Direct Selection Direct 405,000.00 386,972.00 Signed 2018-05-22 2018-05-28 2018-05-29 2018-05-29 2018-07-08 2018-06-06 2020-07-06 HCC SB-HCC-63006-CS-CDS / 1 - Community Liaison Officers IDA / D2920 Urban Works and Services Post Direct Selection Direct 25,200.00 26,801.13 Signed 2018-05-22 2018-05-29 2018-06-01 2018-06-04 2018-08-05 2018-06-22 2020-08-04 (Honiara) - HCC SB-HCC-61407-CS-CDS / 1 - Community Liaison Officers IDA / D2920 Urban Works and Services Post Direct Selection Direct 25,200.00 27,026.28 Signed 2018-05-22 2018-05-29 2018-06-01 2018-06-04 2018-08-05 2018-06-25 2020-08-04 (Honiara) - HCC SB-HCC-61412-CS-CDS / Data IDA / D2920 Project Management Post Direct Selection Direct 13,680.00 18,580.91 Signed 2018-05-22 2018-05-29 2018-06-01 2018-06-04 2018-08-05 2018-06-26 2020-08-04 Entry Operator SB-HCC-61409-CS-INDV / Individual Consultant Media & Communications IDA / D2920 Project Management Post Open 45,600.00 41,610.24 Signed 2018-05-22 2018-05-29 2018-07-10 2018-08-13 2018-07-31 2018-08-14 2018-09-04 2018-08-15 2020-09-03 Selection Specialist SB-HCC-61408-CS-INDV / Individual Consultant IDA / D2920 Project Management Post Open 33,600.00 35,957.25 Signed 2018-05-22 2018-05-29 2018-07-10 2018-08-08 2018-07-31 2018-08-13 2018-09-04 2018-08-15 2020-09-03 Procurement Officer - HCC Selection SB-HCC-61416-CS-INDV / Individual Consultant Under IDA / D2920 Project Management Post Open 13,680.00 0.00 2018-05-22 2018-05-29 2018-07-10 2018-07-31 2018-09-04 2018-11-16 Payroll Clerk Selection Implementation SB-HCC-61418-CS-INDV / Individual Consultant Under IDA / D2920 Project Management Post Open 45,600.00 0.00 2018-05-22 2018-05-29 2018-07-10 2018-08-15 2018-07-31 2018-09-04 2020-09-03 Safeguards Specialist Selection Implementation SB-HCC-61411-CS-CDS / IDA / D2920 Project Management Post Direct Selection Direct 31,200.00 33,394.32 Signed 2018-05-22 2018-05-29 2018-06-01 2018-06-04 2018-08-05 2018-06-22 2020-08-04 Accounting Clerk SB-HCC-61422-CS-CDS / Deputy Project Manager/Finance IDA / D2920 Project Management Post Direct Selection Direct 84,000.00 83,712.00 Signed 2018-05-22 2018-05-29 2018-06-01 2018-06-04 2018-08-05 2018-06-22 2020-08-04 Officer SB-HCC-61423-CS-CDS / Filing IDA / D2920 Project Management Post Direct Selection Direct 13,200.00 17,049.18 Signed 2018-05-22 2018-05-29 2018-06-01 2018-06-04 2018-08-05 2018-06-26 2020-08-04 Clerk SB-HCC-63001-CS-INDV / 1 - Individual Consultant Under Community Liaison Officers (PIU) IDA / D2920 Urban Works and Services Post Open 25,200.00 0.00 2018-06-14 2018-05-29 2018-08-02 2018-08-23 2018-09-27 2020-09-26 Selection Implementation - HCC SB-HCC-63003-CS-INDV / 1 Individual Consultant Under Community Liaison Officers (PIU) IDA / D2920 Urban Works and Services Post Open 25,200.00 0.00 2018-06-14 2018-05-29 2018-08-02 2018-08-23 2018-09-27 2020-09-26 Selection Implementation HCC SB-HCC-63004-CS-INDV / 1 - Individual Consultant Under Resident Works Supervisors IDA / D2920 Urban Works and Services Post Open 44,467.00 0.00 2018-06-14 2018-05-28 2018-08-02 2018-08-23 2018-09-27 2020-09-26 Selection Implementation (PIU) - HCC SB-HCC-61305-CS-INDV / 1 - Individual Consultant Under Community Liaison Officers (PIU) IDA / D2920 Urban Works and Services Post Open 25,200.00 0.00 2018-06-14 2018-05-29 2018-08-02 2018-08-23 2018-09-27 2020-09-26 Selection Implementation - HCC SB-HCC-61304-CS-INDV / MIS Individual Consultant Pending IDA / D2920 Project Management Post Open 62,500.00 0.00 2018-05-31 2018-07-19 2018-08-09 2018-09-13 2019-01-11 Software/e-Banking Systems TA Selection Implementation SB-HCC-61310-CS-CDS / 1 - Works Coordinators (Honiara) - IDA / D2920 Urban Works and Services Post Direct Selection Direct 25,200.00 31,560.55 Signed 2018-06-04 2018-05-31 2018-06-14 2018-06-04 2018-08-18 2018-06-25 2020-08-17 HCC SB-HCC-64612-CS-CDS / 1 - Works Coordinator (Honiara) - IDA / D2920 Urban Works and Services Post Direct Selection Direct 25,200.00 28,404.71 Signed 2018-06-04 2018-05-31 2018-06-14 2018-06-04 2018-08-18 2018-06-22 2020-08-17 HCC SB-HCC-64616-CS-INDV / 1 - Individual Consultant Under Resident Works Supervisor (PIU) IDA / D2920 Urban Works and Services Post Open 44,467.00 0.00 2018-06-04 2018-05-31 2018-07-23 2018-08-13 2018-09-17 2019-03-16 Selection Implementation - HCC Page 3