Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: April 3, 2015]: Revision 9 of Updated Procurement Plan, Mar 2, 2017] 2. Date of General Procurement Notice: October 2015 3. Period covered by this procurement plan: The procurement period of project covered from October 2015 to December 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Prior Review Threshold Comments US$ 1. Works Above USD 10M All 2. Goods Above USD 2M All 2. Prequalification. Bidders for _more than US$ 10 million_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Reference to (if any) Project Operational/Procurement Manual: Project Operations Manual and SOPs for Procurement prepared by Planning and Development Department AJK, Provincial Disaster Management Authority Punjab and Punjab Irrigation Department. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 3. Consulting firms Above USD 1M All 4. Individual Consultants Above USD 0.3 M All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None March 30, 2017 PROCUREMENT Pakistan : Disaster and Climate Resilience Improvement Project PLAN General Information Country: Pakistan Banks Approval Date of the Original Procurement Plan: 2016-10-20 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-01-03 Project ID: P154036 GPN Date: Project Name: Disaster and Climate Resilience Improvement Project Loan / Credit No: IDA / 56860 Executing Agency(ies): PIU DCRIP Punjab Irrigation Department, Planning and Development Department, AJK, Provincial Disaster Management Authority Punjab WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PIU PID-2573-CW-RFB / Construction of Concavo-Convex Component 1: Restoring Flood Guide Wall Spur Tied with Mole Protection Infrastructure and Single Stage - One Head Spur at RD 2+750 of IDA / 56860 Prior Request for Bids Open - National 1,400,000.00 1,193,129.78 Signed 2016-10-14 2016-10-21 2016-10-16 2016-11-27 2016-11-08 2016-12-27 2016-12-15 2017-01-31 2017-03-14 2017-05-30 Upgrading Flood Management Envelope Colony Protection Bund Systems Downstream Left of Punjnand Head Works PK-PIU PID-2576-CW-RFB / Restoration Haveli Main Line RD Component 1: Restoring Flood 8+000 to RD 63+000 and its Protection Infrastructure and Single Stage - One IDA / 56860 Prior Request for Bids Open - National 1,346,000.00 1,135,469.45 Signed 2016-10-14 2016-10-21 2016-10-15 2016-10-17 2016-11-16 2016-11-17 2016-12-21 2017-03-13 2017-04-19 Allied Hydraulic Structures and Upgrading Flood Management Envelope Repairing of Escape Damaged Systems During Flood 2014 PK-PIU PID-2812-CW-RFB / Component 1: Restoring Flood Strengthening of River Training Protection Infrastructure and Single Stage - One IDA / 56860 Post Request for Bids Open - National 4,165,000.00 3,674,364.55 Signed 2016-10-28 2016-11-02 2016-12-06 2017-01-05 2016-12-23 2017-02-09 2017-03-15 2017-10-17 Works of Islam Headworks Upgrading Flood Management Envelope bringing to Design Parameters Systems PK-PIU PID-4943-CW-RFB / Component 1: Restoring Flood Restoration of Hassuwali Flood Protection Infrastructure and Single Stage - One Bund along with its River Training IDA / 56860 Post Request for Bids Open - National 3,000,000.00 2,548,581.48 Signed 2016-12-26 2016-11-22 2016-12-27 2017-01-26 2016-12-30 2017-02-25 2017-04-28 2017-04-01 2017-05-19 2017-09-28 Upgrading Flood Management Envelope Structures Damaged During Systems Flood 2014. PK-PIU PID-4944-CW-RFB / Restoration of Lakhi Flood Bund Component 1: Restoring Flood and Protection of Defense Flood Protection Infrastructure and Single Stage - One IDA / 56860 Post Request for Bids Open - National 3,513,000.00 2,798,493.08 Signed 2016-12-26 2016-11-23 2016-12-27 2017-01-26 2016-12-30 2017-02-25 2017-04-12 2017-04-01 2017-05-12 2017-09-28 Bund along with its River Training Upgrading Flood Management Envelope Structures near Dab Kalan Town Systems Damaged during Flood 2014. PK-PIU PID-4945-CW-RFB / Component 1: Restoring Flood Strengthening Left Flood Protection Infrastructure and Single Stage - One IDA / 56860 Post Request for Bids Open - National 2,084,000.00 1,596,570.68 Signed 2016-12-26 2016-12-06 2016-12-27 2017-01-26 2017-01-13 2017-02-25 2017-04-12 2017-04-01 2017-05-12 2017-08-29 Embankment of Link No.III Upgrading Flood Management Envelope RD:142+100 to 227+820. Systems PK-PIU PID-6161-CW-RFQ / Installation of Glass and Component 3: Project Request for Single Stage - One IDA / 56860 Post Limited 5,300.00 5,153.47 Signed 2017-02-10 2017-02-08 2017-04-07 2017-03-07 2017-05-07 Aluminium Cabins and Vertical Management Quotations Envelope Window blinds in Office building PK-PIU PID-8839-CW-RFB / STRENGTHENING, RAISING AND PROVIDING GOOD EARTH Component 1: Restoring Flood COVER OVER EXTENSION Protection Infrastructure and Single Stage - One IDA / 56860 Post Request for Bids Open - National 4,856,000.00 4,281,704.69 Signed 2017-03-01 2017-02-24 2017-03-01 2017-03-08 2017-03-31 2017-03-31 2017-04-30 2017-08-21 2017-06-04 2017-09-11 2018-06-04 MINCHIN FLOOD BUND Upgrading Flood Management Envelope RD 380+000 TO RD 501+000 Systems AND RESTORATION OF ALLIED STRUCTURES PK-PIU AJK-25294-CW-RFB / Package-01/PDO Restoration of damaged Hydro- power Houses & Flood Protection Structures of PDO Component 1: Restoring Flood (containing three lots). Protection Infrastructure and Single Stage - One Under IDA / 56860 Post Request for Bids Open - National 2,242,790.00 0.00 2017-08-31 2017-09-05 2017-09-13 2017-10-17 2017-10-16 2017-11-01 2017-12-15 2017-11-22 2018-11-22 Lot-1 (3 sub-Projects of Districts Upgrading Flood Management Envelope Implementation Hattian & 1 of Mzd) Systems Lot-2 (2 sub-Projects of District Bagh) Lot-3 (2 sub-Projects of District Haveli) PK-PIU AJK-25302-CW-RFB / Package-02/PDO Restoration of damaged Hydro- power Houses & Flood Protection Structures of PDO Component 1: Restoring Flood (containing three lots). Protection Infrastructure and Single Stage - One Under IDA / 56860 Post Request for Bids Open - National 1,852,390.00 0.00 2017-09-15 2017-09-20 2017-09-13 2017-11-01 2017-12-01 2017-12-29 2018-12-29 Lot-1 (2 sub-Projects of Districts Upgrading Flood Management Envelope Implementation Neelum) Systems Lot-2 (3.0 MW Sharda HP in District Neelum) Lot-3 (3 sub-Projects of District Poonch) PK-PIU AJK-30058-CW-RFB / Restoration of Flood Protection Component 1: Restoring Flood Structures of Package-1 (PP&H) Protection Infrastructure and Single Stage - One Under at Bandi Bagh near Nisar Camp, IDA / 56860 Post Request for Bids Open - National 989,160.00 810,291.85 2017-10-06 2017-10-11 2017-11-08 2017-11-22 2017-11-10 2017-12-06 2017-12-14 2018-01-01 2018-12-31 Upgrading Flood Management Envelope Implementation Chehla Bandi at Right Bank Systems Neelum River , District Muzaffarabad GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 Component 1: Restoring Flood Protection Infrastructure and Upgrading Flood Management Systems Email dated January 20, 2016 / Component 4: Contingent Request for IDA / 56860 Prior Open - International N 17,000.00 65.05 Terminated 2016-01-25 NOL for Procurement of Furniture Emergency Response Quotations Component 3: Project Management Component 2: Managing Disasters and Climate Variability Component 1: Restoring Flood Protection Infrastructure and Upgrading Flood Management Systems Email dated June 2, 2016 / Component 4: Contingent Request for Procurement of Office Furniture IDA / 56860 Prior Open - International N 18,000.00 20,378.11 Completed 2016-06-09 2016-06-15 Emergency Response Quotations for PIU Component 3: Project Management Component 2: Managing Disasters and Climate Variability PK-PDMA PUNJAB-2497-GO- Component 2: Managing Request for Single Stage - One Pending RFQ / IT related Office IDA / 56860 Post Open - National 48,000.00 0.00 2016-10-15 2016-12-10 2017-06-08 Disasters and Climate Variability Quotations Envelope Implementation Equipment for DDMAs PK-PDMA PUNJAB-2499-GO- Component 2: Managing Request for Single Stage - One Under IDA / 56860 Post Open - National 40,000.00 23,736.21 2016-10-15 2016-12-10 2017-06-08 RFQ / Office Furniture for PIU Disasters and Climate Variability Quotations Envelope Implementation PK-PDMA PUNJAB-2495-GO- RFQ / 1. Fixtures and Furnishers for establishment of PIU Head Component 2: Managing Request for Single Stage - One Under IDA / 56860 Post Open - National 50,000.00 34,059.20 2016-10-14 2016-12-09 2017-06-07 Quarter Disasters and Climate Variability Quotations Envelope Implementation 2. Necessary equipment for PIU HQ PK-PDMA PUNJAB-2503-GO- Component 2: Managing Single Stage - Two Pending RFQ / Establishment of EOC at IDA / 56860 Post Request for Bids Open - National 115,000.00 0.00 2016-11-10 2016-11-15 2016-12-27 2017-03-11 2017-04-15 2017-10-12 Disasters and Climate Variability Envelope Implementation District Level PK-PDMA PUNJAB-2769-GO- CD / "Equipment for Component 2: Managing Single Stage - One Pending Establishment of Central IDA / 56860 Post Request for Bids Open - National 150,000.00 0.00 2016-11-14 2016-11-19 2016-12-31 2017-01-30 2017-03-06 2017-09-02 Disasters and Climate Variability Envelope Implementation Command and Control Center (CCC)" PK-PDMA PUNJAB-2770-GO- Component 2: Managing Single Stage - One Pending CD / Relief and Rescue IDA / 56860 Post Request for Bids Open - National 500,000.00 0.00 2016-11-17 2016-11-22 2016-12-22 2017-01-21 2017-02-25 2017-08-24 Disasters and Climate Variability Envelope Implementation Equipment for Priority Districts PK-PDMA PUNJAB-2493-GO- Component 2: Managing Request for Single Stage - One RFQ / Operational Vehicles (4 x IDA / 56860 Prior Open - National 160,000.00 0.00 Canceled 2016-10-14 2016-12-09 2017-06-07 Disasters and Climate Variability Quotations Envelope 4) = 04 PK-PIU AJK-3735-GO-RFQ / Component 3: Project Request for Single Stage - One IDA / 56860 Post Open - National 46,000.00 44,458.81 Completed 2016-12-03 2017-01-28 2016-06-16 2017-07-27 2016-06-28 Purchase of IT equipment for PIU Management Quotations Envelope PK-PIU AJK-3736-GO-RFQ / Component 3: Project Request for Single Stage - One Office Equipment (Electric) for IDA / 56860 Post Open - National 34,000.00 28,606.84 Completed 2016-12-03 2017-01-28 2016-06-27 2017-07-27 2016-07-11 Management Quotations Envelope PIU PK-PDMA PUNJAB-2765-GO- Component 2: Managing Single Stage - One CD / Mobile Communication IDA / 56860 Prior Request for Bids Open - International 200,000.00 0.00 Canceled 2016-11-17 2016-11-22 2017-01-03 2017-02-02 2017-03-09 2017-09-05 Disasters and Climate Variability Envelope Office PK-PDMA PUNJAB-3799-GO- Component 2: Managing Request for Single Stage - One Under RFQ / Operational Vehicles (4 x IDA / 56860 Post Open - National 160,000.00 0.00 2016-12-01 2016-12-05 2017-06-03 Disasters and Climate Variability Quotations Envelope Implementation 4) = 04 PK-PIU AJK-2394-GO-RFQ / Component 3: Project Request for Single Stage - One IDA / 56860 Prior Open - National 280,144.00 270,479.40 Signed 2016-12-19 2017-01-30 2017-02-27 2017-04-24 Office ( PIU) Vehicles (7) Management Quotations Envelope PK-PIU AJK-6694-GO-RFQ / Component 2: Managing Request for Single Stage - One Procurement & erection of IDA / 56860 Post Open - National 19,230.00 11,928.05 Completed 2017-03-23 2017-04-10 2017-04-25 2017-05-10 2017-05-25 2017-05-24 Disasters and Climate Variability Quotations Envelope Generator for PIU-DCRIP AJK PK-PIU AJK-6695-GO-RFQ / Component 3: Project Request for Single Stage - One Procurement of Photocopier IDA / 56860 Post Open - National 18,270.00 12,309.75 Completed 2017-03-24 2017-04-10 2017-04-18 2017-05-10 2017-05-18 2017-06-22 Management Quotations Envelope (Single Unit) for PIU-DCRIP AJK PK-PIU AJK-6696-GO-RFQ / Component 2: Managing Request for Single Stage - One Procurement of 3 Motorcycles for IDA / 56860 Post Open - National 3,847.00 3,317.91 Completed 2017-03-23 2017-04-10 2017-04-17 2017-05-10 2017-05-17 2017-06-08 Disasters and Climate Variability Quotations Envelope PIU-DCRIP AJK PK-PIU AJK-6697-GO-RFQ / Component 2: Managing Request for Single Stage - One Procurement & installation of CC IDA / 56860 Post Open - National 2,695.00 1,982.89 Completed 2017-03-23 2017-04-10 2017-04-20 2017-05-10 2017-05-20 2017-06-09 Disasters and Climate Variability Quotations Envelope TV System for PIU-DCRIP AJK PK-PIU AJK-11473-GO-RFQ / Component 2: Managing Request for Single Stage - One Package-5 (Procurement of IT IDA / 56860 Post Open - National 31,327.00 54,540.28 Completed 2017-04-19 2017-06-14 2017-06-06 2017-07-14 2017-07-18 Disasters and Climate Variability Quotations Envelope Equipment for SDMA &DDMA) PK-PIU AJK-11482-GO-RFQ / Package-6 Procurement of Component 2: Managing Request for Single Stage - One Electrical Equipment (11Nos IDA / 56860 Post Open - National 19,231.00 14,870.99 Completed 2017-04-19 2017-05-24 2017-06-06 2017-06-23 2017-07-27 Disasters and Climate Variability Quotations Envelope Generators &UPS ) for SDMA & DDMA PK-PIU AJK-11522-GO-RFQ / Package-7 (Procurement of Component 2: Managing Request for Single Stage - One IDA / 56860 Post Open - National 12,260.00 32,380.41 Completed 2017-04-19 2017-05-24 2017-06-06 2017-06-23 2017-08-01 Office Furniture for SDMA & Disasters and Climate Variability Quotations Envelope DDMA) PK-PIU AJK-12515-GO-RFB / Package-4 (Procurement of Component 2: Managing Single Stage - One Under IDA / 56860 Post Request for Bids Open - National 141,635.00 0.00 2017-04-12 2017-04-14 2017-05-13 2017-05-26 2017-06-02 2017-06-12 2017-09-10 Communication Equipment for Disasters and Climate Variability Envelope Implementation SDMA & DDMA) Page 2 PK-PIU AJK-11471-GO-RFQ / Package-1 (Procurement of (6 Component 2: Managing Request for Single Stage - One IDA / 56860 Post Open - National 230,769.00 225,153.84 Signed 2017-04-30 2017-05-13 2017-06-11 2017-06-09 2017-10-09 Nos) 4x4 Operational Vehicles Disasters and Climate Variability Quotations Envelope for SDMA ) PK-PDMA PUNJAB-14309-GO- Component 2: Managing Request for Single Stage - One Pending RFQ / Critical Equipment IDA / 56860 Post Open - National 40,000.00 0.00 2017-05-08 2017-07-03 2017-12-30 Disasters and Climate Variability Quotations Envelope Implementation (Furniture) for Districts Phase ii PK-PDMA PUNJAB-16391-GO- RFB / Critical Equipment (IT Equipment(Android Mobile Component 2: Managing Single Stage - One Pending IDA / 56860 Post Request for Bids Open - National 180,000.00 0.00 2017-05-29 2017-06-03 2017-07-15 2017-08-14 2017-09-18 2018-03-17 Devices,Laptops,Workstations,Pr Disasters and Climate Variability Envelope Implementation inters,Scanners & UPS) For Phase ii PK-PDMA PUNJAB-16394-GO- RFQ / Video Conferencing Component 2: Managing Request for Single Stage - One Pending IDA / 56860 Post Open - National 30,000.00 0.00 2017-06-03 2017-07-29 2018-01-25 Equipment Installation at PIU Disasters and Climate Variability Quotations Envelope Implementation Office PK-PDMA PUNJAB-16671-GO- RFQ / Critical Equipment For Component 2: Managing Request for Single Stage - One Pending Districts (20*UPS(3KVA)/Power IDA / 56860 Post Open - National 40,000.00 0.00 2017-06-06 2017-08-01 2018-01-28 Disasters and Climate Variability Quotations Envelope Implementation Backup) Proposed by Capacity Building Firm PK-PDMA PUNJAB-16673-GO- RFQ / Critical Equipment for HO Component 2: Managing Request for Single Stage - One Pending (6*UPS (10KVA) & 220 KVA IDA / 56860 Post Open - National 100,000.00 0.00 2017-06-06 2017-08-01 2018-01-28 Disasters and Climate Variability Quotations Envelope Implementation Gen-set )proposed by Capacity Building Firm PK-PIU PID-17004-GO-RFQ / Component 3: Project Request for Single Stage - One Under Procurement of Office IDA / 56860 Post Open - National 38,425.00 0.00 2017-07-12 2017-07-26 2017-09-13 2018-03-12 Management Quotations Envelope Implementation Equipments Component 1: Restoring Flood PK-PIU PID-17513-GO-RFQ / Protection Infrastructure and Single Stage - One Under Procurement of Instruments for IDA / 56860 Post Request for Bids Open - National 540,000.00 0.00 2017-07-07 2017-07-27 2017-07-12 2017-07-27 2017-08-23 2017-09-12 2017-09-22 2017-10-13 2017-10-27 2018-04-25 Upgrading Flood Management Envelope Implementation Hydraulic structure Inspections Systems PK-PIU AJK-25305-GO-RFQ / Establishment of Video Conferencing System along with Component 3: Project Request for Single Stage - One Under IDA / 56860 Post Open - National 46,100.00 13,051.73 2017-09-26 2017-12-05 2018-02-23 Installation and Configuration and Management Quotations Envelope Implementation allied hardware & Software for PIU Office PK-PIU AJK-25309-GO-RFQ / Procurement & Installation of Component 3: Project Request for Single Stage - One Telephone Exchange with main IDA / 56860 Post Open - National 3,350.00 2,532.14 Signed 2017-09-20 2017-11-06 2017-10-02 2018-01-05 Management Quotations Envelope console and (14) Telephone Sets for PIU Office PK-PIU AJK-12514-GO-RFB / Package-3 (Procurement of Component 2: Managing Single Stage - One (5Nos) Rescue & Life Care IDA / 56860 Post Request for Bids Open - National 312,500.00 0.00 Canceled 2017-04-12 2017-04-14 2017-05-13 2017-05-26 2017-06-02 2017-06-12 2017-10-10 Disasters and Climate Variability Envelope Ambulances for SDMA,1122 & DDMA) PK-PIU AJK-12513-GO-RFB / Package-2 (Procurement of Rescue Response Vehicles Component 2: Managing Single Stage - One IDA / 56860 Post Request for Bids Open - National 894,231.00 0.00 Canceled 2017-04-12 2017-04-14 2017-05-13 2017-05-26 2017-06-02 2017-06-12 2017-10-10 (3Nos Road Truck Cranes & Disasters and Climate Variability Envelope 3Nos Fire Tenders) For SDMA , DDMA & Rescue 1122 ) PK-PDMA PUNJAB-25535-GO- Component 2: Managing Request for Single Stage - One Pending RFQ / Additional Operational IDA / 56860 Post Open - National 98,000.00 0.00 2017-08-22 2017-10-03 2018-04-01 Disasters and Climate Variability Quotations Envelope Implementation Vehicles (4 x 4) = 02 PK-PIU AJK-37588-GO-RFB / Supply and conversion of (3) Component 1: Restoring Flood brand new (4x2) Truck chassis Protection Infrastructure and (RHD) with manual transmission Upgrading Flood Management Single Stage - One Pending diesel engine 4 stroke, 6 cylinder IDA / 56860 Post Request for Bids Open - National 375,000.00 0.00 2017-11-30 2017-12-05 2018-01-16 2018-01-30 2018-02-20 2018-06-20 Systems Envelope Implementation vertical in line, water cooled, Component 2: Managing Direct injection, power steering, Disasters and Climate Variability engine displacement (7500-8300) cc into Fire Fighting Vehicle. PK-PIU AJK-37611-GO-RFB / Supply and conversion of (05 Component 1: Restoring Flood Nos) Brand New Wagon type Protection Infrastructure and Van having wide body (Supper Upgrading Flood Management Single Stage - One Pending long) High Roof with Dual Air IDA / 56860 Post Request for Bids Open - National 480,700.00 0.00 2017-11-30 2017-12-05 2018-01-16 2018-01-30 2018-02-20 2018-06-20 Systems Envelope Implementation Conditioner Model 2018 into Component 2: Managing Emergency Service Rescue Disasters and Climate Variability Ambulance for SDMA, DDMA & Rescue 1122 (Package-3) PK-PIU AJK-37616-GO-RFB / Component 1: Restoring Flood Supply of (02 Nos) 35-40 Tons Protection Infrastructure and versatile truck mounted fully Upgrading Flood Management Single Stage - One Pending IDA / 56860 Post Request for Bids Open - National 962,000.00 0.00 2017-11-30 2017-12-05 2018-01-16 2018-01-30 2018-02-20 2018-06-20 foreign assembled Track crane Systems Envelope Implementation for SDMA & Rescue 1122 Component 2: Managing (Package-2b) Disasters and Climate Variability PK-PIU AJK-37628-GO-RFB / Procurement of High Resolution Satellite Imageries at 0.31m Component 1: Restoring Flood Resolution (4 Bands) for 2500 Protection Infrastructure and Sq.Km and Procurement & Upgrading Flood Management Single Stage - One Pending IDA / 56860 Post Request for Bids Open - National 130,500.00 0.00 2017-12-05 2017-12-08 2018-01-19 2018-02-02 2018-03-02 2018-05-31 Upgradation of ERDAS Systems Envelope Implementation IMAGINE, ArcGIS Basic to Component 2: Managing Enterprise, ESRI City Engine Disasters and Climate Variability Licenses and Firewall Software for LUP, P&DD Page 3 PK-PIU AJK-37660-GO-RFB / Procurement of Heavy-duty Component 1: Restoring Flood Workstation for GIS modelling Protection Infrastructure and and DTM generation/processing, Upgrading Flood Management Single Stage - One Pending Large Format Scanner (62 Inch), IDA / 56860 Post Request for Bids Open - National 111,250.00 0.00 2017-12-05 2017-12-10 2018-01-21 2018-02-04 2018-02-28 2018-05-29 Systems Envelope Implementation Laptop Core i7, GNSS System Component 2: Managing (Base + Rover) for Topographical Disasters and Climate Variability surveying and Soil testing equipment for LUP P&DD PK-PDMA PUNJAB-39964-GO- RFB / IT Equipment (Integration of Early Warning System with DEOCs at District Level - Turnkey Solution, Workstation Component 2: Managing Single Stage - One Pending IDA / 56860 Post Request for Bids Open - National 1,500,000.00 0.00 2017-12-19 2017-12-24 2018-02-04 2018-03-06 2018-04-10 2018-10-07 with UPS, Printers, Scanners, Disasters and Climate Variability Envelope Implementation Photocopiers, Fax Machine, Telephone Sets, 02 Ton Cabinet ACs, bandwidth, Biometric Dashboard, Digital Cameras) PK-PDMA PUNJAB-3855-GO- Component 2: Managing Single Stage - One RFB / Mobile Communication IDA / 56860 Post Request for Bids Open - International 200,000.00 0.00 Canceled 2016-11-30 2016-12-05 2017-01-16 2017-02-15 2017-03-22 2017-09-18 Disasters and Climate Variability Envelope Office NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PDMA PUNJAB-16392-NC- RFQ / Early Warning Notifications through mobile Component 2: Managing Request for Single Stage - One Pending IDA / 56860 Post Open - National 20,000.00 0.00 2017-06-03 2017-07-29 2018-01-25 Short Messaging Service Disasters and Climate Variability Quotations Envelope Implementation (Number of people at risk receive alerts) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Restoring Flood Protection Infrastructure and SDMA Capacity Assessment / Upgrading Flood Management Hiring of consultant firm to Systems Consultant undertake capacity assessment Component 4: Contingent IDA / 56860 Prior Qualification Open - International N 160,000.00 137,354.01 Completed 2016-09-02 2016-07-20 2017-05-22 of State Disaster Management Emergency Response Selection Authority (SDMA) and develop a Component 3: Project capacity enhancement plan. Management Component 2: Managing Disasters and Climate Variability PK-PIU AJK-2396-CS-QCBS / Project proposal review, Component 2: Managing designing, planning, cost Disasters and Climate Variability Quality And Cost- estimation, feasibility studies, IDA / 56860 Prior Open - International 1,500,000.00 1,380,706.62 Signed 2016-10-09 2016-10-12 2016-10-18 2016-10-21 2016-10-24 2016-10-30 2016-12-29 2016-11-05 2016-12-30 2019-09-30 Component 3: Project Based Selection preparation of PC-1s, tender Management documents, resident supervision etc Component 2: Managing PK-PIU AJK-2397-CS-CQS / Consultant Disasters and Climate Variability Baseline creation and third party IDA / 56860 Post Qualification Open - National 290,000.00 282,252.86 Signed 2016-10-10 2016-10-13 2016-10-19 2016-10-22 2016-06-28 2016-10-28 2016-07-22 2019-09-30 Component 3: Project Monitoring/Validation. Selection Management PK-PDMA PUNJAB-2515-CS- Consultant QCBS / Hiring of Firm for Component 2: Managing Under IDA / 56860 Post Qualification Open - National 100,000.00 0.00 2016-10-24 2016-12-15 2016-11-14 2016-12-28 2017-01-27 2017-03-03 2017-08-30 Development and Implementation Disasters and Climate Variability Implementation Selection of CBDRM Program PK-PIU PID-3480-CS-QCBS / Component 1: Restoring Flood Project Management and Protection Infrastructure and Quality And Cost- Under IDA / 56860 Prior Open - International 2,870,000.00 2,027,371.50 2016-11-17 2016-11-18 2016-11-20 2016-11-25 2016-11-25 2016-12-25 2016-12-28 2017-01-29 2017-02-03 2017-03-05 2017-03-08 2018-03-05 Implementation Consultants Upgrading Flood Management Based Selection Implementation (PMIC) Systems PK-PDMA PUNJAB-2767-CS- CQS / Hiring of Firm for Consultant Organizational Capacity Component 2: Managing IDA / 56860 Post Qualification Open - National 80,000.00 0.00 Canceled 2016-10-31 2016-11-21 2017-01-04 2017-02-03 2017-03-10 2017-09-06 Assessment and Capacity Disasters and Climate Variability Selection Enhancement Plan at Provincial and District Level PK-PIU AJK-2399-CS-CQS / Consultant Component 2: Managing Development of Emergency IDA / 56860 Post Qualification Open - National 250,000.00 233,538.01 Completed 2016-10-16 2016-05-12 2016-10-19 2016-10-25 2016-10-28 2016-06-28 2016-11-21 2016-07-20 2017-07-19 2017-05-31 Disasters and Climate Variability Logistic Plan for SDMA Selection PK-PIU AJK-2400-CS-CQS / Consultant Development of Disaster Risk Component 2: Managing IDA / 56860 Post Qualification Open - National 280,000.00 276,309.34 Completed 2016-10-16 2016-05-12 2016-10-19 2016-10-25 2016-10-28 2016-06-28 2016-11-03 2016-07-22 2017-08-30 2017-06-02 Management Plans of State and Disasters and Climate Variability Selection 10 Districts PK-PIU AJK-2402-CS-CQS / Mapping of Major Nullahs and Consultant Tributaries in AJK for Proposing Component 2: Managing IDA / 56860 Post Qualification Open - National 295,000.00 291,872.43 Completed 2016-10-16 2016-05-10 2016-10-19 2016-10-25 2016-10-28 2016-06-28 2016-11-21 2016-07-20 2017-07-19 2017-06-16 Gauging Stations for Flood Early Disasters and Climate Variability Selection Warning and Mitigation Measures PK-PDMA PUNJAB-3509-CS- CQS / Hiring of Firm for Consultant Organizational Capacity Component 2: Managing IDA / 56860 Prior Qualification Open - National 150,000.00 0.00 Canceled 2016-11-17 2016-11-17 2016-12-02 2016-12-24 2016-12-27 2017-01-06 2017-07-05 Assessment and Capacity Disasters and Climate Variability Selection Enhancement Plan at Provincial and District Level Page 4 PK-PDMA PUNJAB-2511-CS- Consultant QCBS / Hiring of Firm for Component 2: Managing IDA / 56860 Prior Qualification Open - National 150,000.00 0.00 Canceled 2016-10-23 2016-11-13 2016-12-27 2017-01-26 2017-03-02 2017-08-29 Provincial Disaster Management Disasters and Climate Variability Selection Plan and SOPs PK-PDMA PUNJAB-3807-CS- CQS / Hiring of Firm for Consultant Organizational Capacity Component 2: Managing Under IDA / 56860 Post Qualification Open - National 150,000.00 0.00 2016-11-30 2016-12-15 2016-12-15 2017-01-12 2017-01-19 2017-02-16 2017-08-15 Assessment and Capacity Disasters and Climate Variability Implementation Selection Enhancement Plan at Provincial and District Level PK-PDMA PUNJAB-3856-CS- Consultant CQS / Hiring of Firm for Component 2: Managing Under IDA / 56860 Post Qualification Open - National 150,000.00 0.00 2016-11-30 2016-12-15 2016-12-21 2017-02-03 2017-03-05 2017-04-09 2017-10-06 Provincial Disaster Management Disasters and Climate Variability Implementation Selection Plan and SOPs PK-PIU AJK-2398-CS-QCBS / Detailed Feasibility Study & Component 2: Managing Quality And Cost- Designing Flood Protection IDA / 56860 Post Open - International 769,231.00 519,988.54 Signed 2016-10-15 2016-10-18 2016-10-24 2016-10-27 2016-10-30 2016-12-22 2016-12-04 2017-03-10 2017-01-08 2017-03-17 2017-07-07 Disasters and Climate Variability Based Selection Works for Mandi Kotli Vulnerable Areas. PK-PIU AJK-2404-CS-QCBS / Climate Impact , Soil erosion Impacts and landslides Component 2: Managing Quality And Cost- Assessment along with the IDA / 56860 Post Open - International 524,039.00 0.00 Canceled 2016-12-30 2017-01-20 2017-03-05 2017-04-02 2017-05-02 2017-06-06 2017-07-11 2018-07-11 Disasters and Climate Variability Based Selection Recpmendation,Project Paper and Policy Documents of AJK Climate Resilience Diagnostic PK-PIU AJK-5915-CS-QCBS / Soil investigation, Geo-hazard, Component 2: Managing Quality And Cost- Under landslide susceptibility and IDA / 56860 Post Open - National 524,039.00 0.00 2017-02-15 2017-09-25 2017-05-06 2017-09-27 2017-06-19 2017-07-17 2017-08-16 2017-09-20 2017-10-25 2018-10-25 Disasters and Climate Variability Based Selection Implementation Climate Change Resilience Studies in AJ&K PK-PIU PID-17510-CS-QBS / Component 1: Restoring Flood Development of Decision Support Protection Infrastructure and Quality And Cost- Under IDA / 56860 Prior Open - International 4,400,000.00 0.00 2017-07-07 2017-07-18 2017-07-28 2017-09-06 2017-09-10 2017-10-08 2017-11-07 2017-12-12 2018-01-16 2019-06-25 System for Flood Management in Upgrading Flood Management Based Selection Implementation western Rivers of Punjab Systems PK-PIU AJK-26781-CS-CQS / Landslide Stabilization to Consultant Component 2: Managing Under Safeguard Civil Population and IDA / 56860 Post Qualification Open - National 288,000.00 0.00 2017-09-26 2017-09-07 2017-10-03 2017-09-13 2017-12-01 2017-12-15 2018-01-12 2018-09-09 Disasters and Climate Variability Implementation Infrastructure of Muzaffarabad Selection City - AJ&K INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Restoring Flood Protection Infrastructure and Upgrading Flood Management Systems Component 4: Contingent 3/16/2016 / Interim PMIC IDA / 56860 Prior Direct Selection Direct N 400,000.00 384,409.88 Signed 2016-05-03 Emergency Response Component 3: Project Management Component 2: Managing Disasters and Climate Variability PK-PIU AJK-2380-CS-INDV / Component 3: Project Individual Consultant IDA / 56860 Prior Open 80,769.00 68,718.67 Signed 2016-10-10 2016-10-19 2016-10-22 2016-12-27 2016-10-28 2015-12-01 2019-07-05 Financial Management Expert Management Selection PK-PIU AJK-2381-CS-INDV / Component 3: Project Individual Consultant IDA / 56860 Prior Open 80,769.00 17,681.22 Terminated 2016-10-10 2016-10-19 2016-10-22 2016-12-27 2016-10-28 2016-03-18 2019-07-05 Procurement Expert Management Selection PK-PIU AJK-2383-CS-INDV / Component 3: Project Individual Consultant IDA / 56860 Prior Open 80,769.00 37,545.53 Terminated 2016-10-10 2016-10-19 2016-10-22 2016-12-27 2016-10-28 2015-12-01 2019-07-05 Environmental Expert Management Selection PK-PIU AJK-2385-CS-INDV / Component 3: Project Individual Consultant IDA / 56860 Post Open 80,769.00 59,219.61 Signed 2016-11-01 2016-12-20 2017-01-10 2017-04-10 2017-02-14 2017-05-11 2019-09-30 Project Manager DCRIP Management Selection PK-PIU AJK-2388-CS-INDV / IT Component 3: Project Individual Consultant IDA / 56860 Post Open 34,615.00 29,712.32 Signed 2016-11-01 2016-12-20 2017-01-10 2017-02-14 2016-06-03 2019-09-30 Expert Management Selection PK-PIU AJK-2392-CS-INDV / Component 3: Project Individual Consultant IDA / 56860 Post Open 2,885.00 333.95 Completed 2016-10-10 2016-10-18 2016-10-21 2016-10-27 2016-09-01 2017-04-25 2017-02-28 AutoCAD / Drafting Technician Management Selection PK-PDMA PUNJAB-2478-CS- Component 2: Managing Individual Consultant INDV / Financial Management IDA / 56860 Prior Open 36,000.00 27,479.61 Terminated 2016-10-10 2016-11-28 2016-08-27 2016-12-19 2017-01-31 2017-01-23 2016-09-17 2017-07-22 Disasters and Climate Variability Selection Specialist PK-PDMA PUNJAB-2481-CS- Component 2: Managing Individual Consultant IDA / 56860 Post Open 48,000.00 45,823.39 Signed 2016-10-10 2016-11-28 2017-01-07 2016-12-19 2017-01-16 2017-01-23 2017-01-26 2017-07-22 INDV / DRM Specialist Disasters and Climate Variability Selection PK-PDMA PUNJAB-2488-CS- Component 2: Managing Individual Consultant Pending INDV / Monitoring and Evaluation IDA / 56860 Post Open 36,000.00 0.00 2016-10-10 2016-11-28 2016-12-19 2017-01-23 2017-07-22 Disasters and Climate Variability Selection Implementation Specialist PK-PDMA PUNJAB-2491-CS- Component 2: Managing Individual Consultant IDA / 56860 Post Open 36,000.00 21,760.91 Terminated 2016-10-10 2016-11-28 2016-07-30 2016-12-19 2016-08-02 2017-01-23 2016-08-09 2017-07-22 INDV / Communications Expert Disasters and Climate Variability Selection PK-PDMA PUNJAB-2496-CS- Component 2: Managing Individual Consultant Pending INDV / Mainstreaming DRR IDA / 56860 Post Open 54,000.00 0.00 2016-10-10 2016-11-28 2016-12-19 2017-01-23 2017-07-22 Disasters and Climate Variability Selection Implementation Expert PK-PDMA PUNJAB-2506-CS- Component 2: Managing Individual Consultant Pending INDV / IT Experts for Districts (5 IDA / 56860 Post Open 150,000.00 0.00 2016-10-10 2016-11-28 2016-12-19 2017-01-23 2017-07-22 Disasters and Climate Variability Selection Implementation priority districts) and PIU x 12 Page 5 PK-PDMA PUNJAB-2508-CS- Component 2: Managing Individual Consultant Under INDV / Emergency Operations IDA / 56860 Post Open 43,000.00 0.00 2016-10-10 2016-11-02 2016-11-28 2017-01-17 2016-12-19 2017-01-23 2017-07-22 Disasters and Climate Variability Selection Implementation Coordinator PK-PDMA PUNJAB-2510-CS- Component 2: Managing Individual Consultant Pending IDA / 56860 Post Open 30,000.00 0.00 2016-10-10 2016-11-28 2016-12-19 2017-01-23 2017-07-22 INDV / Public Finance Specialist Disasters and Climate Variability Selection Implementation PK-PIU PID-2565-CS-INDV / Component 3: Project Individual Consultant Under Procurement & Contract IDA / 56860 Prior Limited 114,900.00 0.00 2016-10-14 2016-10-21 2016-10-15 2016-10-07 2016-11-05 2016-12-10 2017-06-08 Management Selection Implementation Specialist PK-PIU PID-2567-CS-INDV / Component 3: Project Individual Consultant Under IDA / 56860 Prior Limited 114,900.00 0.00 2016-10-14 2016-10-21 2016-10-15 2016-10-07 2016-11-05 2016-12-10 2017-06-08 Financial Management Specialist Management Selection Implementation PK-PIU PID-2568-CS-INDV / Component 3: Project Individual Consultant Under IDA / 56860 Prior Limited 114,900.00 18,607.76 2016-10-14 2016-10-21 2016-10-15 2016-09-28 2016-11-05 2016-11-24 2016-12-10 2016-12-01 2017-06-08 Social Safeguard Specialist Management Selection Implementation PK-PDMA PUNJAB-2475-CS- Component 2: Managing Individual Consultant Under INDV / Project Director for 3 IDA / 56860 Post Open 90,000.00 0.00 2016-10-09 2016-11-27 2016-12-18 2017-01-22 2017-07-21 Disasters and Climate Variability Selection Implementation years PK-PDMA PUNJAB-2494-CS- INDV / 1. District Disaster Risk Component 2: Managing Individual Consultant IDA / 56860 Post Open 51,600.00 51,551.32 Signed 2016-10-08 2016-11-26 2016-07-30 2016-12-17 2016-09-28 2017-01-21 2016-09-28 2017-07-20 Management Coordinator Disasters and Climate Variability Selection (DDMC) , Sialkot PK-PDMA PUNJAB-3132-CS- INDV / District Disaster Risk Component 2: Managing Individual Consultant IDA / 56860 Post Open 36,000.00 51,551.32 Signed 2016-11-14 2017-01-02 2016-07-30 2017-01-23 2016-08-09 2017-02-27 2016-08-09 2017-08-26 Management Coordinator Disasters and Climate Variability Selection Hafizabad PK-PDMA PUNJAB-3133-CS- Component 2: Managing Individual Consultant INDV / District Disaster Risk IDA / 56860 Post Open 258,000.00 51,551.32 Signed 2016-11-14 2017-01-02 2016-07-30 2017-01-23 2016-08-01 2017-02-27 2016-08-09 2017-08-26 Disasters and Climate Variability Selection Management Coordinator Jhang PK-PDMA PUNJAB-3134-CS- Component 2: Managing Individual Consultant INDV / District Disaster Risk IDA / 56860 Post Open 258,000.00 51,551.32 Signed 2016-11-14 2015-12-26 2017-01-02 2016-07-30 2017-01-23 2016-08-01 2017-02-27 2016-08-09 2017-08-26 Disasters and Climate Variability Selection Management Coordinator Layyah PK-PDMA PUNJAB-3135-CS- INDV / District Disaster Risk Component 2: Managing Individual Consultant IDA / 56860 Post Open 258,000.00 51,551.32 Signed 2016-11-14 2017-01-02 2016-07-30 2017-01-23 2016-08-09 2017-02-27 2016-08-09 2017-08-26 Management Coordinator Disasters and Climate Variability Selection Muzaffargarh PK-PDMA PUNJAB-3277-CS- INDV / Insurance Policy expert Component 2: Managing Individual Consultant Under IDA / 56860 Post Open 21,000.00 0.00 2016-11-13 2016-11-17 2017-01-01 2017-01-22 2017-02-26 2017-08-25 for Disaster Risk Financing Disasters and Climate Variability Selection Implementation initiative PK-PDMA PUNJAB-3278-CS- Component 2: Managing Individual Consultant Under INDV / Financial Consultant for IDA / 56860 Post Open 21,000.00 0.00 2016-11-14 2016-11-17 2017-01-02 2017-01-23 2017-02-27 2017-08-26 Disasters and Climate Variability Selection Implementation Disaster Risk Financing initiative PK-PDMA PUNJAB-2504-CS- Component 2: Managing Individual Consultant IDA / 56860 Prior Open 45,000.00 0.00 Canceled 2016-10-10 2016-11-28 2016-08-27 2016-12-19 2017-01-23 2017-07-22 INDV / Logistics Expert Disasters and Climate Variability Selection PK-PDMA PUNJAB-2480-CS- Component 2: Managing Individual Consultant IDA / 56860 Prior Open 36,000.00 0.00 Canceled 2016-10-10 2016-11-28 2016-12-19 2017-01-23 2017-07-22 INDV / Procurement Specialist Disasters and Climate Variability Selection PK-PDMA PUNJAB-3858-CS- Component 2: Managing Individual Consultant Pending IDA / 56860 Post Open 45,000.00 0.00 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2017-09-11 INDV / Logistics Expert Disasters and Climate Variability Selection Implementation PK-PDMA PUNJAB-3861-CS- Component 2: Managing Individual Consultant IDA / 56860 Post Open 36,000.00 54,813.09 Terminated 2016-11-30 2017-01-18 2016-12-05 2017-02-08 2016-12-08 2017-03-15 2016-12-16 2017-09-11 INDV / Procurement Specialist Disasters and Climate Variability Selection PK-PIU AJK-5913-CS-INDV / Component 3: Project Individual Consultant IDA / 56860 Prior Open 69,230.00 61,065.79 Signed 2017-01-26 2017-02-01 2017-03-10 2017-03-24 2017-04-07 2017-04-28 2017-04-10 2019-11-30 Procurement Expert Management Selection PK-PIU PID-5959-CS-INDV / Component 3: Project Individual Consultant IDA / 56860 Post Limited 114,900.00 2,047.51 Signed 2017-01-28 2016-10-21 2017-01-28 2017-01-17 2017-01-31 2017-01-19 2017-02-28 2017-01-31 2017-08-27 Environmental Specialist Management Selection PK-PIU PID-5960-CS-INDV / Component 3: Project Individual Consultant Under Monitoring and Evaluation IDA / 56860 Post Limited 114,900.00 0.00 2017-01-28 2016-10-21 2017-01-28 2017-01-31 2017-02-28 2017-08-27 Management Selection Implementation Specialist PK-PIU PID-2569-CS-INDV / Component 3: Project Individual Consultant IDA / 56860 Prior Limited 114,900.00 0.00 Canceled 2016-10-14 2016-10-21 2016-10-15 2017-01-17 2016-11-05 2016-12-10 2017-06-08 Environmental Specialiast Management Selection PK-PIU PID-2570-CS-INDV / Component 3: Project Individual Consultant Monitoring and Evaluation IDA / 56860 Prior Limited 114,900.00 0.00 Canceled 2016-10-14 2016-10-21 2016-10-15 2016-11-05 2016-12-10 2017-06-08 Management Selection Specialist PK-PDMA PUNJAB-5988-CS- Component 2: Managing Individual Consultant Under INDV / Financial Management IDA / 56860 Prior Open 36,000.00 27,363.43 2017-01-30 2017-02-02 2017-01-25 2017-02-03 2017-02-06 2017-02-05 2017-08-04 Disasters and Climate Variability Selection Implementation Specialist PK-PDMA PUNJAB-6384-CS- Component 2: Managing Individual Consultant Pending IDA / 56860 Post Open 36,000.00 0.00 2017-02-07 2017-02-18 2017-02-20 2017-02-22 2017-08-21 INDV / Communications Expert Disasters and Climate Variability Selection Implementation PK-PIU AJK-11655-CS-INDV / Component 2: Managing Individual Consultant IDA / 56860 Post Open 103,125.00 88,753.16 Signed 2017-04-05 2017-04-05 2017-04-12 2017-04-12 2017-04-30 2017-05-02 2019-11-30 Coordinator (Based in P&DD) Disasters and Climate Variability Selection PK-PIU AJK-11688-CS-INDV / Component 3: Project Individual Consultant Social Safeguard Expert PIU- IDA / 56860 Post Open 66,635.00 60,174.77 Signed 2017-04-05 2017-04-10 2017-04-15 2017-03-28 2017-04-24 2017-04-24 2019-11-30 Management Selection AJ&K PK-PIU AJK-11724-CS-INDV / Component 2: Managing Individual Consultant IDA / 56860 Post Open 12,115.00 11,450.38 Completed 2017-04-05 2017-04-05 2017-04-10 2017-03-28 2017-04-17 2017-04-17 2017-10-16 2017-10-17 Infrastructure Specialist Disasters and Climate Variability Selection PK-PIU AJK-11728-CS-INDV / Component 3: Project Individual Consultant IDA / 56860 Post Open 66,635.00 61,051.20 Signed 2017-04-05 2017-04-05 2017-04-05 2017-04-07 2017-04-06 2017-04-07 2019-11-30 Monitoring and Evaluation Expert Management Selection Page 6 PK-PIU AJK-11730-CS-INDV / Component 2: Managing Individual Consultant IDA / 56860 Post Open 66,635.00 -38,955.81 Terminated 2017-04-05 2017-04-05 2017-04-10 2017-03-29 2017-04-17 2017-04-18 2019-11-30 GIS Specialist Disasters and Climate Variability Selection PK-PIU AJK-2386-CS-INDV / Component 2: Managing Individual Consultant IDA / 56860 Prior Open 103,846.00 0.00 Canceled 2016-11-01 2016-12-20 2017-01-10 2017-02-14 2019-09-30 Coordinator (Based in P&DD) Disasters and Climate Variability Selection PK-PIU AJK-2384-CS-INDV / Component 3: Project Individual Consultant IDA / 56860 Prior Open 80,769.00 0.00 Canceled 2016-11-01 2016-12-20 2017-01-10 2017-02-14 2019-09-30 Social Safeguard Expert Management Selection PK-PIU AJK-2391-CS-INDV / Component 2: Managing Individual Consultant IDA / 56860 Prior Open 11,538.00 0.00 Canceled 2016-11-01 2016-12-20 2017-01-10 2017-02-14 2017-08-13 Infrastructure Specialist Disasters and Climate Variability Selection PK-PIU AJK-2387-CS-INDV / Component 3: Project Individual Consultant IDA / 56860 Prior Open 80,769.00 0.00 Canceled 2016-11-01 2016-12-20 2017-01-10 2017-02-14 2019-09-30 Monitoring and Evaluation Expert Management Selection PK-PIU AJK-2389-CS-INDV / Component 2: Managing Individual Consultant IDA / 56860 Prior Open 11,538.00 0.00 Canceled 2016-11-01 2016-12-20 2017-01-10 2017-02-14 2018-02-14 GIS Specialist Disasters and Climate Variability Selection PK-PDMA PUNJAB-12871-CS- INDV / District Disaster Component 2: Managing Individual Consultant Pending IDA / 56860 Post Open 36,000.00 0.00 2017-04-14 2017-06-02 2017-06-23 2017-07-28 2018-01-24 Management Coordinator Multan Disasters and Climate Variability Selection Implementation (Detail TORs in comments) PK-PDMA PUNJAB-12858-CS- INDV / District Disaster Component 2: Managing Individual Consultant Pending Management Coordinator IDA / 56860 Post Open 36,000.00 0.00 2017-04-14 2017-06-02 2017-06-23 2017-07-28 2018-01-24 Disasters and Climate Variability Selection Implementation Rajanpur (Detail TORs in comments) PK-PDMA PUNJAB-12861-CS- INDV / District Disaster Component 2: Managing Individual Consultant Pending Management Coordinator Rahim IDA / 56860 Post Open 36,000.00 0.00 2017-04-14 2017-06-02 2017-06-23 2017-07-28 2018-01-24 Disasters and Climate Variability Selection Implementation Yar Khan (Detail TORs in comments) PK-PDMA PUNJAB-12864-CS- INDV / District Disaster Component 2: Managing Individual Consultant Pending Management Coordinator Dera IDA / 56860 Post Open 36,000.00 0.00 2017-04-14 2017-06-02 2017-06-23 2017-07-28 2018-01-24 Disasters and Climate Variability Selection Implementation Ghazi Khan (Detail TORs in comments) PK-PDMA PUNJAB-12868-CS- INDV / District Disaster Component 2: Managing Individual Consultant Pending Management Coordinator IDA / 56860 Post Open 36,000.00 0.00 2017-04-14 2017-06-02 2017-06-23 2017-07-28 2018-01-24 Disasters and Climate Variability Selection Implementation Mianwali (Detail TORs in comments) PK-PDMA PUNJAB-12870-CS- INDV / District Disaster Component 2: Managing Individual Consultant Pending Management Coordinator IDA / 56860 Post Open 36,000.00 0.00 2017-04-14 2017-06-02 2017-06-23 2017-07-28 2018-01-24 Disasters and Climate Variability Selection Implementation Khushab (Detail TORs in comments) PK-PDMA PUNJAB-12866-CS- INDV / District Disaster Component 2: Managing Individual Consultant Pending Management Coordinator IDA / 56860 Post Open 36,000.00 0.00 2017-04-14 2017-06-02 2017-06-23 2017-07-28 2018-01-24 Disasters and Climate Variability Selection Implementation Bhakkar (Detail TORs in comments) PK-PIU AJK-21250-CS-INDV / Component 2: Managing Individual Consultant Environmental Expert PIU- IDA / 56860 Post Open 56,000.00 51,267.44 Signed 2017-07-24 2017-08-08 2017-08-11 2017-09-07 2017-08-15 2017-09-21 2019-11-30 Disasters and Climate Variability Selection DCRIP PK-PDMA PUNJAB-26387-CS- INDV / International Consultant Component 2: Managing Individual Consultant Pending IDA / 56860 Post Open 48,400.00 0.00 2017-08-28 2017-09-04 2017-09-05 2017-09-07 2017-11-06 on Disaster Risk Financing Disasters and Climate Variability Selection Implementation Strategy Development PK-PDMA PUNJAB-27894-CS- Component 2: Managing Individual Consultant Pending IDA / 56860 Post Open 30,000.00 0.00 2017-09-08 2017-09-14 2017-09-16 2017-09-20 2018-03-19 INDV / Climate Change Expert Disasters and Climate Variability Selection Implementation Component 1: Restoring Flood PK-PIU AJK-30285-CS-INDV / Protection Infrastructure and Individual Consultant Infrastructure Specialist PIU- IDA / 56860 Post Open 50,000.00 48,410.07 Signed 2017-09-29 2017-10-08 2017-10-13 2017-10-17 2017-10-17 2017-10-17 2019-11-30 Upgrading Flood Management Selection DCRIP Systems PK-PDMA PUNJAB-36023-CS- Component 2: Managing Individual Consultant Pending IDA / 56860 Post Open 36,000.00 0.00 2017-11-08 2017-11-13 2017-11-15 2017-12-07 2018-12-02 INDV / Procurement Specialist Disasters and Climate Variability Selection Implementation Page 7