Procurement Plan First South West Indian Ocean Fisheries Governance and Shared Growth project P132123 IOC Mauritius I. General 2. Bank’s approval Date of the procurement Plan : October 2015 ; Revision ongoing 3. Date of General Procurement Notice: N/A 4. Period covered by this procurement plan: The procurement period of project covered for January 2017 to December 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: 2. Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 4,000,000 All 2. NCB (Goods) Above US$ 500,000 None 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 None [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [N/A 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manuel 2016 5. Any Other Special Procurement Arrangements: N/A 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce July 9, 2010 (yes/no) Summary of 0,114 5 No Post the Shopping (Goods) Summary of 0,662 23 No Post the Shopping (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 200,000 2. Single Source (Firms) All 3. Individual Above US$ 400,000 2. Short list comprising entirely of regional consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: N/A 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of number 0.020 2 Post of contracts that will be let under QCBS Summary of number 0.192 3 Prior of contracts that will be let under SSS Summary of number 0,006 1 Prior of contracts that will be let under LCS July 9, 2010 PROCUREMENT Africa : AFCC2/RI-South West Indian Ocean Fisheries Governance and Shared Growth Project 1 PLAN General Information Country: Africa Banks Approval Date of the Original Procurement Plan: 2017-03-08 Revised Plan Date(s): (comma delineated, leave blank if none) 2017-10-06 Project ID: P132123 GPN Date: Project Name: AFCC2/RI-South West Indian Ocean Fisheries Governance and Shared Growth Project 1 Loan / Credit No: IDA / 55890, IDA / 55460, IDA / Q8660 Executing Agency(ies): Ministry of Agriculture,Natural Resources, Livestock and Fisheries, The Deep See Fishing Authority, Ministry of Sea, Interior Waters and Fisheries, Ministry of Livestock and Fisheries Development WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MANRLF-8435-CW-RFQ / Construction of New Office Component 2. Improved Request for Single Stage - One Pending Buildings for TUMCA, IDA / 55890 Post Open - National 0.00 2017-05-29 2017-08-09 2018-02-05 governance of priority fisheries Quotations Envelope Implementation CHABAMCA and Ranger Posts (Pungume) TZ-MANRLF-8432-CW-RFB / Construction of Zanzibar Marine Component 2. Improved Single Stage - One Pending IDA / 55890 Post Request for Bids Open - National 0.00 2017-05-15 2017-05-20 2017-06-19 2017-07-10 2017-08-14 2018-02-10 Research Unit in NYANGUMI governance of priority fisheries Envelope Implementation HOUSE TZ-MANRLF-24229-CW-RFQ / Component 2. Improved Request for Single Stage - One Pending Refurbish SFC offices/resource IDA / 55890 Post Open - National 0.00 2017-09-02 2017-10-28 2018-04-26 governance of priority fisheries Quotations Envelope Implementation centers TZ-MANRLF-8433-CW-RFQ / Rehabilitation of MBCA (Kizimkazi, Fumba and Component 2. Improved Request for Single Stage - One Pending Kikungwi, Mesali Island IDA / 55890 Post Open - National 0.00 2017-05-30 2017-08-10 2018-02-06 governance of priority fisheries Quotations Envelope Implementation Conservation Area (main office), PECCA (main office) and Ranger Post in Mesali Island TZ-DSFA-8978-CW-RFB / Constructions of Boat Ramp at Component 2. Improved Single Stage - One Pending IDA / 55890 Prior Request for Bids Open - National 0.00 2017-03-13 2017-03-13 2017-03-13 2017-03-13 2017-03-13 2017-03-13 Deep Sea Fishing Authority governance of priority fisheries Envelope Implementation (Tuna Fishery) GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MANRLF-8259-GO-RFQ / Supply of Research and Component 2. Improved Request for Single Stage - One Pending IDA / 55890 Post Open - National 0.00 2017-03-12 2017-05-07 2017-11-03 Monitoring Equipment for Priority governance of priority fisheries Quotations Envelope Implementation Fisheries TZ-DSFA-8980-GO-RFQ / supply of laboratory equipments Component 2. Improved Request for Single Stage - One IDA / 55890 Post Open - National 43,887.87 Signed 2017-03-11 2017-05-06 2017-06-22 2017-08-04 and chemical for Deep Sea governance of priority fisheries Quotations Envelope Fishing Authority MZ-MMAIP-9071-GO-RFQ / Component 2. Improved Request for Single Stage - One IDA / 55460 Post Limited 80,578.53 Signed 2017-05-18 2017-03-24 2017-09-15 2017-05-02 2018-09-15 Motorcycles governance of priority fisheries Quotations Envelope MZ-MMAIP-9075-GO-RFB / Component 4. Project Single Stage - One Under IDA / 55460 Post Request for Bids Open - National 0.00 2017-05-31 2017-04-12 2017-06-30 2017-05-09 2017-08-11 2017-05-09 2017-09-25 2017-05-23 2017-11-19 2018-11-19 Videoconference equipment management and coordination Envelope Implementation TZ-MLFD-9175-GO-RFQ / SUPPLY, INSTALLATION AND TRAINING OF GIS SOFTWARE Component 2. Improved Request for Single Stage - One Pending IDA / 55890 Post Open - National 0.00 2017-03-06 2017-04-25 2017-10-22 LICENSES FOR FISHERIES governance of priority fisheries Quotations Envelope Implementation DEVELOPMENT DIVISION FOR FDD TZ-MLFD-9178-GO-RFQ / Component 2. Improved Request for Single Stage - One Pending IDA / 55890 Post Open - National 0.00 2017-03-06 2017-04-25 2017-10-22 Supply of Underwater Camera governance of priority fisheries Quotations Envelope Implementation TZ-MLFD-9208-GO-RFQ / Supply of equipment for patrol Component 2. Improved Request for Single Stage - One Pending camps (Tents, Life IDA / Q8660 Post Open - National 0.00 2017-03-07 2017-04-25 2017-10-22 governance of priority fisheries Quotations Envelope Implementation jackets,Binocular and Radio call) for Mbudya, Bongoyo & Sinda TZ-MANRLF-8273-GO-RFB / Supply of Demarcation Buoys for Component 2. Improved Single Stage - One Pending IDA / 55890 Post Request for Bids Open - National 0.00 2017-03-15 2017-03-20 2017-05-01 2017-05-31 2017-07-05 2018-01-01 Selected Marine Conservation governance of priority fisheries Envelope Implementation Areas TZ-DSFA-11207-GO-RFQ / M&E Equipment(server,computer & software), this activity was Component 2. Improved Request for Single Stage - One Pending included in activity of supply of IDA / 55890 Post Open - National 0.00 2017-04-29 2017-06-24 2017-12-21 governance of priority fisheries Quotations Envelope Implementation computer IT Equipment, software and communication Equipment for DSFA. TZ-MLFD-11460-GO-RFQ / Supply of research fishing gears Component 2. Improved Request for Single Stage - One Pending and equipment for priority IDA / 55890 Post Open - National 0.00 2017-04-08 2017-06-03 2017-11-30 governance of priority fisheries Quotations Envelope Implementation fisheries (Lot 1. Octopus and Lot 2. Prawn) Page 1 TZ-MLFD-11462-GO-RFQ / Supply and installation of Vessel Component 2. Improved Request for Single Stage - One Pending Monitoring System (VMS) sub- IDA / 55890 Post Open - National 0.00 2017-04-08 2017-06-03 2017-11-30 governance of priority fisheries Quotations Envelope Implementation station for surveillance of territorial waters TZ-MLFD-11464-GO-RFQ / Purchase of Management Component 4. Project Request for Single Stage - One Pending Information System (MIS) IDA / 55890 Post Open - National 0.00 2017-04-09 2017-06-04 2017-12-01 management and coordination Quotations Envelope Implementation Software license for Mainland, Zanzibar and DSFA TZ-MLFD-11465-GO-RFQ / Supply of Monitoring and Component 4. Project Request for Single Stage - One Pending Evaluation (M&E server) IDA / 55890 Post Open - National 0.00 2017-04-09 2017-06-04 2017-12-01 management and coordination Quotations Envelope Implementation equipment for National Management Unit TZ-MLFD-11466-GO-RFQ / Supply of Information Technology Component 2. Improved Request for Single Stage - One Under IDA / 55890 Post Open - National 0.00 2017-04-09 2017-06-04 2017-12-01 and Communication Equipment governance of priority fisheries Quotations Envelope Implementation with related Accessories TZ-MLFD-11467-GO-RFQ / Supply of research fishing gears Component 2. Improved Request for Single Stage - One Pending and equipment for priority IDA / 55890 Post Open - National 0.00 2017-04-09 2017-06-04 2017-12-01 governance of priority fisheries Quotations Envelope Implementation fisheries (Lot 3 Small Pelagic and Lot 4. Tuna TZ-DSFA-15214-GO-RFQ / Component 2. Improved Request for Single Stage - One IDA / 55890 Post Open - National 11,594.51 Signed 2017-05-25 2017-06-15 2017-06-22 2017-12-12 Supply of office furniture governance of priority fisheries Quotations Envelope TZ-MLFD-8282-GO-RFB / Component 2. Improved Single Stage - One Supply of 12 Motor Vehicle and IDA / 55890 Post Request for Bids Open - National 670,773.74 Signed 2017-02-23 2016-08-22 2017-02-23 2017-02-23 2016-09-20 2017-03-09 2016-09-30 2017-07-03 2017-06-19 2017-12-30 governance of priority fisheries Envelope 17 Motor cycles TZ-MLFD-20419-GO-RFQ / SUPPLY, INSTALLATION AND TESTING OF 2 BOAT, Component 2. Improved Request for Single Stage - One Pending OUTBOARD ENGINE AND ITS IDA / 55890 Post Open - National 0.00 2017-07-13 2017-09-07 2017-12-06 governance of priority fisheries Quotations Envelope Implementation ACCESSORIES FOR TACMP AND FETA (FIBRE GLASS BOAT) MZ-MMAIP-9009-GO-RFQ / Component 2. Improved Request for Single Stage - One Pending IDA / 55460 Post Limited 0.00 2017-09-20 2018-02-02 2018-05-03 Office furniture governance of priority fisheries Quotations Envelope Implementation MZ-MMAIP-21863-GO-RFQ / Accounting and Procurement Component 4. Project Request for Single Stage - One Pending IDA / 55460 Post Open - National 0.00 2017-08-18 2017-10-13 2018-10-13 Software and technical management and coordination Quotations Envelope Implementation assistandce MZ-MMAIP-9069-GO-RFQ / Component 2. Improved Request for Single Stage - One Pending IDA / 55460 Post Limited 0.00 2017-08-26 2017-12-09 2018-02-07 Fisheries sampling equipment governance of priority fisheries Quotations Envelope Implementation MZ-MMAIP-22966-GO-DIR / Component 2. Improved Pending IDA / 55460 Post Direct Selection Direct 0.00 2017-08-31 2017-09-05 2017-10-10 2019-10-18 Laboratory Proficience Test governance of priority fisheries Implementation MZ-MMAIP-23325-GO-RFQ / Component 2. Improved Under Vessel Monitoring System IDA / 55460 Post Direct Selection Direct 0.00 2017-08-10 2017-08-21 2017-08-20 2017-09-27 2018-09-27 governance of priority fisheries Implementation (VMS) License MZ-MMAIP-9015-GO-RFB / Component 2. Improved Single Stage - One Under Computers equipment and IDA / 55460 Prior Request for Bids Open - National 0.00 2017-08-18 2017-08-29 2017-09-15 2017-09-10 2017-10-27 2017-12-03 2018-02-01 2018-04-02 governance of priority fisheries Envelope Implementation software MZ-MMAIP-9067-GO-RFQ / GIS Component 2. Improved Request for Single Stage - One Pending software license and related IDA / 55460 Post Limited 0.00 2017-09-12 2017-12-26 2018-02-24 governance of priority fisheries Quotations Envelope Implementation hardware MZ-MMAIP-9074-GO-RFQ / Component 4. Project Request for Single Stage - One Pending IDA / 55460 Post Limited 0.00 2017-09-09 2017-11-23 2017-12-23 Communication equipment management and coordination Quotations Envelope Implementation MZ-MMAIP-9070-GO-RFQ / C0- Component 2. Improved Request for Single Stage - One Pending IDA / 55460 Post Limited 0.00 2017-08-28 2017-12-14 2018-02-12 management equipment governance of priority fisheries Quotations Envelope Implementation TZ-MANRLF-10324-GO-RFB / Supply of Fisheries Patrol Boats Component 2. Improved Single Stage - One Pending IDA / 55890 Post Request for Bids Open - National 0.00 2016-12-25 2016-12-25 2016-12-25 2017-03-23 2017-04-27 2017-10-24 and Communications Equipment governance of priority fisheries Envelope Implementation for 3 Marine Conservation Areas TZ-MANRLF-8293-GO-RFQ / 1 Component 2. Improved Request for Single Stage - One IDA / 55890 Post Open - National 0.00 Canceled 2017-03-22 2017-05-17 2017-11-13 car for Department of Fisheries governance of priority fisheries Quotations Envelope TZ-MANRLF-24271-GO-RFQ / Component 2. Improved Request for Single Stage - One Pending Equipment for quality control of IDA / 55890 Post Open - National 0.00 2017-10-03 2017-11-28 2018-05-27 governance of priority fisheries Quotations Envelope Implementation priority fisheries catch data TZ-MANRLF-24278-GO-RFQ / Component 2. Improved Request for Single Stage - One Pending Procurement of Fisheries patrol IDA / 55890 Post Open - National 0.00 2017-10-23 2017-12-18 2018-06-16 governance of priority fisheries Quotations Envelope Implementation equipment for 3 MCAs TZ-MANRLF-24282-GO-RFQ / Component 2. Improved Request for Single Stage - One Pending Procurement of one motor cycle IDA / 55890 Post Open - National 0.00 2017-10-31 2017-12-26 2018-06-24 governance of priority fisheries Quotations Envelope Implementation for new district MZ-MMAIP-9073-GO-RFQ / Component 2. Improved Request for Single Stage - One Pending Boat surveillance equipment for IDA / 55460 Post Limited 0.00 2017-06-10 2017-10-08 2018-10-08 governance of priority fisheries Quotations Envelope Implementation CCP MZ-MMAIP-9068-GO-RFQ / Component 2. Improved Request for Single Stage - One Pending GPS equipment and Precision IDA / 55460 Post Limited 0.00 2017-04-14 2017-07-28 2018-07-28 governance of priority fisheries Quotations Envelope Implementation Equipment for DEPI & IIP Page 2 MZ-MMAIP-9072-GO-RFQ / Component 2. Improved Request for Single Stage - One Pending Navigation safety equipment for IDA / 55460 Post Limited 0.00 2017-04-15 2017-08-13 2018-08-13 governance of priority fisheries Quotations Envelope Implementation CCP TZ-MLFD-11463-GO-RFQ / Component 2. Improved Request for Single Stage - One Pending Supply of acoustic equipment for IDA / 55890 Post Open - National 0.00 2017-04-08 2017-06-03 2017-11-30 governance of priority fisheries Quotations Envelope Implementation dynamite fishing for FDD TZ-MLFD-9209-GO-DIR / Supply Component 2. Improved Pending of CTD Equipment for physical IDA / 55890 Post Direct Selection Direct 0.00 2017-07-13 2017-08-03 2017-09-28 2018-03-27 governance of priority fisheries Implementation Oceanographic paremeters TZ-DSFA-24530-GO-RFQ / Component 2. Improved Request for Single Stage - One Under IDA / 55890 Post Open - National 0.00 2017-09-05 2017-10-31 2018-04-29 Supply of Office furniture governance of priority fisheries Quotations Envelope Implementation TZ-DSFA-24531-GO-RFQ / Component 2. Improved Request for Single Stage - One Under Supply of IT equipment, software IDA / 55890 Post Open - National 0.00 2017-09-05 2017-10-31 2018-04-29 governance of priority fisheries Quotations Envelope Implementation and licenses TZ-MLFD-25824-GO-RFB / Component 2. Improved Single Stage - One Supply of 12 Motor Vehicle and IDA / 55890 Prior Request for Bids Open - National 670,773.74 Signed 2015-11-15 2015-11-25 2016-01-06 2016-09-20 2017-08-23 2017-08-23 2017-09-27 2017-06-15 2018-03-26 governance of priority fisheries Envelope 17 Motor cycles TZ-MANRLF-8287-GO-RFB / 2 cars for the 2 new MCAs Component 2. Improved Single Stage - One Under (CHABAMCA, TUMCA) and one IDA / 55890 Post Request for Bids Open - National 0.00 2017-04-04 2017-09-25 2017-04-09 2017-05-21 2017-06-20 2017-07-25 2018-01-21 governance of priority fisheries Envelope Implementation car for Department of fisheries Development NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-MMAIP-9027-NC-DIR / Component 2. Improved Under vessels charter (shrimp firheries IDA / 55460 Post Direct Selection Direct 0.00 2017-03-24 2017-04-01 2017-03-29 2017-04-19 2017-06-12 2018-11-30 governance of priority fisheries Implementation survey) MZ-MMAIP-22950-NC-DIR / Component 2. Improved Pending Vessels charter (shrimp fisheries IDA / 55460 Post Direct Selection Direct 0.00 2018-02-28 2018-03-05 2018-04-09 2018-05-09 governance of priority fisheries Implementation survey_2018) MZ-MMAIP-22951-NC-DIR / Component 2. Improved Pending Vessels Charter (small IDA / 55460 Post Direct Selection Direct 0.00 2017-09-28 2017-10-03 2017-11-07 2017-12-07 governance of priority fisheries Implementation pelagic_2017) MZ-MMAIP-22965-NC-DIR / Component 2. Improved Pending Sample Testing in Reference IDA / 55460 Post Direct Selection Direct 0.00 2017-09-12 2017-09-17 2017-10-22 2019-10-30 governance of priority fisheries Implementation Laboratories MZ-MMAIP-23390-NC-DIR / Component 2. Improved Pending Mass Calibration of Laboratory IDA / 55460 Post Direct Selection Direct 0.00 2017-08-25 2017-09-04 2017-10-14 2019-10-22 governance of priority fisheries Implementation Equipment MZ-MMAIP-23391-NC-DIR / Component 2. Improved Pending Laboratory volumetry equipment IDA / 55460 Post Direct Selection Direct 0.00 2017-08-25 2017-09-04 2017-10-19 2019-10-27 governance of priority fisheries Implementation calibration TZ-DSFA-24533-NC-DIR / Supply of Air patrols service for Component 2. Improved IDA / 55890 Prior Direct Selection Direct 0.00 Under Review 2017-08-31 2017-09-05 2017-09-22 2018-03-21 tuna fishery inside Exclusive governance of priority fisheries Economic Zone (EEZ). CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-MMAIP-9021-CS-QCBS / Component 2. Improved Quality And Cost- Evaluation of PESPA IDA / 55460 Post Open - National 242,720.53 Signed 2017-03-24 2017-04-01 2017-04-28 2017-06-30 2017-05-18 2017-08-11 2017-09-10 2017-06-30 2017-10-15 2017-11-28 2017-08-16 2019-04-30 governance of priority fisheries Based Selection implementation Plans MZ-MMAIP-9076-CS-QCBS / Component 3. Increased Elaboration of National Master Quality And Cost- Under IDA / 55460 economic benefits from priority Prior Open - International 0.00 2017-04-30 2017-05-30 2017-05-31 2017-08-16 2017-08-29 2017-09-28 2017-11-07 2018-01-06 2018-02-25 2020-01-31 Plan for infrastructure to support Based Selection Implementation fisheries fisheries and aquaculture MZ-MMAIP-9086-CS-QCBS / Component 3. Increased Quality And Cost- Study on facilitation of access to IDA / 55460 economic benefits from priority Post Open - National 60,411.67 Signed 2017-03-17 2017-03-22 2017-04-07 2017-06-06 2017-05-19 2017-07-06 2017-08-05 2017-06-30 2017-10-04 2017-08-11 2017-12-03 2017-08-30 2019-07-03 Based Selection finance fisheries TZ-MLFD-9166-CS-CQS / Consultancy services to develop Consultant Component 2. Improved Under Business pla for Kilindoni IDA / 55890 Post Qualification Open - National 0.00 2017-03-06 2016-09-09 2017-03-06 2017-03-13 2017-04-12 2017-05-17 2017-11-13 governance of priority fisheries Implementation Nyamisati & Masoko Pwani Selection Landing Sites TZ-MLFD-9168-CS-CQS / Consultancy Services to Conduct Component 3. Increased Consultant Pending Value Chain Analysis for small IDA / 55890 economic benefits from priority Post Qualification Open - National 0.00 2017-03-06 2017-03-06 2017-03-13 2017-04-12 2017-05-17 2017-11-13 Implementation pelagics, Artisanal Tuna, fisheries Selection Octopus and Prawns TZ-MLFD-9170-CS-CQS / Consultancy services for Consultant Component 2. Improved Pending designing of TAFIRI DSM Centre IDA / 55890 Post Qualification Open - National 0.00 2017-03-06 2017-03-06 2017-04-19 2017-05-19 2017-06-23 2017-12-20 governance of priority fisheries Implementation Wet Lab Building and TACMP Selection Staff Housing Compound Page 3 TZ-MANRLF-9663-CS-CQS / Consultant Consultancy services for Component 2. Improved Pending IDA / 55890 Post Qualification Open - National 0.00 2017-03-16 2017-04-06 2017-05-20 2017-06-19 2017-07-24 2018-01-20 designing of Zanzibar Marine governance of priority fisheries Implementation Selection Research Unit Building TZ-MANRLF-10339-CS-CQS / Consultancy Services for Component 3. Increased Consultant Pending Carrying out Enterprise Survey in IDA / 55890 economic benefits from priority Post Qualification Open - National 0.00 2016-08-30 2016-08-30 2016-08-30 2017-03-23 2017-04-13 2017-10-10 Implementation Marine Fisheries Business fisheries Selection (Mainland and Zanzibar) TZ-MANRLF-10332-CS-CQS / Component 3. Increased Consultant Consultancy Services for Under IDA / 55890 economic benefits from priority Post Qualification Open - National 0.00 2016-10-30 2016-10-30 2017-04-12 2017-05-12 2017-06-16 2017-12-13 Preparation of a Business Plan Implementation fisheries Selection for Tumbe Landing Sites TZ-MLFD-8295-CS-CQS / Component 3. Increased Consultant Consultancy services for external Under IDA / 55890 economic benefits from priority Post Qualification Open - National 0.00 2017-02-23 2016-02-25 2017-02-23 2017-02-23 2017-03-25 2017-04-29 2017-10-26 institution support for fisheries Implementation fisheries Selection research activities TZ-DSFA-8269-CS-CQS / Consultancy service for review of Consultant Deep Sea fishing Authority Component 2. Improved Under IDA / 55890 Prior Qualification Open - National 0.00 2017-03-03 2017-03-03 2017-03-03 2017-09-21 2017-03-03 2017-03-03 2017-03-03 (DSFA) current Act and governance of priority fisheries Implementation Selection Regulations and prepare the new draft. MZ-MMAIP-9084-CS-QCBS / Elaboration of Monitoring, Control Component 2. Improved Quality And Cost- Under IDA / 55460 Prior Open - National 0.00 2017-08-31 2017-08-14 2017-09-24 2017-09-12 2017-11-23 2017-12-24 2018-01-23 2018-03-08 2018-05-07 2019-11-23 and Surveillance Strategy for governance of priority fisheries Based Selection Implementation fisheries MZ-MMAIP-23156-CS-QCBS / Design and Establishment of an Component 2. Improved Quality And Cost- Pending IDA / 55460 Post Open - International 0.00 2017-11-30 2017-12-21 2018-02-03 2018-03-03 2018-04-02 2018-05-07 2018-07-20 2019-07-20 Integrated Fisheries Information governance of priority fisheries Based Selection Implementation System TZ-MANRLF-9523-CS-CQS / Consultancy Services to Conduct Study of fisheries & Economic Consultant impacts of Closures, train Component 2. Improved Under IDA / 55890 Post Qualification Open - National 0.00 2017-03-30 2017-04-20 2017-06-03 2017-07-03 2017-08-07 2018-02-03 selected DFD, District governance of priority fisheries Implementation Selection &exporters on seasonal closures and prepare communication video for trial closures TZ-DSFA-24537-CS-CQS / Consultancy services for Pre Consultant Feasibility study on Fishing ports Component 2. Improved Pending IDA / 55890 Prior Qualification Open - International 0.00 2018-12-14 2019-01-04 2019-02-13 2019-03-15 2019-04-19 2019-10-16 constructions and facilities for governance of priority fisheries Implementation Selection industrial and semi-industrial fleet. MZ-MMAIP-22997-CS-CQS / Component 3. Increased Quality And Cost- Under Promotion of savings and IDA / 55460 economic benefits from priority Prior Open - International 0.00 2017-08-18 2017-09-08 2017-10-22 2017-11-19 2017-12-19 2018-01-23 2018-04-07 2021-02-20 Based Selection Implementation revolving credit groups fisheries MZ-MMAIP-26547-CS-CQS / Component 3. Increased Consultant Under Value Chain Analyses for Small IDA / 55460 economic benefits from priority Post Qualification Open - National 0.00 2017-09-15 2017-09-05 2017-10-06 2017-09-29 2017-11-19 2017-12-19 2018-01-23 2018-05-08 Implementation Scale Fisheries fisheries Selection TZ-MANRLF-24289-CS-CQS / Consultancy Services to design Consultant MCS strategy, operational plan, Component 2. Improved Pending IDA / 55890 Post Qualification Open - National 0.00 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2018-07-27 development of reef fisheries governance of priority fisheries Implementation Selection protocol and information system development for 3 MCAs TZ-MANRLF-26871-CS-CQS / CONSULTANCY SERVICES FOR PREPARATION OF THREE Consultant Component 2. Improved Under MANAGEMENT PLANS FOR IDA / 55890 Post Qualification Open - National 0.00 2017-09-01 2017-09-25 2017-09-22 2017-11-05 2017-12-05 2018-01-09 2018-07-08 governance of priority fisheries Implementation REEF, OCTOPUS AND SMALL Selection PELAGIC FISHERIES IN ZANZIBAR INDIVIDUAL CONSULTANTS Page 4