Sample Procurement Plan I. General 1. Project Information : Disaster Risk Management and Urban Development Project (P145268) /Gouvernement de la République du Niger 2. Bank’s approval Date of the procurement Plan 19-oct.-15 3. Date of General Procurement Notice: March 17, 2015 4. Period covered by this procurement plan: Juillet 2017- Décembre 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 1,000,000 All 2. NCB (Goods) NA 3. ICB (Works) Above US$ 10 million All 4. NCB (Works) NA 5. (Non-Consultant Services) Above US$ 1,000,000 All [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Description Estimated Packages Review Comments July 9, 2010 Ref. Cost Domestic by Bank No. US$ Preference (Prior / million (yes/no) Post) Summary of 16.734 1 N/A Prior the ICB (Work) Summary of 0 0 N/A Post the ICB (Goods) Summary of 26.993 24 N/A Post the NCB (Works) Summary of 0.449 2 N/A Post the NCB (Goods) Summary of 0 0 N/A Post the ICB (Non Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold (en Comments US$ 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) Above US$ 100,000 3. Individual (Comparison of CVs) Above US$ 100,000 Individual (Single source) Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_200,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 3.124 11 Prior number of contracts that will be let under QCBS July 9, 2010 Summary of 1.886 18 Post CQS, CDS, number of IC contracts that will be let under other methods July 9, 2010 PROCUREMENT Niger : Niger Disaster Risk Management and Urban Development Project PLAN General Information Country: Niger Bank’s Approval Date of the Original Procurement Plan: 2017-10-19 2020-01-09 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P145268 GPN Date: Project Name: Niger Disaster Risk Management and Urban Development Project Loan / Credit No: IDA / 53400, IDA / Q8620, IDA / 64130 Executing Agency(ies): Projet de Gestion des Risques de Catastrophes et de DéveloppementUrbain (PGRC-DU) WORKS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-PGRC-DU-21866-CW- RFB / TRAVAUX DE Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Appel d'offres Open - National 1,666,666.00 1,926,017.13 Achevé 2017-07-25 2017-07-30 2017-09-10 2017-10-10 2017-11-14 2018-05-13 REALISATION DE LA Management Investments Envelope DIGUE ROUTE DE DOSSO NE-PGRC-DU-21896-CW- RFB / Réhabilitation et construction d'infrastructures Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Appel d'offres Open - National 320,667.00 0.00 Annulé 2017-07-25 2017-07-30 2017-09-10 2017-10-10 2017-11-14 2018-05-13 scolaires dans les zones Management Investments Envelope touchées par les inondations à Diffa NE-PGRC-DU-22531-CW- RFB / REHABILITATION D'INFRASTRUCTURES Comp. 1: Flood Risk Single Stage - One En attente IDA / 53400 A posteriori Appel d'offres Open - National 100,000.00 0.00 2017-10-10 2017-10-15 2017-11-26 2017-12-26 2018-01-30 2018-07-29 SCOLAIRES DANS LES Management Investments Envelope d'exécution REGIONS DE DOSSO ET TILLABERY NE-PGRC-DU-22568-CW- RFB / Construction Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Appel d'offres Open - National 280,000.00 0.00 Annulé 2017-10-02 2017-10-07 2017-11-18 2017-12-18 2018-01-22 2018-07-21 d'infrastructure scolaires et Management Investments Envelope de sante à SENO NE-PGRC-DU-22586-CW- Comp. 1: Flood Risk Single Stage - One RFB / Travaux d'Extension IDA / 53400 A posteriori Appel d'offres Open - National 430,000.00 0.00 Annulé 2017-12-04 2017-12-09 2018-01-20 2018-02-19 2018-03-26 2018-09-22 Management Investments Envelope du réseau AEP à SENO NE-PGRC-DU-22598-CW- RFB / Réhabilitation des Comp. 1: Flood Risk Single Stage - One En attente infrastructures scolaires IDA / 53400 A posteriori Appel d'offres Open - National 83,333.00 0.00 2017-12-11 2017-12-16 2018-01-27 2018-02-26 2018-04-02 2018-09-29 Management Investments Envelope d'exécution dans les Régions de Dosso et Tillabery NE-PGRC-DU-22601-CW- RFB / Travaux de construction du mur de Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Appel d'offres Open - National 141,667.00 0.00 Annulé 2017-10-02 2017-10-07 2017-11-18 2017-12-18 2018-01-22 2018-07-21 clôture de l'Hôpital de Management Investments Envelope district de Kollo Région de Tillabéry NE-PGRC-DU-22611-CW- RFB / Travaux de construction de 10 blocs de Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Appel d'offres Open - National 700,000.00 0.00 Annulé 2017-10-16 2017-10-21 2017-12-02 2018-01-01 2018-02-05 2018-08-04 3 classes en matériaux Management Investments Envelope définitifs dans la Région de Diffa NE-PGRC-DU-22626-CW- Comp. 1: Flood Risk Single Stage - One RFB / Electrification de 23 IDA / 53400 A posteriori Appel d'offres Open - National 800,000.00 0.00 Annulé 2018-04-02 2018-04-07 2018-05-19 2018-06-18 2018-07-23 2019-01-19 Management Investments Envelope carrefours NE-PGRC-DU-22649-CW- RFB / Travaux de Comp. 1: Flood Risk Single Stage - One IDA / 53400 A priori Appel d'offres Open - National 6,000,000.00 0.00 Annulé 2017-07-28 2017-08-02 2017-09-13 2017-10-13 2017-11-17 2018-05-16 réhabilitation des AHA de Management Investments Envelope DOSSO NE-PGRC-DU-22674-CW- RFB / Construction de Treize (13) Casernes de Comp. 1: Flood Risk Single Stage - One En attente IDA / 53400 A posteriori Appel d'offres Open - National 3,453,443.00 0.00 2017-07-28 2017-08-02 2017-09-13 2017-10-13 2017-11-17 2018-05-16 Sapeurs Pompiers reparties Management Investments Envelope d'exécution sur les 4 Régions du Niger en 13 lots NE-PGRC-DU-22681-CW- RFB / Comp. 1: Flood Risk Single Stage - One Construction/renforcement 3 IDA / 53400 A posteriori Appel d'offres Open - National 2,795,280.00 0.00 Annulé 2017-07-28 2017-08-02 2017-09-13 2017-10-13 2017-11-17 2018-05-16 Management Investments Envelope Digues de protection a Niamey Page 1 NE-PGRC-DU-22592-CW- RFB / Travaux de Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Appel d'offres Open - National 1,666,667.00 0.00 Annulé 2017-11-06 2017-11-11 2017-12-23 2018-01-22 2018-02-26 2018-08-25 réhabilitation des AHA de Management Investments Envelope Diffa NE-PGRC-DU-34098-CW- RFB / Réalisation des travaux de Traitement des Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Appel d'offres Open - National 2,000,000.00 0.00 Annulé 2017-12-01 2017-12-06 2018-01-17 2018-02-16 2018-03-23 2018-09-19 Koris de Karma, Youri et Management Investments Envelope Gourou Kaina en 3 lots, Region de Tillabery NE-PGRC-DU-48784-CW- RFB / Construction de CSI Type II à Kanya, d'une Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Appel d'offres Open - National 1,000,000.00 0.00 Annulé 2018-04-30 2018-05-05 2018-06-16 2018-07-16 2018-08-20 2019-02-16 maternité à Goubey et d'un Management Investments Envelope mur de cloture à l'hôpital de district de Kollo NE-PGRC-DU-22620-CW- Comp. 1: Flood Risk Single Stage - One RFB / Construction de la IDA / 53400 A posteriori Appel d'offres Open - National 4,000,000.00 0.00 Annulé 2017-09-25 2017-09-30 2017-11-11 2017-12-11 2018-01-15 2018-07-14 Management Investments Envelope route Maine soroa-Gaidam NE-PGRC-DU-22528-CW- RFB / Rehabilitation et construction d'INFRASTRUCTURES Comp. 1: Flood Risk Single Stage - One SCOLAIRES ET IDA / 53400 A posteriori Appel d'offres Open - National 997,917.00 0.00 Annulé 2017-07-28 2017-08-02 2017-09-13 2017-10-13 2017-11-17 2018-05-16 Management Investments Envelope SANITAIRES dans les zones touchées par les inondationsdans la region de Tillabéri NE-PGRC-DU-34095-CW- RFB / Travaux de Comp. 1: Flood Risk Open - Single Stage - One IDA / 53400 A posteriori Appel d'offres 4,000,000.00 0.00 Annulé 2018-06-03 2018-06-08 2018-07-20 2018-08-19 2018-09-23 2019-03-22 réalisation de la Route Management Investments International Envelope Mainé-Gaidam NE-PGRC-DU-22535-CW- Comp. 1: Flood Risk Single Stage - One RFB / Réalisation caniveaux IDA / 53400 A posteriori Appel d'offres Open - National 1,833,333.00 0.00 Annulé 2018-02-05 2018-02-10 2018-03-24 2018-04-23 2018-05-28 2018-11-24 Management Investments Envelope de Dosso NE-PGRC-DU-22512-CW- RFB / Viabilisation site de recasement SENO: blocs sanitaires LOT1, Construction et Equipement Comp. 1: Flood Risk Single Stage - One de classes (2 blocs de of six IDA / 53400 A posteriori Appel d'offres Open - National 1,558,333.00 0.00 Annulé 2017-07-28 2017-08-02 2017-09-13 2017-10-13 2017-11-17 2018-05-16 Management Investments Envelope classes, bloc administratif, case gardien, latrines et clôture) LO2, Construction de Centre de santé intégré de type II (avec maternité) NE-PGRC-DU-22554-CW- RFB / Travaux de Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Appel d'offres Open - National 2,416,667.00 0.00 Annulé 2017-12-11 2017-12-16 2018-01-27 2018-02-26 2018-04-02 2018-09-29 réalisation de forages, puits Management Investments Envelope et caniveaux à Tillabery NE-PGRC-DU-57981-CW- RFQ / Fixation des dunes (clayonnage, plantations, Comp. 1: Flood Risk Single Stage - One ensemencement et IDA / Q8620 A posteriori Demande de prix Open - National 50,000.00 62,377.47 Achevé 2018-04-20 2018-06-15 2018-12-12 Management Investments Envelope gardiennage) dans la Région de Diffa commune de Chetimari Zone N°1 NE-PGRC-DU-58098-CW- RFQ / Réalisation des regarnis sur les sites de Comp. 1: Flood Risk Single Stage - One récuperation de terres de IDA / Q8620 A posteriori Demande de prix Open - National 28,744.00 26,280.83 Achevé 2018-04-20 2018-06-15 2018-12-12 Management Investments Envelope 2015 et 2016 dans les départements de Loga et Tibiri (7 sites) NE-PGRC-DU-58096-CW- RFQ / Réalisation des regarnis sur les sites de Comp. 1: Flood Risk Single Stage - One IDA / Q8620 A posteriori Demande de prix Open - National 111,145.00 64,222.67 Achevé 2018-04-20 2018-06-15 2018-12-12 récuperation de terres de Management Investments Envelope 2015 et 2016 dans la région de Diffa (9 sites) NE-PGRC-DU-58076-CW- RFQ / Réalisation des regarnis sur les sites de Comp. 1: Flood Risk Single Stage - One récuperation de terres de IDA / Q8620 A posteriori Demande de prix Open - National 15,617.00 23,729.21 Achevé 2018-04-20 2018-06-15 2018-12-12 Management Investments Envelope 2015 et 2016 dans les départements de Doutchi et Dosso (11 sites) Page 2 NE-PGRC-DU-58100-CW- RFQ / Réalisation des regarnis sur les sites de Comp. 1: Flood Risk Single Stage - One récuperation de terres de IDA / Q8620 A posteriori Demande de prix Open - National 64,000.00 45,814.12 Achevé 2018-04-20 2018-06-15 2018-12-12 Management Investments Envelope 2015 et 2016 dans le département de Mainé-Soroa (7 sites) NE-PGRC-DU-58101-CW- RFQ / Réalisation des regarnis sur les sites de Comp. 1: Flood Risk Single Stage - One récuperation de terres de IDA / Q8620 A posteriori Demande de prix Open - National 37,138.00 12,208.12 Achevé 2018-04-20 2018-06-15 2018-12-12 Management Investments Envelope 2015 et 2016 dans les départements de Kollo et Niamey V (6 sites) NE-PGRC-DU-58106-CW- RFQ / Réalisation des regarnis sur les sites de Comp. 1: Flood Risk Single Stage - One récuperation de terres de IDA / Q8620 A posteriori Demande de prix Open - National 30,234.00 26,399.61 Achevé 2018-04-20 2018-06-15 2018-12-12 Management Investments Envelope 2015 et 2016 dans le département de Filingue (12 sites) NE-PGRC-DU-58103-CW- RFQ / Réalisation des regarnis sur les sites de Comp. 1: Flood Risk Single Stage - One récuperation de terres de IDA / Q8620 A posteriori Demande de prix Open - National 15,409.00 41,956.95 Achevé 2018-04-20 2018-06-15 2018-12-12 Management Investments Envelope 2015 et 2016 dans les départements de Ouallam (9 sites) NE-PGRC-DU-58104-CW- RFQ / Réalisation des regarnis sur les sites de Comp. 1: Flood Risk Single Stage - One récuperation de terres de IDA / Q8620 A posteriori Demande de prix Open - National 16,398.00 42,224.84 Achevé 2018-04-20 2018-06-15 2018-12-12 Management Investments Envelope 2015 et 2016 dans le département de Tillabery (8 sites) NE-PGRC-DU-58109-CW- RFQ / Réalisation des regarnis sur les sites de Comp. 1: Flood Risk Single Stage - One récuperation de terres de IDA / Q8620 A posteriori Demande de prix Open - National 40,258.00 55,126.08 Achevé 2018-04-20 2018-06-15 2018-12-12 Management Investments Envelope 2015 et 2016 dans les départements de Tera, Torodi et Bankilaré (9 sites) NE-PGRC-DU-57987-CW- RFQ / Fixation des dunes (clayonnage, plantations, Comp. 1: Flood Risk Single Stage - One ensemencement et IDA / Q8620 A posteriori Demande de prix Open - National 80,000.00 124,847.48 Achevé 2018-04-20 2018-06-15 2018-12-12 Management Investments Envelope gardiennage) dans la Région de Diffa Commune de Chetimari Zone N°2 NE-PGRC-DU-58051-CW- RFQ / Fixation des dunes (clayonnage, plantations, Comp. 1: Flood Risk Single Stage - One ensemencement et IDA / Q8620 A posteriori Demande de prix Open - National 60,000.00 124,831.28 Signé 2018-04-20 2018-06-15 2018-12-12 Management Investments Envelope gardiennage) dans la Région de Diffa commune de Chetimari Zone 5 NE-PGRC-DU-58057-CW- RFQ / Fixation des dunes (clayonnage, plantations, Comp. 1: Flood Risk Single Stage - One ensemencement et IDA / Q8620 A posteriori Demande de prix Open - National 30,000.00 62,750.54 Achevé 2018-04-20 2018-06-15 2018-12-12 Management Investments Envelope gardiennage) dans la Région de Diffa commune de Chetimari Zone 7 NE-PGRC-DU-58111-CW- RFQ / Réalisation de 75 km de cordons de pierres sèches Comp. 1: Flood Risk Single Stage - One En cours IDA / Q8620 A posteriori Demande de prix Open - National 37,500.00 0.00 2018-04-20 2018-06-15 2018-12-12 sur les versants des Management Investments Envelope d'exécution plateaux dans la Région de Tillabéry NE-PGRC-DU-58112-CW- RFQ / Réalisation de 75 km de cordons de pierres sèches Comp. 1: Flood Risk Single Stage - One En cours IDA / Q8620 A posteriori Demande de prix Open - National 37,500.00 0.00 2018-04-20 2018-06-15 2018-12-12 sur les versants des Management Investments Envelope d'exécution plateaux dans la Région de Dosso Page 3 NE-PGRC-DU-58073-CW- RFQ / Réalisation des regarnis sur les sites de Comp. 1: Flood Risk Single Stage - One récuperation de terres de IDA / Q8620 A posteriori Demande de prix Open - National 41,652.00 29,706.83 Achevé 2018-04-20 2018-06-15 2018-12-12 Management Investments Envelope 2015 et 2016 dans les départements de Boboye et Dioudou (10 sites) NE-PGRC-DU-57993-CW- RFQ / Fixation des dunes (clayonnage, plantations, Comp. 1: Flood Risk Single Stage - One ensemencement et IDA / Q8620 A posteriori Demande de prix Open - National 80,000.00 62,768.43 Achevé 2018-04-20 2018-06-15 2018-12-12 Management Investments Envelope gardiennage) dans la Région de Diffa commune de Chetimari Zone 3 NE-PGRC-DU-58041-CW- RFQ / Fixation des dunes (clayonnage, plantations, Comp. 1: Flood Risk Single Stage - One ensemencement et IDA / Q8620 A posteriori Demande de prix Open - National 120,000.00 62,124.13 Achevé 2018-04-20 2018-06-15 2018-12-12 Management Investments Envelope gardiennage) dans la Région de Diffa commune de Chetimari Zone 3 NE-PGRC-DU-58060-CW- RFQ / Fixation des dunes (clayonnage, plantations, Comp. 1: Flood Risk Single Stage - One ensemencement et IDA / Q8620 A posteriori Demande de prix Open - National 80,000.00 62,246.44 Achevé 2018-04-20 2018-06-15 2018-12-12 Management Investments Envelope gardiennage) dans la Région de Diffa commune de Chetimari Zone 6 NE-PGRC-DU-59864-CW- RFB / TRAVAUX DE REHABILITATION DES AMENAGEMENTS HYDRO- Comp. 1: Flood Risk Open - Single Stage - One IDA / 53400 A priori Appel d'offres 16,734,385.00 16,808,670.30 Signé 2017-02-06 2017-02-11 2017-03-25 2017-04-24 2017-05-29 2017-11-25 AGRICOLE Management Investments International Envelope DANS LES REGIONS DE TILLABERY ET NIAMEY EN 6 (SIX) LOTS NE-PGRC-DU-39244-CW- RFB / Travaux de réhabilitation des Comp. 1: Flood Risk Open - Single Stage - One IDA / 53400 A priori Appel d'offres 16,734,385.00 0.00 Annulé 2017-12-04 2017-12-09 2018-01-20 2018-02-19 2018-03-26 2018-09-22 Aménagement Hydro Management Investments International Envelope Agricoles dans les Régions de Niamey et Tillabéry NE-PGRC-DU-22589-CW- RFB / TRAVAUX DE PROTECTION MECANIQUE Comp. 1: Flood Risk Single Stage - One DES BERGES DE KORIS IDA / 53400 A posteriori Appel d'offres Open - National 333,333.00 0.00 Annulé 2018-03-05 2018-03-10 2018-04-21 2018-05-21 2018-06-25 2018-12-22 Management Investments Envelope (9 KORIS A NIAMEY, DO et TY + TAGABATTI ET YOURI NE-PGRC-DU-22561-CW- Comp. 1: Flood Risk Single Stage - One RFB / Réalisation Piste IDA / 53400 A posteriori Appel d'offres Open - National 500,000.00 0.00 Annulé 2017-12-18 2017-12-23 2018-02-03 2018-03-05 2018-04-09 2018-10-06 Management Investments Envelope SENO NE-PGRC-DU-103840-CW- RFB / Construction des Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Appel d'offres Open - National 781,250.00 582,292.03 Signé 2019-04-01 2019-04-06 2019-05-18 2019-06-17 2019-07-22 2020-01-18 caniveaux dans la région de Management Investments Envelope Tillabéri NE-PGRC-DU-103785-CW- RFB / Installer des feux Comp. 2: Capacity Building Single Stage - One tricolores et passages cloutés IDA / 53400 for Urban Development and A posteriori Appel d'offres Open - National 572,916.67 494,525.02 Signé 2019-03-04 2019-03-09 2019-04-20 2019-05-20 2019-06-24 2019-12-21 Envelope au niveau de 23 carrefours Disaster Risk Management de la ville de Niamey NE-PGRC-DU-103831-CW- RFB / Travaux de Comp. 1: Flood Risk Single Stage - One Construire des forages et IDA / 53400 A posteriori Appel d'offres Open - National 684,027.78 783,695.23 Signé 2019-03-20 2019-03-25 2019-05-06 2019-06-05 2019-07-10 2020-01-06 Management Investments Envelope puits villageois dans la région de Tillabéri NE-PGRC-DU-103819-CW- RFB / Réhabiliter les Comp. 1: Flood Risk Single Stage - One En attente stations de pompage et de IDA / 53400 A posteriori Appel d'offres Open - National 868,055.56 0.00 2019-04-20 2019-04-25 2019-06-06 2019-07-06 2019-08-10 2020-02-06 Management Investments Envelope d'exécution drainage de l'AHA de Saga dans la région de Niamey NE-PGRC-DU-103833-CW- RFB / Construction de Comp. 1: Flood Risk Single Stage - One salles de classes en IDA / 53400 A posteriori Appel d'offres Open - National 260,416.67 260,873.12 Signé 2019-04-20 2019-04-25 2019-06-06 2019-07-06 2019-08-10 2020-02-06 Management Investments Envelope matériaux définitifs dans la region de Diffa Page 4 NE-PGRC-DU-103795-CW- RFQ / Construction mur de Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Demande de prix Limited 17,361.11 16,637.89 Signé 2019-05-20 2019-07-15 2020-01-11 clôture de l'école de Management Investments Envelope Bandabari NE-PGRC-DU-103787-CW- RFQ / Construire le mur Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Demande de prix Limited 104,166.67 83,009.84 Signé 2019-05-20 2019-07-15 2020-01-11 de clôture du l'Hopital de Management Investments Envelope district de Kollo NE-PGRC-DU-103844-CW- Comp. 1: Flood Risk Single Stage - One RFQ / Construire une IDA / 53400 A posteriori Demande de prix Limited 104,166.67 78,246.83 Signé 2019-05-20 2019-07-15 2020-01-11 Management Investments Envelope maternité à Goubey NE-PGRC-DU-103829-CW- RFQ / Réhabilitation de la Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Demande de prix Limited 86,805.56 83,382.04 Signé 2019-05-20 2019-07-15 2020-01-11 case de santé de Ajé Management Investments Envelope Muraba en CSI (Gaya) NE-PGRC-DU-103799-CW- RFQ / Construire le mur de Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Demande de prix Limited 43,402.78 57,759.16 Signé 2019-05-20 2019-07-15 2020-01-11 cloture du CSI de Moussa Management Investments Envelope Dey NE-PGRC-DU-103828-CW- RFQ / Réhabiliter du service Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Demande de prix Limited 104,166.67 86,616.49 Signé 2019-05-20 2019-07-15 2020-01-11 des urgences de l'Hôpital de Management Investments Envelope District de Mainé Soroa NE-PGRC-DU-103812-CW- RFB / Réaliser les travaux Comp. 1: Flood Risk Single Stage - One En attente de protection des berges des IDA / 53400 A posteriori Appel d'offres Open - National 225,694.44 0.00 2019-04-20 2019-04-25 2019-06-06 2019-07-06 2019-08-10 2020-02-06 Management Investments Envelope d'exécution koris dans la région de Dosso NE-PGRC-DU-103813-CW- RFB / Réaliser les travaux de protection des berges du Comp. 1: Flood Risk Single Stage - One En attente IDA / 53400 A posteriori Appel d'offres Open - National 138,888.89 0.00 2019-04-20 2019-04-25 2019-06-06 2019-07-06 2019-08-10 2020-02-06 kori de Bangou Koira Zéno Management Investments Envelope d'exécution et Saga Fondo , région de Tillabéri NE-PGRC-DU-103794-CW- RFB / Travaux de Comp. 1: Flood Risk Single Stage - One En attente realisation de l'Ouvrage de IDA / 53400 A posteriori Appel d'offres Open - National 319,444.44 0.00 2019-04-20 2019-04-25 2019-06-06 2019-07-06 2019-08-10 2020-02-06 Management Investments Envelope d'exécution franchissement de Sirfi Koira NE-PGRC-DU-103826-CW- RFB / Travaux de Comp. 1: Flood Risk Single Stage - One En cours realisation des Ouvrages de IDA / 53400 A posteriori Appel d'offres Open - National 781,250.00 0.00 2019-07-03 2019-07-08 2019-08-19 2019-09-18 2019-10-23 2020-04-20 Management Investments Envelope d'exécution protection dans les régions d'Agadez et Tahoua NE-PGRC-DU-103832-CW- RFQ / Selection des ONGs pour la realisation des Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Demande de prix Limited 170,000.00 235,466.15 Signé 2019-04-25 2019-06-20 2019-12-17 activités de renforcement Management Investments Envelope des fixations des dunes sur 300 HA en 3 Lot à Diffa NE-PGRC-DU-103792-CW- RFQ / Traitement Comp. 1: Flood Risk Single Stage - One En attente mécanique et biologique du IDA / Q8620 A posteriori Demande de prix Limited 52,083.33 0.00 2019-04-25 2019-06-20 2019-12-17 Management Investments Envelope d'exécution plateau et du bassin versant de Youri NE-PGRC-DU-103825-CW- RFB / Travaux de Comp. 1: Flood Risk Single Stage - One En attente IDA / 53400 A posteriori Demande de prix Open - National 187,500.00 0.00 2019-06-30 2019-08-25 2020-02-21 Construction puits villageois Management Investments Envelope d'exécution Dosso NE-PGRC-DU-103791-CW- RFQ / Selection des ONGs pour Assurer le regarnis des Comp. 1: Flood Risk Single Stage - One En attente IDA / Q8620 A posteriori Demande de prix Limited 138,888.89 0.00 2019-04-25 2019-06-20 2019-12-17 sites de restauration des Management Investments Envelope d'exécution terres de 2015,2016 et 2017 NE-PGRC-DU-34154-CW- RFB / travaux supplémentaires de Passation de Comp. 1: Flood Risk rehabilitation des routes en IDA / 53400 A posteriori marché de gré à Direct 44,560.00 0.00 Annulé 2018-01-08 2018-01-13 2018-02-17 2018-08-16 Management Investments terres Région de Dosso Lot gré 2: SIA-ADIGA-KAWRAN DEBE (31 km) Page 5 NE-PGRC-DU-22521-CW- RFB / Rehabilitation ou construction de latrines dans Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Appel d'offres Open - National 333,333.00 0.00 Annulé 2017-07-28 2017-08-02 2017-09-13 2017-10-13 2017-11-17 2018-05-16 les zones touchées par les Management Investments Envelope inondations dans la Région de Tillabéri NE-PGRC-DU-22624-CW- RFB / Travaux de Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Appel d'offres Open - National 1,000,000.00 0.00 Annulé 2018-02-05 2018-02-10 2018-03-24 2018-04-23 2018-05-28 2018-11-24 construction de la Digue de Management Investments Envelope DIFFA NE-PGRC-DU-22547-CW- RFB / Travaux de Comp. 1: Flood Risk Single Stage - One réalisation de de Puits et IDA / 53400 A posteriori Appel d'offres Open - National 450,000.00 0.00 Annulé 2017-11-06 2017-11-11 2017-12-23 2018-01-22 2018-02-26 2018-08-25 Management Investments Envelope Mini AEP dans la Région de Diffa NE-PGRC-DU-103839-CW- RFQ / Construire le mur Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Demande de prix Limited 86,805.56 0.00 Annulé 2019-05-20 2019-07-15 2020-01-11 de clôture du l'Hopital de Management Investments Envelope district de Kollo NE-PGRC-DU-138616-CW- RFQ / Construction d'un Comp. 2: Capacity Building mur de clôture de la Single Stage - One En cours IDA / Q8620 for Urban Development and A posteriori Demande de prix Limited 60,000.00 55,142.76 2019-10-20 2019-12-15 2020-06-12 Caserne de Sapeurs Envelope d'exécution Disaster Risk Management Pompiers de la ville de Diffa NE-PGRC-DU-103842-CW- RFB / Réalisation des Collecteurs Prioritaires du Comp. 1: Flood Risk Single Stage - One En cours IDA / 53400 A posteriori Appel d'offres Open - National 2,400,000.00 0.00 2019-11-17 2019-11-22 2020-01-03 2020-02-02 2020-03-08 2020-09-04 Bassin versant S3 dans Management Investments Envelope d'exécution l’Arrondissement Communal n°1 de Niamey NE-PGRC-DU-145434-CW- RFB / Travaux de Comp. 1: Flood Risk Single Stage - One En cours construction de 10 puits IDA / 53400 A posteriori Appel d'offres Open - National 220,000.00 0.00 2019-11-14 2019-11-19 2019-12-31 2020-01-30 2020-03-05 2020-09-01 Management Investments Envelope d'exécution cimentés dans la Région de Dosso NE-PGRC-DU-151386-CW- RFB / Travaux de pose de Pierres sèches et gabions Comp. 1: Flood Risk Single Stage - One En attente 4350 m/l sur les sites de IDA / 53400 A posteriori Appel d'offres Open - National 945,455.00 0.00 2020-01-20 2020-01-25 2020-03-07 2020-04-06 2020-05-11 2020-11-07 Management Investments Envelope d'exécution TAGAZAR, BOGHOL, ELIWALANE à Tirozerine Region d'Agadez NE-PGRC-DU-151515-CW- RFQ / Ouvrage d’épandage Comp. 1: Flood Risk Single Stage - One En attente sur des terres pastorales  à IDA / 64130 A posteriori Demande de prix Limited 181,818.00 0.00 2020-02-20 2020-04-16 2020-10-13 Management Investments Envelope d'exécution Agarégaré (INGALL) Region d'Agadez : NE-PGRC-DU-151414-CW- RFB / Travaux de Comp. 1: Flood Risk Single Stage - One En attente réalisation de 800 ml de IDA / 64130 A posteriori Appel d'offres Open - National 263,636.00 0.00 2020-02-15 2020-02-20 2020-04-02 2020-05-02 2020-06-06 2020-12-03 Management Investments Envelope d'exécution canivaux dans la Ville de Tahoua NE-PGRC-DU-151421-CW- RFB / Travaux de pavage Comp. 1: Flood Risk Single Stage - One En attente de rue (9km)/ chaussées IDA / 64130 A posteriori Appel d'offres Open - National 589,091.00 0.00 2020-02-15 2020-02-20 2020-04-02 2020-05-02 2020-06-06 2020-12-03 Management Investments Envelope d'exécution drainantes dans la Ville de Tahoua NE-PGRC-DU-151419-CW- RFQ / Travaux de Comp. 1: Flood Risk Single Stage - One En attente rehabilitation de 20 puits IDA / 64130 A posteriori Demande de prix Limited 63,636.00 0.00 2020-03-20 2020-05-15 2020-11-11 Management Investments Envelope d'exécution maraichers (complement) à Iferouna Région d'Agadez NE-PGRC-DU-151415-CW- RFB / Travaux d'Aménagements mare de Babaye (Endiguement Comp. 1: Flood Risk Single Stage - One En attente IDA / 64130 A posteriori Appel d'offres Open - National 530,000.00 0.00 2020-02-15 2020-02-20 2020-04-02 2020-05-02 2020-06-06 2020-12-03 &plantation) et travaux de Management Investments Envelope d'exécution traitement de Koris de Maboya Amaré (Region de Tahoua) NE-PGRC-DU-151361-CW- RFB / Travaux de Construction de 2250 ml de Comp. 1: Flood Risk Single Stage - One En attente IDA / 64130 A posteriori Appel d'offres Open - National 586,364.00 0.00 2020-03-10 2020-03-15 2020-04-26 2020-05-26 2020-06-30 2020-12-27 chaussées drainantes dans Management Investments Envelope d'exécution la Ville de Konni Region de Tahoua Page 6 NE-PGRC-DU-151416-CW- Comp. 2: Capacity Building RFQ / Rehabilitation des Single Stage - One En attente IDA / 64130 for Urban Development and A posteriori Demande de prix Limited 36,000.00 0.00 2020-03-15 2020-05-10 2020-11-06 salles de classes à Loubé Envelope d'exécution Disaster Risk Management (Deoulé/Bouza) NE-PGRC-DU-151387-GO- RFB / Traitement mécanique et biologique le plateau et Comp. 1: Flood Risk Single Stage - One En attente les berges du Koris à IDA / 53400 A posteriori Appel d'offres Open - National 345,455.00 0.00 2020-03-10 2020-03-15 2020-04-26 2020-05-26 2020-06-30 2020-12-27 Management Investments Envelope d'exécution Loubé /Bouza commune rurale de Déoulé et à Bado dans la commune d’Illéla NE-PGRC-DU-151364-CW- RFQ / Travaux de Comp. 1: Flood Risk Single Stage - One En attente construction d’un seuil IDA / 64130 A posteriori Demande de prix Limited 127,273.00 0.00 2020-03-15 2020-05-10 2020-11-06 Management Investments Envelope d'exécution radier à Toumboul commune d’Illéla NE-PGRC-DU-151359-CW- RFQ / Activité de fixation Comp. 1: Flood Risk Single Stage - One En attente IDA / Q8620 A posteriori Demande de prix Limited 181,000.00 0.00 2020-04-15 2020-06-10 2020-12-07 des dunes dans la Région Management Investments Envelope d'exécution de Diffa GOODS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-PGRC-DU-22700-GO- RFB / Fournitures pour l'Assainissement Piloté par Comp. 1: Flood Risk Single Stage - One En attente IDA / 53400 A posteriori Appel d'offres Open - National 360,000.00 0.00 2017-08-25 2017-08-30 2017-10-11 2017-11-10 2017-12-15 2018-06-13 les Communautés (ATPC) Management Investments Envelope d'exécution dans les régions de Diffa, Tillabéri, Dosso NE-PGRC-DU-34106-GO- RFB / Fourniture et installation de panneaux de signalisation et rehabilitation Comp. 1: Flood Risk Open - Single Stage - One IDA / 53400 A posteriori Appel d'offres 800,000.00 968,388.84 Signé 2017-12-04 2017-12-09 2018-01-20 2018-02-19 2018-03-26 2018-09-22 de 42 feux tricolores avec Management Investments International Envelope amenagement des passages cloutés à proximité des feux dans la ville de Niamey NE-PGRC-DU-34111-GO- RFB / Acquisition de divers Comp. 1: Flood Risk Single Stage - One materiels informatiques et IDA / 53400 A posteriori Appel d'offres Open - National 200,000.00 0.00 Annulé 2017-11-15 2017-11-20 2018-01-01 2018-01-31 2018-03-07 2018-09-03 Management Investments Envelope mobiliers au profit des partennaires du PGRC-DU NE-PGRC-DU-34117-GO- RFQ / Acquisition de Comp. 1: Flood Risk Single Stage - One mobiliers pour equiper 9 IDA / 53400 A posteriori Demande de prix Limited 27,000.00 19,517.66 Achevé 2017-11-20 2018-01-15 2018-07-14 Management Investments Envelope salles de classe dans la Région de Diffa NE-PGRC-DU-34142-GO- RFQ / Acquisition de Comp. 1: Flood Risk Single Stage - One mobiliers pour equiper 6 IDA / 53400 A posteriori Demande de prix Limited 10,000.00 27,708.96 Achevé 2017-11-20 2018-01-15 2018-07-14 Management Investments Envelope salles de classe dans la Région de Tillabery NE-PGRC-DU-34091-GO- DIR / Travaux de fourniture Passation de Comp. 1: Flood Risk En attente et pose de 80 panneaux de IDA / 53400 A posteriori marché de gré à Direct 40,000.00 0.00 2017-11-15 2017-11-20 2017-12-25 2018-06-23 Management Investments d'exécution signalisation pour les 40 gré mini AEP solaire de Diffa NE-PGRC-DU-48782-GO- RFB / Acquisition des Comp. 1: Flood Risk Open - Single Stage - One équipements de recyclage IDA / 53400 A posteriori Appel d'offres 200,000.00 160,045.69 Signé 2018-05-15 2018-05-20 2018-07-01 2018-07-31 2018-09-04 2019-03-03 Management Investments International Envelope des déchets plastiques dans les communes urbaines NE-PGRC-DU-32968-GO- RFB / Fourniture de 1072 pompes solaires installation Comp. 4: Contingency Open - Single Stage - One et formation des utilisateurs IDA / 53400 A priori Appel d'offres 5,788,800.00 4,347,188.22 Signé 2018-02-27 2018-03-04 2018-04-15 2018-05-15 2018-06-19 2018-12-16 Component International Envelope dans les Régions de Tahoua et Agadez dans le cadre du MRI-2017 Page 7 NE-PGRC-DU-50933-GO- Comp. 1: Flood Risk Single Stage - One RFQ / Acquisition des IDA / 53400 A posteriori Demande de prix Limited 26,000.00 25,924.94 Achevé 2018-03-03 2018-04-28 2018-10-25 Management Investments Envelope gadgets publicitaires 2018 NE-PGRC-DU-49754-GO- DIR / Acquisition de 3 Passation de cameras d'évaluation de Comp. 1: Flood Risk IDA / 53400 A posteriori marché de gré à Direct 69,900.00 59,954.94 Achevé 2018-02-28 2018-03-05 2018-04-09 2018-10-06 catastrophes et formation Management Investments gré des agents de la protection civile sur leur utilisation NE-PGRC-DU-54042-GO- RFQ / Acquisition des semences et l'ensemencement Comp. 1: Flood Risk Single Stage - One IDA / Q8620 A posteriori Demande de prix Limited 100,000.00 73,458.42 Achevé 2018-04-14 2018-06-09 2018-12-06 des sites de récupération Management Investments Envelope des terres de 2015, 2016 et 2017 NE-PGRC-DU-54044-GO- RFQ / Acquisition des Pneu Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Demande de prix Limited 6,500.00 6,100.68 Achevé 2018-03-24 2018-05-19 2018-11-15 pour le Parc des UEP ( Management Investments Envelope Tillabéry et Dosso) NE-PGRC-DU-80731-GO- RFQ / Acquisition d'Equipement et de matériel Comp. 1: Flood Risk Single Stage - One informatique pour IDA / 53400 A posteriori Demande de prix Limited 60,000.00 60,996.79 Achevé 2018-10-25 2018-12-20 2019-06-18 Management Investments Envelope l'opérationnalisation SAP- DNPGCA et des dispositifs locaux d'alerte précoce. NE-PGRC-DU-80656-GO- RFQ / Acquisition et installation des lampes Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Demande de prix Limited 56,000.00 51,884.03 Achevé 2018-10-25 2018-12-20 2019-06-18 solaires dans la ville de Management Investments Envelope Niamey en appui au programme Niamey Nyalla NE-PGRC-DU-80707-GO- Comp. 1: Flood Risk Single Stage - One RFQ / Acquisition de IDA / 53400 A posteriori Demande de prix Limited 18,200.00 16,858.11 Achevé 2018-11-04 2018-12-30 2019-06-28 Management Investments Envelope Gabgets publicitaires 2019 NE-PGRC-DU-103808-GO- RFB / Acquisition des materiaux pour l'appui à Comp. 1: Flood Risk Single Stage - One En attente IDA / 53400 A posteriori Appel d'offres Open - National 120,000.00 0.00 2019-04-15 2019-04-20 2019-06-01 2019-07-01 2019-08-05 2020-02-01 l'amélioration des latrines Management Investments Envelope d'exécution familiales dans les régions de Diffa, Dosso et Tillabéri NE-PGRC-DU-103800-GO- RFQ / Acquisition de Comp. 1: Flood Risk Single Stage - One En attente matériel d'etuvage et autres IDA / 53400 A posteriori Demande de prix Limited 10,416.67 0.00 2019-04-20 2019-06-15 2019-12-12 Management Investments Envelope d'exécution activités dans le cadre de l'AGR Tillabery NE-PGRC-DU-103836-GO- RFQ / Assurer l'acquisition des semences et Comp. 1: Flood Risk Single Stage - One En cours IDA / Q8620 A posteriori Demande de prix Limited 34,722.22 0.00 2019-04-27 2019-06-22 2019-12-19 l'ensemencement des sites Management Investments Envelope d'exécution de récupération des terres de 2015, 2016; et 2017 NE-PGRC-DU-103834-GO- RFQ / Acquisition de Comp. 1: Flood Risk Single Stage - One En attente IDA / 53400 A posteriori Demande de prix Limited 5,208.33 0.00 2019-05-20 2019-07-15 2020-01-11 mobilier de bureau pour les Management Investments Envelope d'exécution UEP de Tahoua et Agadez NE-PGRC-DU-103843-GO- RFQ / Acquisition de Comp. 1: Flood Risk Single Stage - One serveurs et les equipements IDA / 53400 A posteriori Demande de prix Limited 26,041.67 27,879.73 Achevé 2019-04-25 2019-06-20 2019-12-17 Management Investments Envelope accessoires pour la base des données PGRC-DU NE-PGRC-DU-103796-GO- RFQ / Acquisition des Comp. 2: Capacity Building equipements informatique Single Stage - One En cours IDA / 53400 for Urban Development and A posteriori Demande de prix Open - National 475,694.00 0.00 2019-07-13 2019-09-07 2020-03-05 pour les partennaires dans Envelope d'exécution Disaster Risk Management le cadre de la composante NTIC NE-PGRC-DU-103827-GO- RFQ / Acquisition des Autres équipements Comp. 1: Flood Risk Single Stage - One En attente IDA / 53400 A posteriori Demande de prix Open - National 63,574.00 0.00 2019-07-06 2019-08-31 2020-02-27 techniques (Ondulaire, Management Investments Envelope d'exécution projecteur vidéo, panneau solaire) NTIC Page 8 NE-PGRC-DU-103807-GO- Comp. 1: Flood Risk Open - Single Stage - One En attente RFB / Acquisition de drones IDA / 53400 A posteriori Appel d'offres 118,924.00 0.00 2019-07-01 2019-07-06 2019-08-17 2019-09-16 2019-10-21 2020-04-18 Management Investments International Envelope d'exécution pour les partenaires NTIC NE-PGRC-DU-103823-GO- RFB / Acquisition du Comp. 1: Flood Risk Open - Single Stage - One En attente matériel d’assainissement IDA / 53400 A posteriori Appel d'offres 781,250.00 0.00 2019-07-08 2019-07-13 2019-08-24 2019-09-23 2019-10-28 2020-04-25 Management Investments International Envelope d'exécution pour les communes urbaines d’Agadez et de Tahoua NE-PGRC-DU-103810-GO- RFB / Acquisition de Comp. 1: Flood Risk Single Stage - One En attente IDA / 53400 A posteriori Demande de prix Open - National 88,585.00 0.00 2019-07-20 2019-09-14 2020-03-12 materiel de cartographie Management Investments Envelope d'exécution NTIC NE-PGRC-DU-54058-GO- RFQ / Acquisition fourniture Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Demande de prix Limited 5,500.00 0.00 Annulé 2018-03-31 2018-05-26 2018-11-22 de bureau UCP et UEP Management Investments Envelope (Diffa, Dosso et Tillabéry) NE-PGRC-DU-138597-GO- RFQ / Acquisition des intrants (semences de riz, semences potagères et Comp. 1: Flood Risk Single Stage - One engrais) pour appuyer les IDA / Q8620 A posteriori Demande de prix Limited 35,000.00 38,504.41 Achevé 2019-10-08 2019-12-03 2020-05-31 Management Investments Envelope producteurs opérant autour des Aménagements Hydro Agricoles de la Région de Tillabery. NE-PGRC-DU-138610-GO- RFQ / acquisition des plants Comp. 1: Flood Risk Single Stage - One En attente IDA / Q8620 A posteriori Demande de prix Limited 73,000.00 0.00 2019-10-20 2019-12-15 2020-06-12 pour les activités de Management Investments Envelope d'exécution regarnis 2019 NE-PGRC-DU-34100-GO- RFB / Fourniture et installation de deux (02) Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Appel d'offres Open - National 140,000.00 0.00 Annulé 2017-11-07 2017-11-12 2017-12-24 2018-01-23 2018-02-27 2018-08-26 groupes électrogénes au Management Investments Envelope profit du MAH/GC et l'UEP de Diffa NE-PGRC-DU-145419-GO- Comp. 3: Project Single Stage - One En attente RFQ / Acquisition des IDA / 64130 A posteriori Demande de prix Limited 20,000.00 0.00 2019-11-26 2020-01-21 2020-07-19 Management Envelope d'exécution gadgets publicitaires 2020 NE-PGRC-DU-151417-GO- RFQ / Acquisition des Comp. 2: Capacity Building Single Stage - One En attente Autres équipements IDA / 64130 for Urban Development and A posteriori Demande de prix Limited 65,455.00 0.00 2020-03-15 2020-05-10 2020-11-06 Envelope d'exécution techniques (panneaux Disaster Risk Management solaires) NTIC NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-PGRC-DU-53790-NC- RFQ / Réalisation de Spot publicitaire sur la Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Demande de prix Limited 23,000.00 26,576.63 Achevé 2018-03-24 2018-05-19 2018-11-15 sensibilisation à l'utilisation Management Investments Envelope civique des lignes d'appel d'urgence 18 NE-PGRC-DU-68111-NC- RFQ / Appui pour l'Acquisition et installation Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Demande de prix Limited 10,000.00 0.00 Annulé 2018-07-28 2018-09-22 2019-03-21 d'un logiciel de gestion du Management Investments Envelope parc auto pour le compte de la primature NE-PGRC-DU-139716-GO- RFQ / Confection des plaques de visibilité pour les infrastructures réalisées Comp. 3: Project Single Stage - One En attente dans le cadre du PGRC-DU IDA / 53400 A posteriori Demande de prix Limited 45,000.00 0.00 2019-10-20 2019-12-15 2020-06-12 Management Envelope d'exécution dans différentes zones d'intervention du Projet (Diffa, Dosso, Tillabery, Niamey, Tahoua et Agadez) Page 9 NE-PGRC-DU-151683-NC- RFQ / Confection de Comp. 3: Project Single Stage - One En attente Gadgets publicitaires 2020 IDA / 64130 A posteriori Demande de prix Limited 20,000.00 0.00 2019-12-30 2020-02-24 2020-08-22 Management Envelope d'exécution pour l'UCP et les differents UEP du PGRC-DU CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Interest Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-PGRC-DU-22707-CS- QCBS / Etudes et base de Comp. 2: Capacity Building Sélection fondée données en ligne sur Open - IDA / 53400 for Urban Development and A posteriori sur la qualité et 438,000.00 0.00 Annulé 2017-08-15 2017-09-05 2017-10-19 2017-11-16 2017-12-16 2018-01-20 2018-02-24 2019-02-24 l'occupation des zones International Disaster Risk Management le coût inondables et pistes pour la réduction des risques NE-PGRC-DU-22713-CS- QCBS / Etude d'avant projet sommaire (APS), d'avant projet détaillé (APD) et Sélection fondée Comp. 1: Flood Risk Open - En attente dossiers d'appel d'offres IDA / 53400 A priori sur la qualité et 576,000.00 0.00 2017-11-20 2017-12-11 2018-01-24 2018-02-21 2018-03-23 2018-04-27 2018-06-01 2019-06-01 Management Investments International d'exécution (DAO) et s uivi contrôle des le coût travaux pour la construction de collecteurs S3, S4, S5, S8 et S10 NE-PGRC-DU-22716-CS- QCBS / Elaboration de plans urbains de référence de 13 Communes , de Comp. 2: Capacity Building Sélection fondée Open - En attente l'audit urbain des villes des IDA / 53400 for Urban Development and A posteriori sur la qualité et 300,000.00 0.00 2017-12-25 2018-01-15 2018-02-28 2018-03-28 2018-04-27 2018-06-01 2018-07-06 2019-07-06 International d'exécution 4 Régions d'intervention du Disaster Risk Management le coût Projet et de l'audit organisationnel et financier des communes NE-PGRC-DU-22718-CS- Comp. 2: Capacity Building Sélection fondée Open - En attente QCBS / Elaboration des IDA / 53400 for Urban Development and A posteriori sur la qualité et 360,000.00 0.00 2017-07-28 2017-08-18 2017-10-01 2017-10-29 2017-11-28 2018-01-02 2018-02-06 2019-02-06 International d'exécution PDCs de 24 communes Disaster Risk Management le coût NE-PGRC-DU-22719-CS- Comp. 2: Capacity Building QBS / Réalisation de l'audit Sélection fondée IDA / 53400 for Urban Development and A posteriori Open - National 100,712.00 0.00 Annulé 2018-03-05 2018-03-26 2018-05-09 2018-06-06 2018-07-06 2018-08-05 2018-09-09 2019-09-09 organisationnel et financier sur la qualité Disaster Risk Management des communes NE-PGRC-DU-22720-CS- LCS / APS APS EIES DAOet suivi contrôle des Comp. 1: Flood Risk Sélection au En cours IDA / 53400 A posteriori Open - National 100,000.00 0.00 2017-07-28 2017-08-18 2017-10-01 2017-10-29 2017-11-28 2018-01-02 2018-02-06 2018-08-05 travaux d'aménagement Management Investments moindre coût d'exécution d'une décharge pour la ville de Niamey NE-PGRC-DU-22724-CS- CQS / Etude d'avant projet Sélection fondée détaillé (APD) et dossiers Comp. 1: Flood Risk sur les En attente d'appel d'offres (DAO) et IDA / 53400 A posteriori Open - National 100,000.00 0.00 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 Management Investments qualifications des d'exécution suivi contrôle des travaux consultants pour la digue route de Dosso NE-PGRC-DU-22726-CS- QCBS / APS APD EIES Sélection fondée Comp. 1: Flood Risk Open - DAO pour la construction de IDA / 53400 A posteriori sur la qualité et 300,000.00 0.00 Annulé 2017-09-04 2017-09-25 2017-11-08 2017-12-06 2018-01-05 2018-02-09 2018-03-16 2019-03-16 Management Investments International canaux et reprofilage le long le coût du Gounty Yena (9 km) NE-PGRC-DU-22727-CS- CQS / Etudes Sélection fondée APD/EIES/DAO et suivi Comp. 1: Flood Risk sur les En attente IDA / 53400 A posteriori Open - National 120,500.00 0.00 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 contrôle pour les travaux de Management Investments qualifications des d'exécution construction de caniveaux consultants puits et forages à Tillabery NE-PGRC-DU-22728-CS- CQS / ETUDES Sélection fondée COMPLEMENTAIRES ET Comp. 1: Flood Risk sur les En attente SUIVI CONTRÖLE DES IDA / 53400 A posteriori Open - National 100,000.00 0.00 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 Management Investments qualifications des d'exécution TRAVAUX DE consultants REALISATION DE LA DIGUE ROUTE DE DOSSO Page 10 NE-PGRC-DU-22733-CS- Sélection fondée CQS / ETUDES APS APD Comp. 1: Flood Risk sur les DAO REHABILITATION IDA / 53400 A posteriori Open - National 150,000.00 0.00 Annulé 2018-03-05 2018-03-26 2018-05-09 2018-06-08 2018-07-13 2019-01-09 Management Investments qualifications des CONSTRUCTION PUITS ET consultants CANIVEAU DOSSO NE-PGRC-DU-22734-CS- Sélection fondée QCBS / Actualisation études Comp. 1: Flood Risk Open - IDA / 53400 A posteriori sur la qualité et 200,000.00 290,289.49 Achevé 2017-07-28 2017-08-18 2017-10-01 2017-10-29 2017-11-28 2018-01-02 2018-02-06 2019-02-06 et suivi contrôle Route Management Investments International le coût Mainé-Gaidam NE-PGRC-DU-22735-CS- CQS / Actualisation des Sélection fondée études et suivi contrôle des Comp. 1: Flood Risk sur les En cours travaux de construction IDA / 53400 A posteriori Open - National 90,000.00 0.00 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 Management Investments qualifications des d'exécution d'infrastructures scolaires et consultants sanitaires dans la régions de Dosso et Tillabery NE-PGRC-DU-22740-CS- CQS / RECRUTEMENT Sélection fondée D'UNE ONG POUR Comp. 1: Flood Risk sur les En attente ACCOMPAGNEMENT DES IDA / 53400 A posteriori Open - National 244,152.00 0.00 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 Management Investments qualifications des d'exécution ACTIVITES AGR consultants AMENAGEMENT DOSSO (Sakongui, Tara et Kessa) NE-PGRC-DU-22741-CS- CQS / ACTUALISATION ETUDES ETSUIVI CONTRÔLE DES Sélection fondée TRAVAUX DE Comp. 1: Flood Risk sur les En attente CONSTRUCTION DES 10 IDA / 53400 A posteriori Open - National 90,000.00 0.00 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 Management Investments qualifications des d'exécution BLOCS DE 3 CLASSES consultants EN PLAQUE ECOLOGIQUE DANS LE CADRE DE L'URGENCE REGION DE DIFFA NE-PGRC-DU-22742-CS- CQS / Elaboration de la Sélection fondée Comp. 2: Capacity Building politique nationale de sur les En attente IDA / 53400 for Urban Development and A posteriori Open - National 200,000.00 0.00 2018-01-15 2018-02-05 2018-03-21 2018-04-20 2018-05-25 2018-11-21 l'action humanitaire et de la qualifications des d'exécution Disaster Risk Management gestion des catastrophes et consultants de son plan d'actions NE-PGRC-DU-70949-CS- INDV / CONCEPTION ET HEBERGEMENT D'UN SITE WEB POUR LE Comp. 3: Project Sélection fondée En cours PROJET DE GESTION DES IDA / 53400 A posteriori Open - National 10,181.00 0.00 2018-07-31 2018-08-21 2018-10-04 2018-11-01 2018-12-01 2018-12-31 2019-02-04 2020-02-04 Management sur la qualité d'exécution RISQUES DE CATASTROPHES ET DU DÉVELOPPEMENT URBAIN (PGRC-DU) NE-PGRC-DU-80733-CS- QCBS / Recrutement d'un Sélection fondée auditeur Externe pour la Comp. 1: Flood Risk En cours IDA / 53400 A priori sur la qualité et Open - National 50,000.00 0.00 2018-11-01 2018-11-22 2019-01-05 2019-02-02 2019-03-04 2019-04-08 2019-05-13 2020-05-12 réalisation d'audit des Management Investments d'examen le coût compte exercice 2018, 2019, 2020 et cloture NE-PGRC-DU-80700-CS- CQS / Recrutement d'un consultant chargé de la Sélection fondée mise à jour de 8 plans de Comp. 1: Flood Risk sur les IDA / 53400 A posteriori Open - National 120,000.00 147,948.08 Signé 2018-11-10 2018-12-01 2019-01-14 2019-02-13 2019-03-20 2019-09-16 Developpement Communaux Management Investments qualifications des (PDC) en intégrant les consultants dimensions ''changements climatiques, paix et securité" NE-PGRC-DU-96507-CS- QCBS / Recrutement d'un Sélection fondée auditeur Externe pour la Comp. 3: Project Open - IDA / 53400 A posteriori sur la qualité et 50,000.00 37,490.67 Achevé 2018-12-31 2019-01-21 2019-03-06 2019-04-03 2019-05-03 2019-06-07 2019-07-12 2020-07-11 réalisation d'audit des Management International le coût compte exercice 2018, 2019, 2020 et cloture NE-PGRC-DU-96510-CS- QCBS / Recrutement d'un Sélection fondée Comp. 3: Project Open - cabinet chargé de IDA / 53400 A posteriori sur la qualité et 15,000.00 13,208.92 Achevé 2018-12-31 2019-01-21 2019-03-06 2019-04-03 2019-05-03 2019-06-07 2019-07-12 2020-07-11 Management International sélectionner le coordonnateur le coût National du PGRC-DU NE-PGRC-DU-103786-CS- Sélection fondée CQS / Appui à Comp. 2: Capacity Building sur les En attente l'amélioration des latrines IDA / 53400 for Urban Development and A posteriori Open - National 50,000.00 0.00 2019-04-15 2019-05-06 2019-06-19 2019-07-19 2019-08-23 2020-02-19 qualifications des d'exécution familiales dans les régions Disaster Risk Management consultants de Diffa, Dosso et Tillabéri Page 11 NE-PGRC-DU-103793-CS- Sélection fondée CQS / Suivi contrôle des Comp. 1: Flood Risk sur les En attente travaux de l'Ouvrage de IDA / 53400 A posteriori Open - National 27,777.78 0.00 2019-03-15 2019-04-05 2019-05-19 2019-06-18 2019-07-23 2020-01-19 Management Investments qualifications des d'exécution franchissement de Sirfi consultants Koira NE-PGRC-DU-103841-CS- CQS / Recrutement d'un Sélection fondée cabinet pour realiser les Comp. 1: Flood Risk sur les En attente Etudes techniques et IDA / 53400 A posteriori Open - National 130,208.33 0.00 2019-03-15 2019-04-05 2019-05-19 2019-06-18 2019-07-23 2020-01-19 Management Investments qualifications des d'exécution environementales travaux consultants prévus dans le cadre du Fonds additioonnel NE-PGRC-DU-22722-CS- CQS / Etude d'avant projet Sélection fondée détaillé (APD) et dossiers Comp. 1: Flood Risk sur les IDA / 53400 A posteriori Open - National 110,000.00 0.00 Annulé 2017-09-04 2017-09-25 2017-11-08 2017-12-08 2018-01-12 2018-07-11 d'appel d'offres (DAO) pour Management Investments qualifications des les travaux de réalisation consultants des caniveaux de Dosso NE-PGRC-DU-22717-CS- Comp. 2: Capacity Building Sélection fondée QBS / Elaboration d'un IDA / 53400 for Urban Development and A posteriori Open - National 100,000.00 0.00 Annulé 2018-04-02 2018-04-23 2018-06-06 2018-07-04 2018-08-03 2018-09-02 2018-10-07 2019-10-07 sur la qualité guide sur l'intercollectivité Disaster Risk Management NE-PGRC-DU-22709-CS- QCBS / Etude de faisabilité Sélection fondée pour la régulation des Comp. 1: Flood Risk Open - IDA / 53400 A posteriori sur la qualité et 250,000.00 0.00 Annulé 2017-10-02 2017-10-23 2017-12-06 2018-01-03 2018-02-02 2018-03-09 2018-04-13 2019-04-13 écoulements dans les bassins Management Investments International le coût versants de la SIRBA et du GOROUBI NE-PGRC-DU-22710-CS- QCBS / Elaboration d'une politique nationale Sélection fondée Comp. 1: Flood Risk Open - d'assainissement (eaux IDA / 53400 A posteriori sur la qualité et 400,000.00 0.00 Annulé 2017-11-15 2017-12-06 2018-01-19 2018-02-16 2018-03-18 2018-04-22 2018-05-27 2019-05-27 Management Investments International pluviales, eaux usées, le coût assainissement de base, déchets solides) NE-PGRC-DU-34174-CS- Sélection fondée QBS / Etude-Suivi-contrôle Comp. 1: Flood Risk sur les des travaux supplementaire IDA / 53400 A posteriori Open - National 20,000.00 0.00 Annulé 2017-12-04 2017-12-25 2018-02-07 2018-03-09 2018-04-13 2018-10-10 Management Investments qualifications des sur la Route en Terre SIA- consultants ADIGA NE-PGRC-DU-22729-CS- CQS / ETUDES Sélection fondée COMPLEMENTAIRES ET Comp. 1: Flood Risk sur les SUIVI CONTRÖLE DES IDA / 53400 A posteriori Open - National 100,000.00 0.00 Annulé 2018-03-05 2018-03-26 2018-05-09 2018-06-08 2018-07-13 2019-01-09 Management Investments qualifications des TRAVAUX DE consultants REALISATION DES CANIVEAUX DE DOSSO NE-PGRC-DU-22731-CS- Sélection fondée CQS / ETUDES APS APD Comp. 1: Flood Risk sur les IDA / 53400 A posteriori Open - National 100,000.00 0.00 Annulé 2018-02-05 2018-02-26 2018-04-11 2018-05-11 2018-06-15 2018-12-12 DAO CONFORTATION AHA Management Investments qualifications des KARMA consultants NE-PGRC-DU-22732-CS- Sélection fondée CQS / ETUDES APS APD Comp. 1: Flood Risk sur les IDA / 53400 A posteriori Open - National 100,000.00 0.00 Annulé 2018-02-05 2018-02-26 2018-04-11 2018-05-11 2018-06-15 2018-12-12 DAO CONFORTATION AHA Management Investments qualifications des KARMA consultants NE-PGRC-DU-138614-CS- CQS / Recrutement d'une ONG pour faciliter les Sélection fondée Comp. 2: Capacity Building Activités Génératrices de sur les En cours IDA / Q8620 for Urban Development and A posteriori Open - National 60,000.00 0.00 2019-10-03 2019-10-24 2019-12-07 2020-01-06 2020-02-10 2020-08-08 revenus au profit des qualifications des d'examen Disaster Risk Management groupements des femmes consultants autour des Aménagements Hydro Agricoles de Tillabery NE-PGRC-DU-91457-CS- CQS / Recrutement d'un Sélection fondée Comp. 3: Project Open - cabinet chargé de IDA / 53400 A priori sur la qualité et 15,000.00 0.00 Annulé 2018-12-19 2019-01-09 2019-02-22 2019-03-22 2019-04-21 2019-05-26 2019-06-30 2020-06-29 Management International sélectionner le coordonnateur le coût National du PGRC-DU NE-PGRC-DU-151514-CS- Sélection fondée CQS / Etudes techniques et Comp. 1: Flood Risk sur les En attente IDA / 53400 A posteriori Open - National 36,000.00 0.00 2020-02-15 2020-03-07 2020-04-20 2020-05-20 2020-06-24 2020-12-21 environnementale de la Management Investments qualifications des d'exécution Digue de Kirkissoye Niamey consultants Page 12 NE-PGRC-DU-151420-CS- CQS / Etudes et suivi Sélection fondée Comp. 2: Capacity Building contrôle des travaux de sur les En attente IDA / 64130 for Urban Development and A posteriori Open - National 44,000.00 0.00 2020-01-20 2020-02-10 2020-03-25 2020-04-24 2020-05-29 2020-11-25 construction de la cité de qualifications des d'exécution Disaster Risk Management l'innovation dans le cadre de consultants la composante NTIC INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-PGRC-DU-22736-CS- INDV / consultant Pour conduire la collecte des Comp. 2: Capacity Building données sur les bâtiments En cours IDA / 53400 for Urban Development and A priori Individuel Direct 150,000.00 0.00 2017-07-28 2017-08-07 2017-08-28 2017-10-02 2018-03-31 et les terrains agricoles d'exécution Disaster Risk Management dans la commune V, le quartier de Goudel et le quartier de Lossa-Goungou NE-PGRC-DU-22739-CS- Comp. 1: Flood Risk En attente INDV / EIES DIGUE IDA / 53400 A posteriori Individuel Limited 30,000.00 0.00 2017-07-28 2017-08-02 2017-08-23 2017-09-27 2018-03-26 Management Investments d'exécution ROUTE DIFFA NE-PGRC-DU-48768-CS- INDV / Recrutement d'un consultant chargé de la mise à jour du cadre de Gestion Environnementale et Comp. 4: Contingency IDA / 53400 A posteriori Individuel Limited 13,090.00 9,531.15 Achevé 2018-02-13 2018-02-18 2018-03-11 2018-04-15 2018-10-12 Sociales (CGES) du PGRC- Component DU pour couvrir les régions d'Agadez et de Tahoua dans le cadre de l'extension du projet NE-PGRC-DU-48770-CS- INDV / Recrutement d'un consultant chargé de la mise à jour du cadre de politique de Réinstallation Comp. 4: Contingency IDA / 53400 A posteriori Individuel Limited 9,430.00 7,975.05 Achevé 2018-02-13 2018-02-18 2018-03-11 2018-04-15 2018-10-12 des Populations (CPRP) du Component PGRC-DU pour couvrir les régions d'Agadez et de Tahoua dans le cadre de l'extension du projet NE-PGRC-DU-48772-CS- INDV / Recrutement d'un consultant chargé de la mise à jour du plan anti- parasitaires et Gestion des Comp. 4: Contingency IDA / 53400 A posteriori Individuel Limited 8,430.00 9,505.78 Achevé 2018-02-13 2018-02-18 2018-03-11 2018-04-15 2018-10-12 Pesticides (GPP) du PGRC- Component DU pour couvrir les régions d'Agadez et de Tahoua dans le cadre de l'extension du projet NE-PGRC-DU-48773-CS- INDV / Recrutement d'un Comp. 3: Project consultant pour la mise à IDA / 53400 A posteriori Individuel Limited 15,000.00 6,866.61 Achevé 2018-03-19 2018-03-24 2018-04-14 2018-05-19 2018-11-15 Management jour du Manuel de procédure du PGRC-DU NE-PGRC-DU-58280-CS- INDV / Recrutement d'un Comp. 1: Flood Risk consultant pour la mise à IDA / 53400 A posteriori Individuel Limited 8,500.00 6,866.61 Achevé 2018-04-16 2018-04-21 2018-05-12 2018-06-16 2018-12-13 Management Investments jour de la base de données "PGRC-DU" NE-PGRC-DU-50930-CS- Sélection de CDS / Recrutement Comp. 1: Flood Risk IDA / 53400 A posteriori consultants par Direct 33,000.00 23,938.03 Achevé 2018-07-31 2018-08-10 2018-10-14 2019-04-12 consultant en Infrastructure Management Investments entente directe pour le suivi des activités du PGRC-DU NE-PGRC-DU-92303-CS- INDV / Recrutement de consultant local pour la Comp. 3: Project En cours poursuite de la mise en IDA / 53400 A posteriori Individuel Limited 20,000.00 0.00 2018-12-26 2018-12-31 2019-01-21 2019-02-25 2019-08-24 Management d'exécution place d'une base de données suivi -évaluation au sein du PGRC-DU NE-PGRC-DU-103835-CS- INDV / Recrutement d'un Comp. 1: Flood Risk En attente consultant pour l'Elaboration IDA / 53400 A posteriori Individuel Limited 17,361.00 0.00 2019-04-20 2019-04-25 2019-05-16 2019-06-20 2019-12-17 Management Investments d'exécution du cadre réglementaire et juridique des drones Page 13 NE-PGRC-DU-108338-CS- INDV / Recrutement du Comp. 1: Flood Risk En cours IDA / 53400 A posteriori Individuel Open 85,750.00 0.00 2019-04-08 2019-05-27 2019-06-17 2019-07-22 2020-01-18 Coordonnateur National du Management Investments d'exécution PGRC-DU NE-PGRC-DU-109638-CS- INDV / Recrutement d'un consultant pour réaliser les Etudes d'Impact Environnemental et Sociale EIES dans le cadre de Comp. 1: Flood Risk IDA / 53400 A posteriori Individuel Limited 17,800.00 16,668.79 Achevé 2019-04-15 2019-04-20 2019-05-11 2019-06-15 2019-12-12 réalisation des Management Investments infrastructures Socio Economiques et les ouvrages de protection des terres et d'habitation dans la Région d'Agadez NE-PGRC-DU-110369-CS- INDV / Recrutement d'un consultant pour la Préparation d'un Plan d'Action de Réinstallation Comp. 1: Flood Risk (PAR) des Personnes IDA / 53400 A posteriori Individuel Limited 14,600.00 15,883.62 Achevé 2019-04-17 2019-04-22 2019-05-13 2019-06-17 2019-12-14 Management Investments Affectées par les Travaux de construction des trois collecteurs dans l'Arrondissement Communal 1 de Niamey NE-PGRC-DU-22743-CS- INDV / ETUDES ET SUIVI Comp. 1: Flood Risk IDA / 53400 A posteriori Individuel Limited 20,000.00 0.00 Annulé 2017-10-02 2017-10-07 2017-10-28 2017-12-02 2018-05-31 CONTRÔLE ROUTE EN Management Investments TERRE SIA ADIGUA NE-PGRC-DU-22737-CS- INDV / Etude sur les Comp. 2: Capacity Building procédures opérationnelles IDA / 53400 for Urban Development and A posteriori Individuel Limited 20,000.00 0.00 Annulé 2018-01-08 2018-01-13 2018-02-03 2018-03-10 2018-09-06 pour l'alerte aux Disaster Risk Management catastrophes NE-PGRC-DU-22738-CS- INDV / AUDIT Comp. 1: Flood Risk ENVIRONNEMENTAL ET IDA / 53400 A posteriori Individuel Limited 18,000.00 0.00 Annulé 2017-10-02 2017-10-07 2017-10-28 2017-12-02 2018-05-31 Management Investments SOCIAL REHABILITATION BASSINS VERSANTS NE-PGRC-DU-22744-CS- Comp. 2: Capacity Building Sélection de CDS / IEC SAMPLAT IDA / 53400 for Urban Development and A priori consultants par Direct 144,000.00 0.00 Annulé 2018-01-16 2018-01-26 2018-04-01 2018-09-28 (POURSUITE 3 MOIS) Disaster Risk Management entente directe NE-PGRC-DU-138600-CS- INDV / Recrutement d'un Comp. 3: Project En cours IDA / 53400 A posteriori Individuel Open 36,000.00 0.00 2019-10-03 2019-11-21 2019-12-12 2020-01-16 2020-07-14 Assistant comptable pour Management d'examen servir à l'UCP de Niamey NE-PGRC-DU-138604-CS- INDV / Recrutement d'un Comp. 3: Project En cours IDA / 53400 A posteriori Individuel Open 48,000.00 0.00 2019-10-03 2019-11-21 2019-12-12 2020-01-16 2020-07-14 Coordonnateur Régional pour Management d'examen l'UEP de Niamey NE-PGRC-DU-103830-CS- CDS / Recrutement d'une Comp. 2: Capacity Building Sélection de ONG pour faciliter les IDA / 53400 for Urban Development and A posteriori consultants par Direct 60,763.89 0.00 Annulé 2019-04-22 2019-05-02 2019-07-06 2020-01-02 Activités Génératrices de Disaster Risk Management entente directe revenus au profit des groupements des femmes NE-PGRC-DU-145431-CS- INDV / Recrutement d’un consultant international individuel pour Comp. 1: Flood Risk En attente l’Organisation d’un Atelier IDA / 64130 A posteriori Individuel Limited 17,000.00 0.00 2019-11-24 2019-11-29 2019-12-20 2020-01-24 2020-07-22 Management Investments d'exécution d’Information sur les Drones et l’appui à la finalisation de la législation des drones au Niger. NE-PGRC-DU-146425-CS- INDV / Recrutement d’un consultant charge de la Réalisation d’une étude Comp. 1: Flood Risk En attente d’impact environnemental et IDA / 53400 A posteriori Individuel Limited 19,000.00 0.00 2019-11-27 2019-12-02 2019-12-23 2020-01-27 2020-07-25 Management Investments d'exécution social du sous-projet des travaux de traitement et la protection des berges du Kori de Dosso Page 14