PROCUREMENT PLAN FOR WORKS/GOODS DISTRIBUTION EFFICIENCY PROJECT HO CHI MINH CITY POWER CORPORATION Subproject: Rehabilitation of 110kV Xa Lo substation April 04, 2017 Design and Pre-bid cost Estimate Bidding Document Bidding Process Bid Evaluation Review Contrac Contract Cost Contrac Description of Goods/ Source of Procureme by Bank t Package Comple Approv Cost estimate estimate Bid Comple Approved Bank no- t signing completi Notes Works fund nt Method (Prior/ Comple Approv Bank no- Bid No. ted date ed date (billion VND) (million date Post) ted date ed date objection issued opened ted date date objection on USD) Supply of 110kV GIS equipment, 24kV MV DEP-XL- cubicles (excluding SF6 WB fund 08 12/2016 12/2016 66.698 3.030 ICB Post 04/2017 04/2017 - 04/2017 06/2017 06/2017 06/2017 - 06/2017 01/2018 G01 cubicles), and control, for DEP months measurement and protection cubicles Supply of materials and equipment (excluding equipment procured Based on under package DEP-XL- process of Package 2 EVNHCMC 59.649 2.710 NCB G01), and construction the of the whole substation, subproject including calibration testing Based on Supervising consultant process of Package 3 for construction and EVNHCMC 1.392 0.063 NCB the equipment installation. subproject Based on process of Package 4 Work insurance EVNHCMC 0.361 0.016 NCB the subproject Based on process of Package 5 Auditing EVNHCMC 0.526 0.024 NCB the subproject Total fund from WB 66.698 3.030 Total fund from EVNHCMC 61.928 2.813 Grand Total 128.626 5.843 Note: Exchange rate 1 USD = 22,012 VND Xa Lo (En) 1/1