Public Disclosure Copy The World Bank Implementation Status & Results Report Central Highlands Connectivity Improvement Project (P159238) Central Highlands Connectivity Improvement Project (P159238) EAST ASIA AND PACIFIC | Vietnam | Transport & Digital Development Global Practice | IBRD/IDA | Investment Project Financing | FY 2017 | Seq No: 2 | ARCHIVED on 05-Apr-2018 | ISR31978 | Implementing Agencies: Socialist Republic of Vietnam, Projects Management Unit No. 2 Key Dates Key Project Dates Bank Approval Date:22-Jun-2017 Effectiveness Date:-- Planned Mid Term Review Date:30-Nov-2020 Actual Mid-Term Review Date:-- Original Closing Date:30-Jun-2023 Revised Closing Date:30-Jun-2023 Project Development Objectives Project Development Objective (from Project Appraisal Document) To improve the connectivity, safety and climate-resilience of the National Highway 19. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Road Improvements:(Cost $145.00 M) Implementation Support:(Cost $8.70 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  Satisfactory  Satisfactory Overall Implementation Progress (IP)  Satisfactory  Satisfactory Overall Risk Rating  Moderate  Moderate Implementation Status and Key Decisions The Project was approved by the Board on June 22, 2017, and the FA was signed on December 27, 2017, but the effectiveness is yet to be declared. 4/5/2018 Page 1 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Central Highlands Connectivity Improvement Project (P159238) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  Low  Low  Low Macroeconomic  Low  Low  Low Sector Strategies and Policies  Moderate  Moderate  Moderate Technical Design of Project or Program  Moderate  Moderate  Moderate Institutional Capacity for Implementation and Sustainability  Moderate  Moderate  Moderate Fiduciary  Substantial  Substantial  Substantial Environment and Social  Moderate  Substantial  Substantial Stakeholders  Moderate  Moderate  Moderate Other  Low  Low  Low Overall  Moderate  Moderate  Moderate Results Project Development Objective Indicators PHINDPDOTBL  Annual average daily traffic (AADT) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 4,950.00 4,950.00 4,950.00 6,600.00 Date 31-Mar-2017 15-Sep-2017 09-Mar-2018 30-Jun-2023 PHINDPDOTBL  Average travel time on the NH19 Corridor (Hours, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 6.00 6.00 6.00 5.00 Date 31-Mar-2017 15-Sep-2017 09-Mar-2018 30-Jun-2023 4/5/2018 Page 2 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Central Highlands Connectivity Improvement Project (P159238) PHINDPDOTBL  Number of kilometers of International Road Assessment Program (iRAP) 3-star rating or above for both cars and motorcycles on the NH19 Corridor (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 75.00 75.00 75.00 228.00 Date 31-Mar-2017 15-Sep-2017 09-Mar-2018 30-Jun-2023 PHINDPDOTBL  Kilometers of roads that are upgraded in compliance with climate/disaster resilient design standards (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 20.00 Date 31-Mar-2017 15-Sep-2017 09-Mar-2018 30-Jun-2023 Overall Comments Intermediate Results Indicators PHINDIRITBL  Roads rehabilitated, Non-rural (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 153.00 Date 31-Mar-2017 15-Sep-2017 09-Mar-2018 30-Jun-2023 4/5/2018 Page 3 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Central Highlands Connectivity Improvement Project (P159238) PHINDIRITBL  Share of citizens from affected communes who participated in consultations (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 70.00 Date 31-Mar-2017 15-Sep-2017 09-Mar-2018 30-Jun-2023 PHINDIRITBL  Share of women from affected communes who participated in consultations (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 20.00 Date 31-Mar-2017 15-Sep-2017 09-Mar-2018 30-Jun-2023 PHINDIRITBL  Manual for motorcycle lane design and specifications (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N N N Y Date 31-Mar-2017 15-Sep-2017 09-Mar-2018 30-Jun-2023 PHINDIRITBL  Guidelines for resilient road design and standards (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N N N Y Date 31-Mar-2017 15-Sep-2017 09-Mar-2018 30-Jun-2023 Overall Comments 4/5/2018 Page 4 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Central Highlands Connectivity Improvement Project (P159238) Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed Not P159238 IDA-61080 USD 140.50 140.50 0.00 0.00 148.72 0% Effective Not P159238 IDA-61090 USD 9.50 9.50 0.00 0.00 10.01 0% Effective Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date Not P159238 IDA-61080 22-Jun-2017 27-Dec-2017 -- 30-Jun-2023 30-Jun-2023 Effective Not P159238 IDA-61090 22-Jun-2017 27-Dec-2017 -- 30-Jun-2023 30-Jun-2023 Effective Cumulative Disbursements Restructuring History 4/5/2018 Page 5 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Central Highlands Connectivity Improvement Project (P159238) There has been no restructuring to date. Related Project(s) There are no related projects. 4/5/2018 Page 6 of 6 Public Disclosure Copy