IN: NATIONLA CYCLONE RISK MITIGATION PROJECT II (P144726) I. General 1. Bank’s approval Date of the procurement Plan: Original: May 21, 2015 2. Date of General Procurement Notice: May 5, 2015 3. Period covered by this procurement plan: The procurement period of project covered from Year May 5, 2015 to October 2016 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB (Goods) Above US$ 2 million All 2. NCB (Goods) Above US$ 2 million All 3. ICB (Works) Above US$ 10 million All 4. NCB (Works) Above US$ 10 million All 5. Services (non-consultant) Above US$ 2 million All 6. LIB Above US$ 30,000 Procurement Methods and Threshold Category Method of Procurement Threshold (US$ Equivalent) Goods and Non-consultant ICB >3,000,000 services LIB Wherever agreed by the Bank NCB Up to 3,000,000 (with NCB conditions) Shopping Up to 100,000 DC As per Para 3.7 of the Bank Guidelines Force Account As per Para 3.9 of Guidelines Framework Agreements As per Para 3.6 of Guidelines Works ICB >40,000,000 NCB Up to 40,000,000 (with NCB conditions) Shopping Up to 200,000 Force Account As per Para 3.9 of Guidelines DC As per Para 3.7 of Guidelines Community Participation As per Para 3.19 of Guidelines Page 1 of 4 Prior Review by the Bank. The Bank will prior review the following contracts: • Works: All contracts more than US$ 10.0 million equivalent; • Goods: All contracts more than US$ 2.0 million equivalent; • Non-Consulting Services: All contracts more than US$ 2.0 million equivalent; The PMU shall prior review the first contract issued by each implementing agency, if the estimate of those contracts are below the prior review threshold value. The Bank will conduct prior review for only those contract whose estimate falls in prior review threshold value. In addition, the justifications for all contracts to be issued on LIB, single-source (>US$ 30,000) or direct contracting (>US$ 30,000) basis will be subject to Banks prior review. These thresholds are for the initial 18 months period and are based on the procurement performance of the project, these thresholds will be modified. In addition, the Bank will carry out an annual ex post procurement review of the procurement falling below the prior review threshold mentioned above. All contracts below the specified prior review threshold value shall be subject to Post Procurement Review (PPR). For the avoidance of doubts, the Bank shall be entitled to conduct, at any time, independent procurement reviews of all the contracts financed under the Credit. The IA shall prepare a list of contract and submit it to the Bank for conducting PPR. The PPR will be conducted on annual basis. All contracts not covered under prior review will be subject to post review during supervision missions, and/or review by consultants to be appointed by the by Bank. 2. Pre-qualification. Not applicable 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable 4. Reference to Project Operational/Procurement Manual: The Project Operations/Procurement Manual was prepared and agreed by the Bank to be used as guidance note while conducting project procurement. All the contracts issued under the project will follow the World Bank’s Guidelines: Bank’s “Guidelines: Procurement under IBRD Loans and IDA Credits” dated January 2011and revised in July 2014and “Guidelines: Selection and Employment of Consultants by World Bank Borrowers” dated January 2011 and revised in July 2014, In case of any inconsistency between the Project Operation/Procurement Manual, the Bank Guidelines shall prevail. 5. Any Other Special Procurement Arrangements: Procurement of goods, works and non- consulting services shall be conducted through e-procurement portal in all the participating states using Bank’s standard bidding documents. International Competitive Bidding (ICB) is the preferred method for procurement of goods, works and non-consulting services. However, it is unlikely that there will be any ICB contract. All National Competitive Bidding (NCB) shall be conducted in accordance with paragraph 3.3 and 3.4 of the Guidelines. In addition, following additional provisions as agreed with GOI task force (as amended form time to time) shall apply: Page 2 of 4 • Only the model bidding documents for NCB as agreed with the GoI Task Force (and as amended from time to time), shall be used for bidding; • Invitation to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily inter-alia giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids; • No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprise from any given State; • Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder; • For prior review contracts, extension of bid validity shall not be allowed with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by Bank only in cases of Force Majeure and circumstance beyond the control of the Purchaser/Employer); • For prior review contracts , re-bidding shall not be carried out with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank; • The system of rejecting bids outside a pre-determined margin or “bracket” of prices shall not be used in the project; • Rates contract entered into by Directorate General of Supplies and Disposal (DGS & D) will not be acceptable as a substitute for NCB procedures unless agreed with the Bank on case to case basis. Such contracts will be acceptable however, for any procurement under the Shopping procedure; • Two or three envelop system will not be used (expect when suing e-procurement system assessed and agreed by the Bank. To meet the Bank's requirements for right to audit and F&C, these clauses may be included in the Purchase Orders, in case the purchasers are directly placing the purchase orders to DGS&D rate contract holders. On the other hand, if indent is placed through DGS&D, the Purchaser has the option to sign a separate undertaking with DGS&D rate contract holder, where Bank’s right to audit and F&C clauses could be mentioned; 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness: Available in STEP. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comment 1. Competitive Methods (Firms) Above US$ 1 million All contract 2. Single Source (Firms) Above US$ 1 million All contract Page 3 of 4 3. Individual Above US$ 300,000 All contracts 4. CQS/LCS Up to US$ 300,000 All contracts 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: The implementation of component 1 (designating of Early Warning Development System) is foreseen as challenge as there are limited consulting firms in the market. M/s Telecommunications Consultant India Ltd. (TCIL) a government owned public sector has been designing EWDS system for Andhra Pradesh and Odisha under NCRMP I project. Many participating states have requested to single source designing of EWDS to TCIL as they do not have capacity to conduct selection process for such firm. NDMA suggested that while it will be an advantage to use TCIL in all the states, an option will be given to the respective states to either single source TCIL or choose competitive selection procedure to select such firms as reflected in the procurement plan in STEP. 4. Consultancy Assignments with Selection Methods and Time Schedule Available on STEP. Page 4 of 4 PROCUREMENT India : National Cyclone Risk Mitigation Project-II PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2016-08-11 2019-11-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P144726 GPN Date: Project Name: National Cyclone Risk Mitigation Project-II Loan / Credit No: IDA / 56930 Executing Agency(ies): SPIU - Relief and Rehabilitation Department, Govt. of Maharashtra WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-RRD-MAH-2620-CW-RFB Cyclone Risk Mitigation Single Stage - Two / Underground cabling works IDA / 56930 Prior Request for Bids Open - National 12,935,000.00 12,897,703.05 Signed 2017-02-01 2017-02-06 2017-03-20 2017-06-02 2017-07-07 2019-07-07 Infrastructure Envelope at Alibag - P1. IN-RRD-MAH-2621-CW-RFB Cyclone Risk Mitigation Single Stage - Two / Underground cabling work IDA / 56930 Prior Request for Bids Open - National 14,615,000.00 13,904,225.98 Signed 2017-03-01 2017-03-06 2017-04-17 2017-06-30 2017-08-04 2019-08-04 Infrastructure Envelope at Ratnagiri - P2. IN-RRD-MAH-2622-CW-RFB Cyclone Risk Mitigation Single Stage - Two / Underground cabling work IDA / 56930 Post Request for Bids Open - National 1,769,000.00 2,438,280.37 Signed 2017-03-15 2017-03-20 2017-05-01 2017-07-14 2017-08-18 2019-02-19 Infrastructure Envelope at Saatpati - P3 IN-RRD-MAH-2624-CW-RFB Cyclone Risk Mitigation Single Stage - Two / Renovation of saline IDA / 56930 Post Request for Bids Open - National 1,153,000.00 0.00 Canceled 2017-01-02 2017-01-07 2017-02-18 2017-05-03 2017-06-07 2019-06-07 Infrastructure Envelope embankment at Kokeri - P2 IN-RRD-MAH-2625-CW-RFB / Renovation of saline Cyclone Risk Mitigation Single Stage - Two IDA / 56930 Post Request for Bids Open - National 835,000.00 0.00 Canceled 2017-01-02 2017-01-07 2017-02-18 2017-05-03 2017-06-07 2019-06-07 embankment at Mora Kotha Infrastructure Envelope - P3 IN-RRD-MAH-2626-CW-RFB / Renovation of saline Cyclone Risk Mitigation Single Stage - Two IDA / 56930 Post Request for Bids Open - National 419,500.00 0.00 Canceled 2017-01-02 2017-01-07 2017-02-18 2017-05-03 2017-06-07 2019-06-07 embankment at Nandgaon Infrastructure Envelope Mazgaon- P4 IN-RRD-MAH-2627-CW-RFB / Renovation of saline Cyclone Risk Mitigation Single Stage - Two IDA / 56930 Post Request for Bids Open - National 1,774,537.00 0.00 Canceled 2017-01-02 2017-01-07 2017-02-18 2017-05-03 2017-06-07 2019-06-07 embankment at Phansapur Infrastructure Envelope Kurdus - P5 IN-RRD-MAH-2628-CW-RFB Under / Renovation of saline Cyclone Risk Mitigation Single Stage - Two IDA / 56930 Post Request for Bids Open - National 2,095,800.00 0.00 Implementati 2017-01-02 2017-01-07 2017-02-18 2017-05-03 2017-06-07 2019-06-07 embankment at Kachali Infrastructure Envelope on Pitkari - P6 IN-RRD-MAH-2629-CW-RFB / Renovation of saline Cyclone Risk Mitigation Single Stage - Two IDA / 56930 Post Request for Bids Open - National 3,490,900.00 0.00 Canceled 2017-01-02 2017-01-07 2017-02-18 2017-05-03 2017-06-07 2019-06-07 embankment at Vadhiv - Infrastructure Envelope P7 IN-RRD-MAH-2630-CW-RFB Cyclone Risk Mitigation Single Stage - Two / Construction of saline IDA / 56930 Post Request for Bids Open - National 2,174,000.00 0.00 Canceled 2017-01-02 2017-01-07 2017-02-18 2017-05-03 2017-06-07 2019-06-07 Infrastructure Envelope embankment at Panju - P8 IN-RRD-MAH-2631-CW-RFB / Construction of Cyclone Risk Mitigation Single Stage - Two IDA / 56930 Post Request for Bids Open - National 507,700.00 0.00 Canceled 2017-02-01 2017-02-06 2017-03-20 2017-06-02 2017-07-07 2019-07-07 Multipurpose Cyclone Shelter Infrastructure Envelope at Saitwade - P1 Page 1 IN-RRD-MAH-2633-CW-RFB / Construction of Multi Cyclone Risk Mitigation Single Stage - Two IDA / 56930 Post Request for Bids Open - National 507,700.00 0.00 Canceled 2017-02-01 2017-02-06 2017-03-20 2017-06-02 2017-07-07 2019-07-07 purpose Shelter at Dabhol - Infrastructure Envelope P3 IN-RRD-MAH-2637-CW-RFB / Construction of Multi Cyclone Risk Mitigation Single Stage - Two IDA / 56930 Post Request for Bids Open - National 507,700.00 0.00 Canceled 2017-02-01 2017-02-06 2017-03-20 2017-06-02 2017-07-07 2019-07-07 purpose Shelter at Infrastructure Envelope Vijaydurg - P7 IN-RRD-MAH-2639-CW-RFB / Construction of Multi Cyclone Risk Mitigation Single Stage - Two IDA / 56930 Post Request for Bids Open - National 507,700.00 0.00 Canceled 2017-02-01 2017-02-06 2017-03-20 2017-06-02 2017-07-07 2019-07-07 purpose Shelter at Achra - Infrastructure Envelope P9 IN-RRD-MAH-2640-CW-RFB / Construction of Multi Cyclone Risk Mitigation Single Stage - Two IDA / 56930 Post Request for Bids Open - National 507,700.00 0.00 Canceled 2017-02-01 2017-02-06 2017-03-20 2017-06-02 2017-07-07 2019-07-07 purpose Shelter at Kalethar Infrastructure Envelope - P10 IN-RRD-MAH-2642-CW-RFB / Construction of Multi Cyclone Risk Mitigation Single Stage - Two IDA / 56930 Post Request for Bids Open - National 507,700.00 0.00 Canceled 2017-02-01 2017-02-06 2017-03-20 2017-06-02 2017-07-07 2019-07-07 purpose cyclone shelter at Infrastructure Envelope Jamsunday - P11 IN-RRD-MAH-2623-CW-RFB / Renovation of Saline Cyclone Risk Mitigation Single Stage - Two Under IDA / 56930 Post Request for Bids Open - National 7,526,000.00 0.00 2017-01-01 2017-01-06 2017-02-17 2017-05-02 2017-06-06 2019-11-23 Embankment at Narvel Infrastructure Envelope Review Benavale - P1 IN-RRD-MAH-2635-CW-RFB / Construction of Multi Cyclone Risk Mitigation Single Stage - Two purpose Shelter at Harnai IDA / 56930 Post Request for Bids Open - National 655,214.00 0.00 Canceled 2019-02-19 2019-02-24 2019-04-07 2019-06-20 2019-07-25 2021-01-23 Infrastructure Envelope Tal Dapoli Dist Ratnagiri - P5 IN-RRD-MAH-2636-CW-RFB / Construction of Multi Cyclone Risk Mitigation Single Stage - Two purpose Shelter at Dighi IDA / 56930 Post Request for Bids Open - National 649,866.00 0.00 Canceled 2019-02-19 2019-02-24 2019-04-07 2019-06-20 2019-07-25 2021-01-23 Infrastructure Envelope Tal Shrivardhan Dist Raigad - P6 IN-RRD-MAH-2634-CW-RFB / Construction of Multi Cyclone Risk Mitigation Single Stage - Two purpose Shelter at Edvan IDA / 56930 Post Request for Bids Open - National 694,129.00 0.00 Canceled 2019-02-19 2019-02-24 2019-04-07 2019-06-20 2019-07-25 2021-01-23 Infrastructure Envelope Tal Palghar Dist Palghar - P4 IN-RRD-MAH-2638-CW-RFB / Construction of Multi Cyclone Risk Mitigation Single Stage - Two purpose Shelter at Borli Tal. IDA / 56930 Post Request for Bids Open - National 507,700.00 0.00 Canceled 2019-03-21 2019-03-26 2019-05-07 2019-07-20 2019-08-24 2021-02-22 Infrastructure Envelope Murbad District Raigad - P8 IN-RRD-MAH-2632-CW-RFB / Construction of Multi Cyclone Risk Mitigation Single Stage - Two purpose Shelter at Usarni IDA / 56930 Post Request for Bids Open - National 507,700.00 0.00 Canceled 2019-03-21 2019-03-26 2019-05-07 2019-07-20 2019-08-24 2021-02-22 Infrastructure Envelope Tal. Palghar District Palghar- P2 IN-RRD-MAH-101353-CW- RFB / Construction of Multipurpose Cyclone Shelter at Saitwade - P1 Activity IN-RRD-MAH-2631- Cyclone Risk Mitigation Single Stage - Two CW-RFB is cancelled because IDA / 56930 Post Request for Bids Open - National 507,700.00 0.00 Canceled 2019-03-07 2019-03-12 2019-04-23 2019-07-06 2019-08-10 2021-02-08 Infrastructure Envelope all the received (3) bids are non-responsive. Fresh activity (IN-RRD-MAH- 101353-CW-RFB) is created and it is a rebidding case. Page 2 IN-RRD-MAH-113949-CW- RFB / Supply and Early Warning Single Stage - Two Under IDA / 56930 Post Request for Bids Open - National 8,387,403.00 0.00 2019-06-13 2019-06-18 2019-07-30 2019-10-12 2019-11-16 2022-11-15 installation of EWDS system Dissemination Systems Envelope Review in Maharashtra. IN-RRD-MAH-101353-CW- RFB-2 / Construction of 11 Multipurpose Cyclone Shelters in Maharashtra Cyclone Risk Mitigation Single Stage - Two IDA / 56930 Post Request for Bids Open - National 6,709,897.00 0.00 Canceled 2019-06-30 2019-07-05 2019-08-16 2019-10-29 2019-12-03 2020-12-02 (Dabhol, Jamsunday, Infrastructure Envelope Vijaydurg, Kalethar, Achra, Harnai, Edvan, Dighi, Borali, Usarni & Saitawade) IN-R&RD-MAH-144739-CW- RFB / Construction of 11 MPCS in Maharashtra Under Cyclone Risk Mitigation Single Stage - Two (Achra, Dabhol, Jamsande, IDA / 56930 Post Request for Bids Open - National 6,709,897.00 0.00 Implementati 2019-11-15 2019-11-20 2020-01-01 2020-03-15 2020-04-19 2021-04-19 Infrastructure Envelope Vijaydurg, Kalethar, Harnai, on Edvan, Dighi, Borali, Saitawade & Usarani) IN-R&RD-MAH-146038-CW- RFB / Renovation of Saline Pending Cyclone Risk Mitigation Single Stage - Two Embankment at Vadhiv IDA / 56930 Post Request for Bids Open - National 2,994,144.64 0.00 Implementati 2019-11-24 2019-11-29 2020-01-10 2020-03-24 2020-04-28 2022-04-28 Infrastructure Envelope Taluka & District Palghar on Maharashtra GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-RRD-MAH-2649-GO-RFB Project Management and Request for Single Stage - One / Purchase of Engineering IDA / 56930 Post Open - National 99,000.00 0.00 Canceled 2016-11-12 2017-01-07 2017-02-06 Implementation Support Quotations Envelope Design & survey equipments IN-RRD-MAH-2651-GO-RFQ Project Management and Request for Single Stage - One / Procurement of Office IDA / 56930 Post Open - National 82,000.00 0.00 Canceled 2016-11-15 2017-01-10 2017-02-09 Implementation Support Quotations Envelope equipment IN-RRD-MAH-3348-GO-RFQ Under Project Management and Request for Single Stage - One / Procurement of office IDA / 56930 Post Open - National 60,000.00 0.00 Implementati 2016-12-20 2017-02-14 2017-08-13 Implementation Support Quotations Envelope furniture on IN-RRD-MAH-2653-GO-RFB / Supply & installation of Early Warning Open - Single Stage - Two IDA / 56930 Prior Request for Bids 4,400,000.00 0.00 Canceled 2017-09-01 2017-09-06 2017-10-18 2017-12-31 2018-02-04 2018-11-01 EWDS system in Dissemination Systems International Envelope Maharashtra. NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-RRD-MAH-2646-NC-RFQ Project Management and Request for Single Stage - One IDA / 56930 Post Open - National 20,000.00 0.00 Canceled 2017-01-07 2017-03-04 2018-03-04 / Hiring of Speed boat Implementation Support Quotations Envelope CONSULTING FIRMS Page 3 Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-RRD-MAH-2645-CS-CQS Consultant Project Management and / Engagement of Internal IDA / 56930 Post Qualification Open - National 100,000.00 6,837.37 Signed 2017-01-02 2017-01-23 2017-03-08 2017-04-07 2017-05-12 2019-10-31 Implementation Support Auditor Selection IN-RRD-MAH-3358-CS- QCBS / Selection of Project Project Management and Quality And Cost- Open - Management IDA / 56930 Prior 900,000.00 1,222,640.54 Signed 2016-11-15 2016-12-06 2017-01-19 2017-02-16 2017-03-18 2017-04-22 2017-05-27 2020-05-26 Implementation Support Based Selection International Consultant(PMC) for NCRMP- II Maharashtra IN-RRD-MAH-3362-CS- QCBS / Selection of consulting firm for providing services of Environmental Project Management and Quality And Cost- IDA / 56930 Post Open - National 250,000.00 115,148.33 Signed 2016-11-15 2016-12-06 2017-01-19 2017-02-16 2017-03-18 2017-04-22 2017-05-27 2017-11-25 and Social Impact Implementation Support Based Selection Assessment Consultancy for Saline Embankment and Underground Cabling IN-RRD-MAH-3367-CS- QCBS / Selection of consulting firm for providing Micro level DGPS (Differential Project Management and Quality And Cost- IDA / 56930 Post Open - National 300,000.00 138,999.11 Signed 2016-11-15 2016-12-06 2017-01-19 2017-02-16 2017-03-18 2017-04-22 2017-05-27 2017-08-25 Global Positioning System) Implementation Support Based Selection survey for Maharashtra State Electricity Distribution Company LTD (MSDCEL) in the state of Maharashtra. IN-RRD-MAH-271-CS-QCBS / Selection of consultating Project Management and Quality And Cost- Open - Under IDA / 56930 Post 800,000.00 0.00 2016-08-11 2016-09-01 2016-10-15 2016-11-12 2016-12-12 2017-01-16 2017-02-20 2019-08-21 Firm for providing Third Implementation Support Based Selection International Implementation Party Quality Audit (TPQA) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-R&RD-MAH-4988-CS- Project Management and CDS / Hiring of consultant IDA / 56930 Prior Direct Selection Direct 150,000.00 173,489.91 Signed 2017-02-06 2017-02-16 2017-04-22 2017-10-19 Implementation Support for EWDS Page 4