Public Disclosure Copy The World Bank Implementation Status & Results Report Sustainable Land and Water Management (P098538) Sustainable Land and Water Management (P098538) AFRICA | Ghana | Environment & Natural Resources Global Practice | Global Environment Project | Investment Project Financing | FY 2011 | Seq No: 17 | ARCHIVED on 17-Apr-2019 | ISR36443 | Implementing Agencies: Republic of Ghana, Ministry of Finance, Ministry of Environment, Science, Technology and Innovation (MESTI) Key Dates Key Project Dates Bank Approval Date: 30-Nov-2010 Effectiveness Date: 09-Mar-2010 Planned Mid Term Review Date: 31-Oct-2013 Actual Mid-Term Review Date: 31-Jan-2014 Original Closing Date: 30-Nov-2020 Revised Closing Date: 30-Nov-2020 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) Project Development Objective is to (a) demonstrate improved sustainable land and water management practices aimed atreducinglanddegradation and enhancing maintenance of biodiversity in selected micro-watersheds, and (b) strengthen spatial planningforidentification of linked watershed investments in the Northern Savannah region of Ghana. Has the Project Development Objective been changed since Board Approval of the Project Objective? Yes Board Approved Revised Global Environmental Objective (If project is formally restructured)HRPDODELs To expand the area under sustainable land and water management practices in selected watersheds. Components Table Name Capacity Building for integrated spatial planning:(Cost $0.94 M) Land and Water Management:(Cost $26.59 M) Project Management and Coordination:(Cost $2.14 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Moderate Moderate Implementation Status and Key Decisions This is a multi-sectoral project implemented across four sectors i.e. Environment, Forestry/ Wildlife, Agriculture and Local Government and coordinated by the Ministry of Environment, Science, Technology and Innovation. The governance structures at all levels to facilitate effective 4/17/2019 Page 1 of 9 Public Disclosure Copy The World Bank Implementation Status & Results Report Sustainable Land and Water Management (P098538) project implementation [Project Steering Committee (at the National Level), Local Steering Committee, Technical Coordination Office (at the Regional Level), District Watershed Planning Teams, Community Watershed Management Teams, Community Resource Management Committees, CREMA Executive Committees] are functioning well. Project overall performance is Moderately Satisfactory. As per March 2019 IS mission, the project overall continues to demonstrate good progress on implementation of the core SLWM activities and continues to show an increasing demand for adoption of SLM practices. Key achievements in 2018 include:  A total of 247 communities, about 27,011 farmers, in the 12 project districts undertook watershed planning exercises, of which 36 communities have completed the plans for implementation in 2019.  65 Village Loan and Saving Associations (VLSA) established and 50 boxes and 1500 passbooks were supplied to new VSLA groups, as a result, 22 VSLA groups in 19 communities in 3 Districts have saved an amount of GHS 60,311.30.  Payment for Environment Services (PES) pilots showed encouraging initial results on seedling survival and many farmers replacing (at their own cost) the seedlings that have died. PES is being piloted in 24 communities.  Activities for the formation and establishment of CREMAs (covering 600,995ha in over 7 districts) in the Western Corridor of the three northern regions have been completed and a corridor-wide management plan encompassing the six CREMAs with specific action plans has been prepared. The following key issues remain valid :  Provide the relevant documents to the WB, for the completion of the final negotiation stages for CREMA establishment, which will support upgrading the rating.  Mapping of the overall project sites by communities remains pending, though the project team has advanced on detailed mapping of some data for 2016  Provide the 2018 sub-project screening results for review and feedback.  Explore design options for shea roasting oven to improve the burn efficiency of firewood in line with ensuring environmental health and safety recommendations for works contracts.  While some records are available, a systematic way of recording the impact on crop yields is needed and should be included in the future progress reports. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- Substantial Substantial Macroeconomic -- Substantial Substantial Sector Strategies and Policies -- Low Low Technical Design of Project or Program -- Moderate Moderate Institutional Capacity for Implementation and Sustainability -- Moderate Moderate Fiduciary -- Substantial Substantial Environment and Social -- Moderate Moderate Stakeholders -- Moderate Moderate Other -- -- -- Overall -- Moderate Moderate Results 4/17/2019 Page 2 of 9 Public Disclosure Copy The World Bank Implementation Status & Results Report Sustainable Land and Water Management (P098538) PDO Indicators by Objectives / Outcomes Improved sustainable land and water management practices IN00684687 ►Land area where sustainable land mgt. practices were adopted as a result of proj (Hectare(Ha), Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 10,698.70 10,992.24 15,000.00 Date 01-Jul-2010 31-Oct-2018 15-Mar-2019 30-Nov-2020 Added 3,653.64 ha in 2018. Comments: IN00684688 ►Land users adopting sustainable land mgt. practices as a result of the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 26,696.00 27,011.00 30,000.00 Date 01-Jul-2010 31-Oct-2018 15-Mar-2019 30-Nov-2020 IN00684689 ►Management Effectiveness Tracking Tool score: Gbele Resource Reserve and Sanyiga Kasena Gavara Kara (SKGK), Moagduri Wuntanluri Kuwesaasi, Bulsa Yening, Wahabu Wiasi, and Gbele-Mole corridor sites (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 45.00 0.00 0.00 80.00 Date 01-Jul-2010 31-Oct-2018 31-Oct-2018 30-Nov-2020 This indicator is tracked through the following sub-indicators (see below). An overall average score will be calculated at the end of the project. During the course of the project CREMA sites 2 and 3 were split into Comments: two (2a, 2b, 3a, 3b). The scores are maintained as before with no addition to values reported during this mission. IN00684690 Gbele Resource Reserve (Number, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 45.00 70.00 70.00 87.50 IN00684711 Sanyiga Kasena Gavara Kara Corridor Site (CREMA Site 1) (Number, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 28.00 29.00 29.00 61.70 IN00684712 Sissala Kasena Fraah Corridor Site (CREMA Site 2a) (Number, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 21.00 24.00 24.00 80.00 IN00684713 Bulkawe Corridor Site (CREMA Site 2b) (Number, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 21.00 24.00 24.00 80.00 IN00684714 Moagduri Wuntanluri Kuwesaasi Corridor Site (CREMA Site 3a) (Number, Custom Supplement) 4/17/2019 Page 3 of 9 Public Disclosure Copy The World Bank Implementation Status & Results Report Sustainable Land and Water Management (P098538) Baseline Actual (Previous) Actual (Current) End Target Value 21.00 24.00 24.00 80.00 IN00684715 Bulsa Yening Corridor Site (CREMA Site 3b) (Number, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 21.00 24.00 24.00 80.00 IN00684716 Chakali Sungmaaluu Corridor (CREMA Site 4) (Number, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 21.00 23.00 23.00 76.70 IN00684717 ►Direct project beneficiaries (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 48,498.00 57,595.00 60,000.00 Date 01-Jul-2010 31-Oct-2018 15-Mar-2019 30-Nov-2020 IN00684718 Female beneficiaries (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 55.50 55.00 40.00 Intermediate Results Indicators by Components Component 1: Capacity Building for Integrated Spatial Planning IN00684719 ►Integrated spatial development framework produced for Northern Savannah zone (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- Yes Yes Date 01-Nov-2010 31-Oct-2018 31-Oct-2018 28-Feb-2018 Activity completed. Comments: IN00684722 ►Pre-feasibility studies conducted for new large-scale multi-purpose water storage investments (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 10.00 10.00 Date 30-Jul-2010 31-Oct-2018 15-Mar-2019 28-Sep-2018 As recorded in the AM and ISR of September 2017, the pre-feasibility studies for two large dams were replaced with reconnaissance surveys for ten small dams owing to failure of SADA to deliver on results. MESTI as a lead Implementing Agency who took responsibility for the activity has completed the ten Comments: reconnaisance surveys which are currently under WB review 4/17/2019 Page 4 of 9 Public Disclosure Copy The World Bank Implementation Status & Results Report Sustainable Land and Water Management (P098538) Component 2: Land and Water Management IN00684721 ►Communities with Community Watershed Development Plans consistent with the Watershed Development Planning Manual (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 211.00 247.00 244.00 Date 30-Jul-2010 31-Oct-2018 15-Mar-2019 30-Nov-2020 IN00684723 ►Demonstration plots established in the target watersheds (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 260.00 260.00 282.00 Date 30-Jul-2010 31-Oct-2018 15-Mar-2019 15-May-2019 The target for the base project has been met but the additional financing target is proceeding on track. Comments: IN00684724 ►Targeted CREMA communities adopting management plans according to criteria defined in CREMA agreements (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 88.00 88.00 98.00 Date 30-Jul-2010 31-Oct-2018 15-Mar-2019 30-Nov-2020 IN00684725 ►A study on feasibility of sustaining SLWM activities through PES market mechanism (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- Yes Yes Date 30-Jul-2010 31-Oct-2018 31-Oct-2018 28-Feb-2018 A PES strategy is in place (study completed) and the PES mechanism is being tested on the ground. Comments: IN00684726 ►Area reforested [within target forest reserves] (Hectare(Ha), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 990.00 990.00 1,060.00 Date 01-Jul-2010 31-Oct-2018 15-Mar-2019 30-Nov-2020 IN00684727 ►Forest area brought under management plans (Hectare(Ha), Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 72,716.00 72,716.00 72,716.00 Date 01-Jul-2010 31-Oct-2018 15-Mar-2019 28-Feb-2018 IN00684728 ►Normalized Difference Vegetation Index (NDVI) in target areas (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value -0.13 0.00 0.00 -0.13 4/17/2019 Page 5 of 9 Public Disclosure Copy The World Bank Implementation Status & Results Report Sustainable Land and Water Management (P098538) Date 02-Jun-2014 31-Oct-2018 15-Mar-2019 30-Nov-2020 Current values are - 0.11 to - 0.81. This indicator is measured at the start and end of project. Comments: IN00684729 ►Community governance structures established, trained and operational (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 115.00 304.00 304.00 347.00 Date 26-Jan-2016 31-Oct-2018 15-Mar-2019 30-Nov-2020 IN00684730 - CREMA Executive Committees (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 3.00 6.00 6.00 5.00 Date 26-Jan-2016 31-Oct-2018 15-Mar-2019 30-Nov-2020 IN00684731 -Community Watershed Management Teams (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 72.00 210.00 210.00 244.00 Date 26-Jan-2016 31-Oct-2018 15-Mar-2019 30-Nov-2020 IN00684732 - CREMA Resource Management Committees (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 40.00 88.00 88.00 98.00 Date 26-Jan-2016 31-Oct-2018 15-Mar-2019 30-Nov-2020 IN00684733 ►Forest users trained (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 821.00 821.00 660.00 Date 21-Feb-2016 31-Oct-2018 15-Mar-2019 30-Nov-2020 IN00684734 Forest users trained - Female (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 262.00 262.00 330.00 Date 21-Feb-2016 31-Oct-2018 15-Mar-2019 30-Nov-2020 IN00684735 ►Beneficiaries that feel project investments reflected their needs (percentage) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 70.00 Date 21-Feb-2016 31-Oct-2018 15-Mar-2019 30-Nov-2020 Comments: This survey is pending and is expected to be done end of 2019. 4/17/2019 Page 6 of 9 Public Disclosure Copy The World Bank Implementation Status & Results Report Sustainable Land and Water Management (P098538) IN00684736 Beneficiaries that feel project inv. reflected their needs - female (number) (Number, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 8,540.00 IN00684737 Total beneficiaries - female (number) (Number, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 12,200.00 IN00684738 Total beneficiaries - male (number) (Number, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 18,300.00 IN00684739 Beneficiaries that feel project inv. reflected their needs - male (number) (Number, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 12,810.00 IN00684740 ►New areas outside protected areas managed as biodiversity-friendly (ha) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 39,107.00 600,995.71 600,995.71 417,299.00 Date 21-Feb-2016 31-Oct-2018 15-Mar-2019 30-Nov-2020 Value determined from actual GIS mapping after formation of the CREMA. Comments: IN00684741 ►Smallholder households supported in coping with the effects of climate change [in 76 communities under AF2] (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 37.00 0.00 3,000.00 Date 26-Jan-2016 31-Oct-2018 15-Mar-2019 30-Nov-2020 Data is currently being compiled and therefore target number was not reported during this mission. Comments: Component 3: Project Management and Coordination IN00684720 ►Project M&E system providing required reports and data in a timely manner (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- Yes Yes Date 01-Nov-2010 31-Oct-2018 15-Mar-2019 30-Nov-2020 4/17/2019 Page 7 of 9 Public Disclosure Copy The World Bank Implementation Status & Results Report Sustainable Land and Water Management (P098538) Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P098538 TF-17090 Effective USD 8.75 8.75 0.00 8.71 0.04 100% P098538 TF-95451 Closed USD 0.20 0.20 0.00 0.20 0.00 100% P098538 TF-97579 Closed USD 8.15 7.99 0.16 7.99 0.00 100% P098538 TF-A2276 Effective USD 12.77 12.77 0.00 7.57 5.20 59% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P098538 TF-17090 Effective 03-Nov-2014 03-Nov-2014 03-Nov-2014 28-Feb-2018 30-Nov-2020 P098538 TF-95451 Closed 22-Feb-2010 09-Mar-2010 09-Mar-2010 14-Oct-2010 14-Oct-2011 P098538 TF-97579 Closed 20-Jan-2011 20-Jan-2011 20-Jan-2011 15-Feb-2016 28-Feb-2018 P098538 TF-A2276 Effective 20-May-2016 06-Jun-2016 06-Jun-2016 30-Nov-2020 30-Nov-2020 Cumulative Disbursements 4/17/2019 Page 8 of 9 Public Disclosure Copy The World Bank Implementation Status & Results Report Sustainable Land and Water Management (P098538) Restructuring History There has been no restructuring to date. Related Project(s) P132100-Sustainable Land and Water Management ,P157595-Ghana: Second Additional Financing for Sustainable Land and Water Management Project 4/17/2019 Page 9 of 9