Government of Malawi Ministry of Education Science and Technology Malawi Education Sector Improvement Project (MESIP) 2017 Draft Procurement Plan I. General 1. Project Information Country: Malawi Project Name: Malawi Education Sector Improvement Plan Project ID: P154185 2. Project Implementation Agency: Ministry of Education Science and Technology 3. Date of the Procurement Plan: 1st April 2017 4. Period Covered by this procurement plan: 18 Months II. Thresholds for Prior Review, Procurement Approaches and Methods A. Goods, Works and Non-Consulting Services Procurement Approaches and Methods (US$ millions) Prior Review Category Open International Open Request for (US$ millions) National Quotation (RfQ) Works ≥ 10 ≥ 15.0 < 15 ≤ 0.2 Goods, IT, and non- ≥2 ≥5 <5 ≤ 0.1 consulting services B. Consulting Services Category Prior Review Short List of National Consultants (US$ million) (US$ millions) Consulting Services Engineering and Construction Supervision Consultants (Firms) ≥1 ≤ 0.3 ≤ 0.3 Individual Consultants ≥ 0.3 NA. NA. [Overall Project Procurement Risk is SUBSTANTIAL] Notes: Terms of Reference: Terms of Reference for all contracts shall be cleared by the Bank, regardless of whether the assignment is for prior or post review. Advertisement: Consultancy Service for Contracts estimated to cost US$ 300,000 equivalent and above per contract shall be advertised in UNDB online in addition to advertising in National News Paper(s) of wide circulation and/or Regional News Paper(s). 1 III. Packages for Goods, Works and Non-Consulting Services Sr./ No Contract Description Estimated Review by Market Approach Selection Evaluation Options Procurement Prequal Domestic Expected Expected Cost (US$) Bank (Open-National/ Method (RFP, (BAFO, Rated Process: ificatio Preference date of date of (Prior/Post) International RFB, RFQ, DS Criteria etc.) (Single/Multi n (Yes/ (Yes/No) bid/ Contract Limited etc.) etc.) ple Stages; No) proposal Signature One/Two opening Envelopes etc) Goods Comp 1: Performance Based School Improvement Grants 1 Design and Printing of training materials Qualification Single (Lot 1 strategies, Lot 2, training manuals 32,000 Post National RFQ Criteria stage No No 22 May lot 3 Brochures 2 Qualification Single Supply of stationery materials for training 14,000 Post National RFQ Criteria stage No No 22 May 3 Supply and delivery of 9 Laptops, 9 LCD Qualification Single 19,500 Post National RFQ Criteria stage No No 22 May Projectors and 8 Projector Screens Comp 2: Improving Equity for the Most Disadvantaged, including Girls 4 Supply and delivery of vehicles and motorcycles {(3 No vehicles for PFT and Qualification Single 717,808 Post National RFB Criteria stage No No 30 Jun Comp 2 and 110 No motorcycles for Comp 2(40) and 3 (70)} Comp 3.2 Such Level Data Collection & Usage 5 Qualification Single Printing and delivery of school registers 753,425 Post National RFB Criteria stage No No 30 Jun 6 Supply and delivery of Tablet Qualification Single Smartphones 1,075 (50 for comp 2, 1020 318,494 Post National RFB Criteria stage No No 30 June for comp 3, 5 for PFT) Comp 5: Improving Learning Outcomes, Accountability & Cost Effectiveness 7 Office equipment (staplers, punchers, Qualification Single binding machine, waste baskets, Office 39 500 Post National RFQ Criteria stage No No 31 May trays, lockable cabinets etc.) 8 Supply of office furniture for PFT (office 20,000 Post National RFQ Qualification Single No No May 2017 desks and chairs, bookshelf Criteria Stage 9 Supply of office refrigerator, electric fan, 9,000 Post National RFQ Qualification Single No No kettle and vacuum flask for PFT Criteria Stage Subtotal for goods 1,884,227 Works Comp 2: Improving Equity for the Most Disadvantaged, including Girls 1 Package 1: Construction of 123 Qualification Single classrooms (Mangochi, Machinga, 2,706,000 Post National RFB Criteria stage No No 30 Aug Chikwawa & Thyolo) 2 Package 2: Construction of 127 Qualification Single classrooms (Mzimba South, Kasungu, 2,794,000 Post National RFB Criteria stage No No 1 Sep Lilongwe Rural West & Dedza Subtotal for works 5,500,000 Non-Consulting Services COMPONENT 1: Performance Based School Improvement Grants 1 Hiring of 8 No Generators for training 5,500 Post National RFB Qualification Single No No May criteria stage 20017 COMPONENT 5 Project Implementation 2 Supply and installation of internet router Qualification 5,000 Post RFQ Criteria Single No No 31 May for PFT 3 Qualification Web site design and email hosting for PFT 5,500 Post RFQ Criteria Single No No 31 May Subtotal for non-consulting services 16,000 Total 7,386,227 3 IV. Packages for Consulting Services Sr. No Contract Description Estimated Review by Market Approach Selection Method Shortlisting Expected date Expected Cost (US$) Bank (Open-National/ (QCBS, FBBS, LCBS, (Yes/ No) of bid/ date of (Prior/Post International Limited QBS, CQS, DS etc.) proposal Contract ) etc.) opening Signature COMPONENT 2: Improving Equity for the Most Disadvantaged, including Girls 1 40 Individual consultancies for clerk of works 46,207 Post Open National IC Yes N/A 30 June services in 8 districts (Mzimba, Kasungu, Lilongwe Rural West, Dedza, Mangochi, Machinga, Thyolo & Chikwawa) 2 4 Individual consultancies for engineering 8,877 Post Open National IC Yes N/A 30 June services in eight districts (Mzimba, Kasungu, Lilongwe Rural West, Dedza, Mangochi, Machinga, Thyolo & Chikwawa) COMPONENT 3: Improving Learning Outcomes, Accountability, and Cost-Effectiveness at School Level 3 Consultancy services for provision of school 700,000 Prior Open International QCBS Yes 31 Oct 31 Dec 2017 leadership training programme for head-teachers, deputy head teachers, and primary education advisers in 800 schools in 34 education districts 4 Consultancy services to develop a platform for 500,000 Post Open International QCBS Yes 31 Oct 31 Dec 2017 real time school data collection and SMS for community involvement in school management COMPONENT 5: Project Management 5 PFT Facilitator 41,100 Post Open National IC Yes N/A 1 March 2017 6 M&E Specialist 41,100 Post Open National IC Yes N/A 1 March 2017 7 Procurement Specialist 41,100 Post Open National IC Yes N/A 1 Apr 2017 8 Financial Management Specialist 41,100 Post Open National IC Yes N/A 1 May 2017 9 Communication specialist 41,100 Post Open National IC Yes N/A 1 June 2017 Total for consulting services 1,234,557 1 V. Capacity Building-Not available at the moment No NAME OF POSITION AREA/TRAINING TRAINING DEPT DURATION ESTIMATED COST US$ CANDIDATE COURSE INSTITUTION DAILY NUMBER DATE/MO TRANSPORT TOTAL TUITION/FEES SUBSISTENCE OF DAYS NTH /FARES COSTS ALLOWANCES PROCUREMENT Malawi : Malawi Education Sector Improvement Project (MESIP) PLAN General Information Country: Malawi Bank’s Approval Date of the Original Procurement Plan: 2017-06-05 2019-08-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P154185 GPN Date: 2017-05-22 Project Name: Malawi Education Sector Improvement Project (MESIP) Loan / Credit No: TF / A2913 Executing Agency(ies): Ministry of Education, Science and Technology WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-MOEST-16450-CW-RFB Component 2: Improving / Construction of 127 Equity for the most Single Stage - One classrooms (Mzimba South, TF / A2913 Post Request for Bids Open - National 2,794,000.00 0.00 Canceled 2017-10-01 2017-10-01 2017-10-01 2017-10-01 2017-10-01 2017-10-01 disadvantaged, including Envelope Kasungu, Lilongwe Rural girls. West & Dedza MW-MOEST-30363-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 397,260.27 0.00 Implementati 2017-09-08 2017-09-30 2017-11-10 2017-12-10 2018-01-14 2018-07-27 Water points in Machinga disadvantaged, including Envelope on Lot 1: Naungu, Namalasa girls. and Likhubula MW-MOEST-30365-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 363,013.70 0.00 Implementati 2017-09-08 2017-09-30 2017-11-10 2017-12-10 2018-01-14 2018-07-27 Water points in Machinga disadvantaged, including Envelope on Lot 3: Kachere, Maiwa and girls. Chilangoma MW-MOEST-30358-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 397,260.27 0.00 Implementati 2017-09-08 2017-09-30 2017-11-11 2017-12-11 2018-01-15 2018-07-27 Water points in Mzimba disadvantaged, including Envelope on South Lot 1: Kalumamba, girls. Khorwa and Mnyenjere MW-MOEST-30359-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 397,260.27 0.00 Implementati 2017-09-08 2017-09-30 2017-11-10 2017-12-10 2018-01-14 2018-07-27 Water points in Mzimba disadvantaged, including Envelope on South Lot 2: Ulida, girls. Kapirisala and Mtangatanga MW-MOEST-30362-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 273,972.60 0.00 Implementati 2017-09-08 2017-09-30 2017-11-10 2017-12-10 2018-01-14 2018-07-27 Water points in Mzimba disadvantaged, including Envelope on South Lot 5: Mlazamira and girls. Ephangweni MW-MOEST-30368-CW-RFB / Construction of Classroom Component 2: Improving Blocks, Pit Latrines and Under Equity for the most Single Stage - One Water points in Thyolo Lot TF / A2913 Post Request for Bids Open - National 616,438.36 0.00 Implementati 2017-09-08 2017-09-30 2017-11-11 2017-12-11 2018-01-15 2018-07-27 disadvantaged, including Envelope 1: Nampira, Matete, on girls. Ndayandika,Malota and Namikango Page 1 MW-MOEST-30352-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 342,465.75 0.00 Implementati 2017-09-08 2017-09-30 2017-11-10 2017-12-10 2018-01-14 2018-07-27 Water points in Chikwawa disadvantaged, including Envelope on Lot No 1:Mikombo, Macheu, girls. Chindole and Finish schools MW-MOEST-30354-CW-RFB / Construction of Classroom Component 2: Improving Blocks, Pit Latrines and Under Equity for the most Single Stage - One Water points in Chikwawa TF / A2913 Post Request for Bids Open - National 424,657.53 0.00 Implementati 2017-09-08 2017-09-30 2017-11-10 2017-12-10 2018-01-14 2018-07-27 disadvantaged, including Envelope Lot No 2: Madugu, on girls. Chambuluka, Mtamanja and Lalanje schools MW-MOEST-30355-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 342,465.75 0.00 Implementati 2017-09-08 2017-09-30 2017-11-10 2017-12-10 2018-01-14 2018-07-27 Water points in Chikwawa disadvantaged, including Envelope on Lot No 3: Mzongwe, Phimbi girls. and Nyakamba schools MW-MOEST-30356-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 171,232.88 0.00 Implementati 2017-09-08 2017-09-30 2017-11-11 2017-12-11 2018-01-15 2018-07-27 Water points in Chikwawa disadvantaged, including Envelope on Lot No 4: Gola and girls. Chimwanjale schools MW-MOEST-30357-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 198,630.14 0.00 Implementati 2017-09-08 2017-09-30 2017-11-11 2017-12-11 2018-01-15 2018-07-27 Water points in Chikwawa disadvantaged, including Envelope on Lot No 5: Mkundula and girls. Dyeratu schools MW-MOEST-30364-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 363,013.70 0.00 Implementati 2017-09-08 2017-09-30 2017-11-10 2017-12-10 2018-01-14 2018-07-27 Water points in Machinga disadvantaged, including Envelope on Lot 2: Chilwa, Mwaiwathu girls. and Msumwa MW-MOEST-30366-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 363,013.70 0.00 Implementati 2017-09-08 2017-09-30 2017-11-10 2017-12-10 2018-01-14 2018-07-27 Water points in Machinga disadvantaged, including Envelope on Lot 4: Makengere, Kanjuli girls. and Matiti MW-MOEST-30367-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 363,013.70 0.00 Implementati 2017-09-08 2017-09-30 2017-11-10 2017-12-10 2018-01-14 2018-07-27 Water points in Machinga disadvantaged, including Envelope on Lot 5: Mchinji, Chiunda and girls. Kawiriwita MW-MOEST-30360-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 397,260.27 0.00 Implementati 2017-09-08 2017-09-30 2017-11-11 2017-12-11 2018-01-15 2018-07-27 Water points in Mzimba disadvantaged, including Envelope on South Lot 3: Kafunda, girls. Kawindula and Kaphuta MW-MOEST-30361-CW-RFB / Construction of Classroom Component 2: Improving Blocks, Pit Latrines and Under Equity for the most Single Stage - One Water points in Mzimba TF / A2913 Post Request for Bids Open - National 273,972.60 0.00 Implementati 2017-09-08 2017-09-30 2017-11-10 2017-12-10 2018-01-14 2018-07-27 disadvantaged, including Envelope South Lot 4: Mgungulu, on girls. Kasambankholi and Chamayembe Page 2 MW-MOEST-30369-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 534,246.58 0.00 Implementati 2017-09-08 2017-09-30 2017-11-10 2017-12-10 2018-01-14 2018-07-27 Water points in Thyolo Lot disadvantaged, including Envelope on 2: Mberenga, Chisoka, girls. Ntawa and Mikalati MW-MOEST-30370-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 554,794.52 0.00 Implementati 2017-09-08 2017-09-30 2017-11-10 2017-12-10 2018-01-14 2018-07-27 Water points in Thyolo Lot disadvantaged, including Envelope on 3. Wilson, Gombwa, Didi girls. and Mtundama MW-MOEST-30911-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 424,657.53 0.00 Implementati 2017-10-04 2017-10-07 2017-11-17 2017-12-17 2018-01-21 2018-07-20 Water points in Dedza Lot disadvantaged, including Envelope on No 1:Chindoole, Chithawale girls. and Chowo MW-MOEST-30912-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 308,219.18 0.00 Implementati 2017-10-04 2017-10-07 2017-11-17 2017-12-17 2018-01-21 2018-07-20 Water points in Dedza Lot disadvantaged, including Envelope on No 2:Mtayandodo, Kapiriuta girls. and Mwalawathonga MW-MOEST-30913-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 308,219.18 0.00 Implementati 2017-10-04 2017-10-07 2017-11-18 2017-12-18 2018-01-22 2018-07-21 Water points in Dedza Lot disadvantaged, including Envelope on No 3:Uswe, Koche and girls. Msapuka MW-MOEST-30914-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 486,301.37 0.00 Implementati 2017-10-04 2017-10-07 2017-11-17 2017-12-17 2018-01-21 2018-07-20 Water points in Dedza Lot disadvantaged, including Envelope on No 4:Kamdzabwino, Banda girls. Hill, Luweya and Kasenjere MW-MOEST-30915-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 308,219.18 0.00 Implementati 2017-10-04 2017-10-07 2017-11-17 2017-12-17 2018-01-21 2018-07-20 Water points in Dedza Lot disadvantaged, including Envelope on No 5:Chipudzi, Kapiri and girls. Mlambe MW-MOEST-30916-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 376,712.33 0.00 Implementati 2017-10-04 2017-10-07 2017-11-17 2017-12-17 2018-01-21 2018-07-20 Water points in Kasungu disadvantaged, including Envelope on Lot 1: Kamwala and girls. Chithiba MW-MOEST-30918-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 410,958.90 0.00 Implementati 2017-10-04 2017-10-07 2017-11-17 2017-12-17 2018-01-21 2018-07-20 Water points in Kasungu disadvantaged, including Envelope on Lot 2: Chinkhoma, Chidedza, girls. Kanjoka and Mdima MW-MOEST-30919-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 301,369.86 0.00 Implementati 2017-10-04 2017-10-07 2017-11-17 2017-12-17 2018-01-21 2018-07-20 Water points in Kasungu disadvantaged, including Envelope on Lot 3: Kavuwa, Mbongozi girls. and Mteketana Page 3 MW-MOEST-30921-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 301,369.86 0.00 Implementati 2017-10-04 2017-10-07 2017-11-17 2017-12-17 2018-01-21 2018-07-20 Water points in Kasungu disadvantaged, including Envelope on Lot 4: Juni, Kapando and girls. Kamdidi MW-MOEST-30928-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 198,630.14 0.00 Implementati 2017-10-04 2017-10-07 2017-11-17 2017-12-17 2018-01-21 2018-07-20 Water points in Lilongwe disadvantaged, including Envelope on Rural West Lot 1: Lowe and girls. Mpingu MW-MOEST-30929-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 410,958.90 0.00 Implementati 2017-10-04 2017-10-07 2017-11-17 2017-12-17 2018-01-21 2018-07-20 Water points in Lilongwe disadvantaged, including Envelope on Rural West Lot 2: Muzu, girls. Airbase, Mphanje and Ngowe MW-MOEST-30930-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 273,972.60 0.00 Implementati 2017-10-04 2017-10-07 2017-11-17 2017-12-17 2018-01-21 2018-07-20 Water points in Lilongwe disadvantaged, including Envelope on Rural West Lot 3: Kachiswe, girls. Sauzamwana and Kakuyu MW-MOEST-30932-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 301,369.86 0.00 Implementati 2017-10-04 2017-10-07 2017-11-17 2017-12-17 2018-01-21 2018-07-20 Water points in Lilongwe disadvantaged, including Envelope on Rural West Lot 4: Katondo, girls. Ntauka and Msauka MW-MOEST-30933-CW-RFB / Construction of Classroom Component 2: Improving Blocks, Pit Latrines and Under Equity for the most Single Stage - One Water points in Lilongwe TF / A2913 Post Request for Bids Open - National 301,369.86 0.00 Implementati 2017-10-04 2017-10-07 2017-11-17 2017-12-17 2018-01-21 2018-07-20 disadvantaged, including Envelope Rural West Lot 5: on girls. Mankhamba,Chisemphere and Mtsindo MW-MOEST-30934-CW-RFB / Construction of Classroom Component 2: Improving Blocks, Pit Latrines and Under Equity for the most Single Stage - One Water points in Lilongwe TF / A2913 Post Request for Bids Open - National 301,369.86 0.00 Implementati 2017-10-04 2017-10-07 2017-11-17 2017-12-17 2018-01-21 2018-07-20 disadvantaged, including Envelope Rural West Lot 6: on girls. Kambulire, Ukwe and Mkunkhu MW-MOEST-30936-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 410,958.90 0.00 Implementati 2017-10-04 2017-10-07 2017-11-17 2017-12-17 2018-01-21 2018-07-20 Water points in Mangochi disadvantaged, including Envelope on Lot 1: Ching'ombe, Maloya girls. and Suludi MW-MOEST-30938-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 356,164.38 0.00 Implementati 2017-10-04 2017-10-07 2017-11-17 2017-12-17 2018-01-21 2018-07-20 Water points in Mangochi disadvantaged, including Envelope on Lot 2: Mkwera, Mwaye and girls. Nanjiwa MW-MOEST-30940-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 410,958.90 0.00 Implementati 2017-10-04 2017-10-07 2017-11-17 2017-12-17 2018-01-21 2018-07-20 Water points in Mangochi disadvantaged, including Envelope on Lot 3: Kalenjeka, Chididi girls. and Luwi Page 4 MW-MOEST-30941-CW-RFB / Construction of Classroom Component 2: Improving Under Blocks, Pit Latrines and Equity for the most Single Stage - One TF / A2913 Post Request for Bids Open - National 410,958.90 0.00 Implementati 2017-10-04 2017-10-07 2017-11-17 2017-12-17 2018-01-21 2018-07-20 Water points in Mangochi disadvantaged, including Envelope on Lot 4: Mpapa, Ntiya and girls. Taliya MW-MOEST-30942-CW-RFB Component 2: Improving / Construction of Classroom Under Equity for the most Single Stage - One Blocks, Pit Latrines and TF / A2913 Post Request for Bids Open - National 239,726.03 0.00 Implementati 2017-10-04 2017-10-07 2017-11-17 2017-12-17 2018-01-21 2018-07-20 disadvantaged, including Envelope Water points in Mangochi on girls. Lot 5: Nsinjiri and Chisawa GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: Improving MW-MOEST-16460-GO-RFB Under Equity for the most Single Stage - One / Supply and delivery of TF / A2913 Prior Request for Bids Open - National 717,805.00 0.00 Implementati 2017-09-15 2017-09-15 2017-09-15 2017-09-15 2017-09-15 2017-09-15 disadvantaged, including Envelope vehicles and motorcycles on girls. MW-MOEST-16448-GO-RFQ Component 5: Project / Office equipment (staplers, Pending management, and sector Request for Single Stage - One punchers, binding machine, TF / A2913 Post Open - National 39,500.00 0.00 Implementati 2017-07-01 2017-07-01 2017-07-01 program support and Quotations Envelope waste baskets, Office trays, on coordination. lockable cabinets etc.) MW-MOEST-16444-GO-RFQ Component 5: Project Under / Supply of office furniture management, and sector Request for Single Stage - One TF / A2913 Post Open - National 20,000.00 14,158.96 Implementati 2017-07-01 2017-07-01 2017-07-01 for PFT (office desks and program support and Quotations Envelope on chairs, bookshelf coordination. MW-MOEST-16447-GO-RFQ Component 5: Project / Supply of office Pending management, and sector Request for Single Stage - One refrigerator, electric fan, TF / A2913 Post Open - National 9,000.00 0.00 Implementati 2017-07-01 2017-07-01 2017-07-01 program support and Quotations Envelope kettle and vacuum flask for on coordination. PFT MW-MOEST-16403-GO-RFQ Component 5: Project Pending / Supply of Laptops, LCD management, and sector Request for Single Stage - One TF / A2913 Post Open - National 19,500.00 0.00 Implementati 2017-07-01 2017-07-01 2017-07-01 Projectors and Projector program support and Quotations Envelope on Screens coordination. Component 1: Performance- MW-MOEST-16272-GO-RFQ Pending based school improvement Request for Single Stage - One / Design and printing of TF / A2913 Post Open - National 32,000.00 0.00 Implementati 2017-06-02 2017-07-28 2018-01-24 grants for improving Quotations Envelope training materials on promotion and retention. Component 1: Performance- MW-MOEST-16278-GO-RFQ Pending based school improvement Request for Single Stage - One / Supply of stationery TF / A2913 Post Open - National 14,000.00 0.00 Implementati 2017-06-02 2017-07-28 2018-01-24 grants for improving Quotations Envelope materials for training on promotion and retention. Component 5: Project Pending MW-MOEST-16281-GO-RFQ management, and sector Request for Single Stage - One TF / A2913 Post Open - National 39,500.00 0.00 Implementati 2017-06-10 2017-08-05 2018-02-01 / Office Equipment for PFT program support and Quotations Envelope on coordination. Component 5: Project MW-MOEST-16283-GO-RFQ Under management, and sector Request for Single Stage - One / Supply of office furniture TF / A2913 Post Open - National 20,000.00 0.00 Implementati 2017-06-10 2017-08-05 2018-02-01 program support and Quotations Envelope for PFT on coordination. Page 5 Component 5: Project MW-MOEST-44643-GO-DIR management, and sector / Supply of accounting TF / A2913 Prior Direct Selection Direct 55,000.00 66,891.67 Signed 2018-01-19 2018-01-24 2018-02-28 2018-08-27 program support and software (Tompro) coordination. Component 5: Project MW-MOEST-56044-GO-RFQ Pending management, and sector Request for Single Stage - One / Supply and delivery of TF / A2913 Post Limited 99,995.00 0.00 Implementati 2018-04-03 2018-04-30 2018-05-15 program support and Quotations Envelope Two PFT Vehicles (4x4) on coordination. MW-MOEST-56052-GO-RFQ Component 5: Project Pending / Supply and Installation of management, and sector Request for Single Stage - One TF / A2913 Post Limited 10,000.00 0.00 Implementati 2018-04-04 2018-05-18 2018-05-30 Local Area Network (LAN) program support and Quotations Envelope on for accounting system coordination. Component 2: Improving MW-MOEST-56059-GO-RFQ Pending Equity for the most Request for Single Stage - One / Supply and delivery of TF / A2913 Post Limited 30,000.00 0.00 Implementati 2018-04-03 2018-05-04 2018-05-31 disadvantaged, including Quotations Envelope tablets for component two on girls. Component 5: Project MW-MOEST-56064-GO-RFQ Pending management, and sector Request for Single Stage - One / Supply and delivery of TF / A2913 Post Limited 12,000.00 0.00 Implementati 2018-04-04 2018-04-23 2018-05-21 program support and Quotations Envelope additional PFT furniture on coordination. MW-MOEST-56068-GO-RFQ Component 5: Project Pending / Supply and delivery of management, and sector Request for Single Stage - One TF / A2913 Post Limited 7,000.00 0.00 Implementati 2018-04-11 2018-04-30 2018-05-11 computer desktops for program support and Quotations Envelope on Tompro Training coordination. Component 3: Improving MW-MOEST-16404-GO-RFB learning outcomes, Single Stage - One / Printing and delivery of TF / A2913 Post Request for Bids Open - National 753,425.00 0.00 Canceled 2017-09-15 2017-09-15 2017-09-15 2017-09-15 2017-09-15 2017-09-15 accountability and cost- Envelope school registers effectiveness at school level. Component 3: Improving MW-MOEST-78219-GO-RFQ Pending learning outcomes, Request for Single Stage - One / Printing and Supply of TF / A2913 Post Limited 99,200.00 0.00 Implementati 2018-09-19 2018-10-26 2018-11-30 accountability and cost- Quotations Envelope Registers on effectiveness at school level. MW-MOEST-100843-GO- Component 3: Improving Pending RFQ / Supply and Delivery learning outcomes, Request for Single Stage - One TF / A2913 Post Limited 35,000.00 0.00 Implementati 2019-03-02 2019-04-27 2019-10-24 of Laptops, Printers and accountability and cost- Quotations Envelope on LCD Projectors effectiveness at school level. Component 5: Project MW-MOEST-104400-GO- Pending management, and sector Request for Single Stage - One RFQ / Supply of switchboard TF / A2913 Post Limited 5,000.00 0.00 Implementati 2019-03-23 2019-05-18 2019-11-14 program support and Quotations Envelope to MESIP offices on coordination. Component 3: Improving Pending MW-MOEST-104794-GO- learning outcomes, Request for Single Stage - One TF / A2913 Post Limited 10,000.00 0.00 Implementati 2019-03-30 2019-05-25 2019-11-21 RFQ / Printing of modules accountability and cost- Quotations Envelope on effectiveness at school level. MW-MOEST-117589-GO- Component 5: Project Pending RFQ / Supply and Delivery management, and sector Request for Single Stage - One TF / A2913 Post Limited 12,000.00 0.00 Implementati 2018-04-30 2018-05-15 2018-06-01 of a server for accounting program support and Quotations Envelope on system and email hosting coordination. MW-MOEST-117597-GO- Component 5: Project Pending RFQ / Printing and supply management, and sector Request for Single Stage - One TF / A2913 Post Limited 4,000.00 0.00 Implementati 2018-11-05 2018-11-28 2019-01-21 of 2019 Calendars and program support and Quotations Envelope on Diaries coordination. Page 6 MW-MOEST-117788-GO- RFQ / Supply and delivery Component 1: Performance- Pending of Cameras, Projectors, based school improvement Request for Single Stage - One TF / A2913 Post Limited 15,000.00 0.00 Implementati 2019-01-14 2019-01-25 2019-03-01 Projector Screens, Projector grants for improving Quotations Envelope on Bags, Laptops and External promotion and retention. Drives MW-MOEST-117791-GO- Component 5: Project Pending RFQ / Printing and Delivery management, and sector Request for Single Stage - One TF / A2913 Post Limited 2,500.00 0.00 Implementati 2018-10-10 2018-11-13 2019-01-30 of Grievance Report program support and Quotations Envelope on Mechanism (GRM) coordination. MW-MOEST-118451-GO- RFQ / Production and printing of standardized Component 1: Performance- Pending tests for Standard 3 and 4 based school improvement Request for Single Stage - One TF / A2913 Post Limited 88,000.00 0.00 Implementati 2019-06-29 2019-08-24 2019-09-23 to verify effectiveness of the grants for improving Quotations Envelope on strategies adopted in promotion and retention. reducing repetition and drop out MW-MOEST-119531-GO- Component 1: Performance- Pending RFQ / Supply and delivery based school improvement Request for Single Stage - One TF / A2913 Post Limited 10,000.00 0.00 Implementati 2019-07-06 2019-08-15 2019-08-18 of Heavy Duty Printer for grants for improving Quotations Envelope on Component 3 promotion and retention. MW-MOEST-119558-GO- Component 1: Performance- RFQ / Supply and delivery Pending based school improvement Request for Single Stage - One of protective gear for TF / A2913 Post Limited 1,500.00 0.00 Implementati 2019-07-06 2019-08-06 2019-09-21 grants for improving Quotations Envelope motorcycle users (boots and on promotion and retention. wind breakers) MW-MOEST-118802-GO- Component 5: Project Pending RFQ / Supply and delivery management, and sector Request for Single Stage - One TF / A2913 Post Limited 7,000.00 0.00 Implementati 2019-09-06 2019-10-05 2019-10-19 of Cameras for capacity program support and Quotations Envelope on building coordination. MW-MOEST-119557-GO- Component 5: Project Pending RFQ / Printing and delivery management, and sector Request for Single Stage - One TF / A2913 Post Limited 40,000.00 0.00 Implementati 2019-08-06 2019-09-13 2019-10-13 of safeguards User Manuals program support and Quotations Envelope on for PEAs coordination. MW-MOEST-119408-GO- RFQ / Supply and delivery Component 3: Improving Pending of computer server and learning outcomes, Request for Single Stage - One TF / A2913 Post Limited 13,000.00 0.00 Implementati 2019-07-06 2019-08-06 2019-08-09 protection software licence accountability and cost- Quotations Envelope on (Antiviruses, Malwares, effectiveness at school level. Spyware etc) Component 5: Project MW-MOEST-119610-GO- Pending management, and sector Request for Single Stage - One RFQ / Printing and delivery TF / A2913 Post Limited 2,086.00 0.00 Implementati 2019-07-06 2019-08-08 2019-09-07 program support and Quotations Envelope of 10 upright banners on coordination. MW-MOEST-119412-GO- Component 5: Project Pending RFQ / Printing and delivery management, and sector Request for Single Stage - One TF / A2913 Post Limited 1,738.00 0.00 Implementati 2019-07-06 2019-08-06 2019-09-05 of 2,500 MESIP posters in 3 program support and Quotations Envelope on languages coordination. Component 5: Project MW-MOEST-119570-GO- Pending management, and sector Request for Single Stage - One RFQ / Supply and delivery TF / A2913 Post Limited 1,000.00 0.00 Implementati 2019-07-06 2019-08-06 2019-09-05 program support and Quotations Envelope of cash chest on coordination. MW-MOEST-118446-GO- Component 5: Project RFQ / Printing of 200 Pending management, and sector Request for Single Stage - One calendars (3 month view), TF / A2913 Post Limited 4,620.00 0.00 Implementati 2019-09-06 2019-10-25 2019-11-24 program support and Quotations Envelope 2000 calendars (12 months on coordination. view) and 150 branded diaries Page 7 MW-MOEST-119545-GO- RFQ / Printing and delivery Component 1: Performance- of curriculum and manual Pending based school improvement Request for Single Stage - One for Mother Group Art and TF / A2913 Post Limited 41,000.00 0.00 Implementati 2019-10-06 2019-11-06 2019-12-06 grants for improving Quotations Envelope Craft Clubs and revised on promotion and retention. strategies, guidelines and PBF Brochures. MW-MOEST-119609-GO- RFQ / Procurement of Component 1: Performance- Pending stationery and toners for based school improvement Request for Single Stage - One TF / A2913 Post Limited 35,000.00 0.00 Implementati 2019-08-06 2019-09-06 2019-10-06 printing of report cards by grants for improving Quotations Envelope on ZEMIS officers and promotion and retention. standardized tests MW-MOEST-124758-GO- Component 5: Project RFQ / Supply and delivery Pending management, and sector Request for Single Stage - One of laptops for additional PFT TF / A2913 Post Limited 7,000.00 0.00 Implementati 2019-01-31 2019-03-24 2019-05-23 program support and Quotations Envelope staff and mobile phones for on coordination. FMS and CM2 MW-MOEST-124746-GO- Component 5: Project Pending RFQ / Supply and delivery management, and sector Request for Single Stage - One TF / A2913 Post Limited 2,000.00 0.00 Implementati 2019-07-02 2019-07-17 2019-08-16 of 3 laptops and projector program support and Quotations Envelope on bag for PFT coordination. Component 5: Project MW-MOEST-125655-GO- Pending management, and sector Request for Single Stage - One RFQ / Printing and delivery TF / A2913 Post Limited 3,130.00 0.00 Implementati 2019-08-10 2019-09-10 2019-10-10 program support and Quotations Envelope of 300 magazines on coordination. MW-MOEST-125657-GO- Component 5: Project Pending RFQ / Printing of 1500 management, and sector Request for Single Stage - One TF / A2913 Post Limited 3,336.00 0.00 Implementati 2019-08-31 2019-10-01 2019-10-31 newsletters and 5000 A5 program support and Quotations Envelope on leaflets coordination. NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 5: Project MW-MOEST-16452-NC-RFQ Under management, and sector Request for Single Stage - One / Supply and installation of TF / A2913 Post Open - National 5,500.00 0.00 Implementati 2017-07-01 2017-07-01 2017-07-01 program support and Quotations Envelope internet router for PFT on coordination. MW-MOEST-56039-NC-DIR Component 2: Improving / Supply and installation of Equity for the most TF / A2913 Prior Direct Selection Direct 120,000.00 209,343.00 Signed 2018-04-10 2018-04-15 2018-05-20 2018-11-16 software for tablet reporting disadvantaged, including system girls. MW-MOEST-100810-NC-RFP Component 5: Project Pending / Information Communication management, and sector Request for Single Stage - One TF / A2913 Post Open - National 60,000.00 0.00 Implementati 2019-02-25 2019-03-02 2019-04-13 2019-05-13 2019-06-17 2020-06-16 Technology (ICT) program support and Proposals Envelope on maintenance services coordination. Component 5: Project MW-MOEST-16458-NC-RFQ management, and sector Request for Single Stage - One / Web site design and email TF / A2913 Post Open - National 5,000.00 0.00 Canceled 2017-07-01 2017-07-01 2017-07-01 program support and Quotations Envelope hosting for PFT coordination. Component 1: Performance- Pending MW-MOEST-104396-NC-RFP based school improvement Request for Single Stage - Two TF / A2913 Post Limited 20,000.00 0.00 Implementati 2019-03-18 2019-03-23 2019-05-04 2019-05-28 2019-06-13 2020-06-12 / Hosting of MESIP website grants for improving Proposals Envelope on promotion and retention. Page 8 MW-MOEST-119417-NC- Component 5: Project Pending RFQ / Production and airing management, and sector Request for Single Stage - One TF / A2913 Post Limited 18,673.00 0.00 Implementati 2019-06-29 2019-08-06 2020-02-02 of 48 (30 mins & 15 mins) program support and Quotations Envelope on radio pgms coordination. MW-MOEST-119428-NC- Component 5: Project Pending RFQ / Production and airing management, and sector Request for Single Stage - One TF / A2913 Post Limited 31,000.00 0.00 Implementati 2019-07-06 2019-08-06 2019-09-05 of 48 (30 min & 15 min) program support and Quotations Envelope on TV programs coordination. MW-MOEST-119604-NC- Component 5: Project RFQ / Printing and delivery management, and sector Request for Single Stage - One of 300 annual magazines, TF / A2913 Post Limited 6,466.00 0.00 Canceled 2019-08-09 2019-09-09 2019-09-12 program support and Quotations Envelope 1500 newsletters and 5000 coordination. A5 leaflets CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-MOEST-16451-CS- QCBS / Consultancy services for provision of school Component 3: Improving leadership training learning outcomes, Quality And Cost- Open - programme for head-teachers, TF / A2913 Prior 700,000.00 881,079.00 Signed 2015-12-17 2015-12-17 2015-12-17 2015-12-17 2015-12-17 2015-12-17 2015-12-17 2015-12-17 accountability and cost- Based Selection International deputy head teachers, and effectiveness at school level. primary education advisers in 800 schools in 34 education districts MW-MOEST-16453-CS- Component 3: Improving QCBS / Consultancy services learning outcomes, Quality And Cost- Open - to develop a platform for TF / A2913 Prior 500,000.00 775,839.89 Signed 2016-01-07 2016-01-07 2016-01-07 2016-01-07 2016-01-07 2016-01-07 2016-01-07 2016-01-07 accountability and cost- Based Selection International real time school data effectiveness at school level. collection and SMS MW-MOEST-78217-CS- QCBS / Consultancy Services Component 3: Improving to Conduct Evaluation of learning outcomes, Quality And Cost- School Leadership Training TF / A2913 Post Open - National 145,000.00 0.00 Canceled 2018-09-24 2018-10-15 2018-11-28 2018-12-26 2019-01-25 2019-03-01 2019-04-05 2019-08-31 accountability and cost- Based Selection Program for Head Teachers, effectiveness at school level. Deputy Head Teachers and Primary Education Advisors Component 5: Project MW-MOEST-82815-CS-LCS management, and sector Least Cost Under / Auditing Services for TF / A2913 Post Open - National 120,000.00 0.00 2018-10-22 2018-10-22 2018-10-25 2018-10-31 2018-11-05 2018-11-13 2018-11-28 2019-05-27 program support and Selection Implementation MESIP coordination. MW-MOEST-107600-CS- QCBS / Consultancy Services Component 5: Project to conduct an independent management, and sector Quality And Cost- Under TF / A2913 Post Open - National 150,000.00 0.00 2019-03-29 2019-04-15 2019-05-29 2019-06-26 2019-07-26 2019-08-30 2019-10-04 2020-01-31 verification of achievement program support and Based Selection Implementation for the Disbursement Linked coordination. Indicators under MESIP INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 9 MW-MOEST-16445-CS-INDV / Four Individual consultancies for engineering Component 2: Improving Individual services in eight districts Equity for the most Under TF / A2913 Post Consultant Open 7,788.00 0.00 2015-01-10 2015-01-10 2015-01-10 2015-01-10 2015-01-10 (Mzimba, Kasungu, Lilongwe disadvantaged, including Implementation Selection Rural West, Dedza, girls. Mangochi, Machinga, Thyolo & Chikwawa) MW-MOEST-16449-CS-INDV / Forty Individual consultancies for clerk of Component 2: Improving Individual works services in districts Equity for the most Pending TF / A2913 Post Consultant Open 46,207.00 0.00 2017-09-01 2017-09-01 2017-09-01 2017-09-01 2017-09-01 (Mzimba, Kasungu, Lilongwe disadvantaged, including Implementation Selection Rural West, Dedza, girls. Mangochi, Machinga, Thyolo & Chikwawa) Component 5: Project Individual MW-MOEST-16462-CS-INDV management, and sector Pending TF / A2913 Post Consultant Open 41,100.00 0.00 2017-06-30 2017-08-09 2017-08-14 2017-08-14 2017-08-14 / Communication specialist program support and Implementation Selection coordination. Component 5: Project MW-MOEST-73886-CS-INDV Individual management, and sector Under / Financial Management TF / A2913 Prior Consultant Limited 41,000.00 0.00 2018-08-17 2018-08-22 2018-08-31 2018-09-10 2020-12-31 program support and Implementation Specialist Selection coordination. Component 5: Project Individual MW-MOEST-80730-CS-INDV management, and sector Pending TF / A2913 Post Consultant Open 58,800.00 0.00 2018-10-04 2018-10-04 2018-10-09 2018-10-11 2019-02-28 / Project Facilitator program support and Implementation Selection coordination. Component 5: Project Individual MW-MOEST-80819-CS-INDV management, and sector Pending TF / A2913 Post Consultant Open 41,000.00 0.00 2018-10-05 2018-10-05 2018-10-10 2018-10-16 2021-01-12 / Procurement Specialist program support and Implementation Selection coordination. Component 5: Project MW-MOEST-80821-CS-INDV Individual management, and sector Pending / Monitoring and Evaluation TF / A2913 Post Consultant Open 41,000.00 0.00 2018-10-05 2018-10-05 2018-10-05 2018-10-11 2021-01-07 program support and Implementation Specialist Selection coordination. Component 5: Project MW-MOEST-80824-CS-INDV Individual management, and sector Pending / Assistant Procurement TF / A2913 Post Consultant Open 25,200.00 0.00 2018-10-05 2018-10-05 2018-10-05 2018-10-10 2020-12-31 program support and Implementation Specialist Selection coordination. Component 5: Project MW-MOEST-80825-CS-INDV Individual management, and sector Pending / Assistant Financial TF / A2913 Post Consultant Open 25,200.00 0.00 2018-10-05 2018-10-05 2018-10-10 2018-10-29 2020-12-31 program support and Implementation Management Specialist Selection coordination. Component 5: Project Individual MW-MOEST-80828-CS-INDV management, and sector Pending TF / A2913 Post Consultant Open 25,200.00 0.00 2018-10-05 2018-10-05 2018-10-15 2018-10-25 2020-12-31 / Project Assistant program support and Implementation Selection coordination. MW-MOEST-116980-CS- Component 3: Improving INDV / Individual Individual learning outcomes, Under consultancy (International) to TF / A2913 Post Consultant Open 80,000.00 0.00 2019-06-17 2019-07-16 2019-07-26 2019-08-30 2020-02-26 accountability and cost- Implementation conduct evaluation of School Selection effectiveness at school level. leadership training MW-MOEST-116981-CS- Component 3: Improving INDV / Individual Individual learning outcomes, Under Consultancy (National) to TF / A2913 Post Consultant Open 65,000.00 0.00 2019-06-17 2019-08-05 2019-08-26 2019-09-30 2020-03-28 accountability and cost- Implementation conduct evaluation of School Selection effectiveness at school level. Leadership Training Page 10 MW-MOEST-117795-CS- Component 3: Improving INDV / Provision of Events Individual learning outcomes, Pending Management Services on TF / A2913 Post Consultant Limited 9,000.00 0.00 2018-10-22 2018-12-10 2018-12-14 2019-01-01 2019-03-06 accountability and cost- Implementation launch of Community Selection effectiveness at school level. Sensitization Meetings Page 11