Procurement Plan Project Name Armenian Education Improvement Project ID P130182 Date 30 January 2014 Revision date/No 15 06 February 2019 USD WB financing * WB+SB co-financing SB co-financing Categories (IDA and IBRD Funds) Estimated Cost Estimated Cost Estimated Cost 1.1 Works 20,312,936 16,250,349 4,062,587 1.2 Goods 4,551,548 3,641,239 910,310 1.3 Consultancy 2,217,485 1,773,988 443,497 1 1.4 Grants 7,024,225 5,619,380 1,404,845 1.5 Training 336,460 269,168 67,292 1.6 Operating Expenses 3,010,470 2,408,376 602,094 2 2 Front-end Fee** 37500 37,500 0 Total 37,490,625 30,000,000 7,490,625 WB financing with contingencies 30,000,000 SB co-financing with contingencies 7,490,625 Total Project Cost with contingencies 37,490,625 * Any payment from categories 1.1-1.6 to be conducted by the WB financing will be divided into two equal parts: respectively from IDA and IBRD Funds. **Amount payable pursuant to Section 2.03 of Loan Agreement (LOAN NUMBER 8342-AM) in accordance with Section 2.07 (b) of the General Conditions. Works No According to the Cost Tables Bidding Document submission No-objection to the Bidding Review by WB PRIOR/ Post Contract Price by Contract WB No to Bid Evaluation Procurement Method Contract Signing Date Contract Currency Completion Date Activities No of Packages Invitation Date Document Report to WB Component 1. Enhancing the Quality of General Education Sub-component 1.2: Enriching Upper Secondary Schools 1-Aug-16 15-Oct-18 918,111,247 AMD Rehabilitation of 2 High 1.2.1_a 2 NCB Prior 18-Mar-16 25-Apr-16 28-Apr-16 25-Jul-16 Schools. 1-Aug-16 31-Jul-18 741,704,287 AMD 24-Aug-16 9-May-18 455,145,131 AMD Rehabilitation of 3 High 1.2.1_b 3 NCB Post 18-Apr-16 N/A 3-May-16 N/A 29-Aug-16 25-Oct-18 699,887,639 AMD Schools. 1-Sep-16 10-Aug-18 461,231,760 AMD 1.2.2 Rehabilitation of 7 High Schools 7 ICB Prior 11-Dec-18 14-Jan-19 1-Feb-19 Apr-19 May-19 Jul-21 Subtotal Sub-component 1.3: Strengthening Key Institutions for Monitoring Rehabilitation of NACET 1.3.1 1 NCB Post N/A N/A 26-Oct-17 N/A 26-Mar-18 15-Apr-19 309,534,835 AMD building Subtotal Total Legend: No According to the Cost Tables Activities Prior review NCB ICB SH DC DC No of Packages Procurement Method Review by WB PRIOR/ Post Bidding Document submission to WB No-objection to the Bidding Document Invitation Date WB No to Bid Evaluation Report Contract Signing Date Completion Date Contract Price by Contract Contract Currency Works No According to the Cost Tables Contract Price in USD/date of contract signing/ Activities Contract No Supplier Status Component 1. Enhancing the Quality of General Education Sub-component 1.2: Enriching Upper Secondary Schools BAGHRAMYANSHIN Contract 1,927,267 39/16 Rehabilitation of 2 High OJSC completed 1.2.1_a Schools. BAGHRAMYANSHIN Contract 1,556,959 40/16 OJSC completed JV Ukrshin OJSC – Contract in 959,534 45/16 Tchanaparh LLC implementation JV Gevorgyan and Rehabilitation of 3 High Contract in 1.2.1_b 1,474,690 Nersisyan LLC – Agat 46/16 Schools. implementation 777 LLC JV Araratshin LLC – Zet Contract in 971,648 47/16 Profil LLC implementation 1.2.2 Rehabilitation of 7 High Schools Subtotal 6,890,097 Sub-component 1.3: Strengthening Key Institutions for Monitoring Rehabilitation of NACET Contract in 1.3.1 644,287 Arpa Sevan OJSC 6/18 building implementation Subtotal 644,287 Total 7,534,384 Legend: No According to the Cost Tables Activities Prior review NCB ICB SH DC DC Contract Price in USD/date of contract signing/ Supplier Contract No Status No According to the Cost Tables Goods Bidding Document submission No-objection to the Bidding Review by WB PRIOR/ Post Contract Price by Contract WB No to Bid Evaluation Procurement Method Contract Signing Date Completion Date Activities No of Packages Invitation Date Document Report to WB Component 1. Enhancing the Quality of General Education Sub-component 1.2: Enriching Upper Secondary Schools Equipment for laboratories in High Schools /not included in the list of 1.2.1_a 1 ICB Prior 2-Dec-16 17-Feb-17 Feb-19 May-19 May-19 Aug-19 the rehabilitated schools and for 5 rehabilitated High Schools/ Furniture for laboratories in High Schools /not included in the list of 1.2.1_b 1 NCB Post N/A N/A Feb-19 N/A Apr-19 Aug-19 the rehabilitated schools and for 5 rehabilitated High Schools/ Equipment for laboratories in 7 1.2.2_a2 High Schools /for rehabilitated 1 ICB Post N/A N/A Feb-21 N/A Apr-21 Jul-21 High Schools/ Furniture for laboratories in 7 High 1.2.2_b2 Schools /for rehabilitated High 1 SH Post N/A N/A May-21 N/A May-21 Jul-21 Schools/ Equipment for laboratories for general schools and colleges 1.2.4_a 1 ICB Prior Oct-19 Oct-19 Oct-19 Jan-20 Feb-20 May-20 providing upper secondary education No According to the Cost Tables Bidding Document submission No-objection to the Bidding Review by WB PRIOR/ Post Contract Price by Contract WB No to Bid Evaluation Procurement Method Contract Signing Date Completion Date Activities No of Packages Invitation Date Document Report to WB Furniture for laboratories for general schools and colleges 1.2.4_b 1 NCB Post N/A N/A Nov-19 N/A Jan-20 May-20 providing upper secondary education Approval of designs of 5 high 1.2.5 1 SH Post N/A N/A 12-Oct-15 N/A 1-Dec-15 30-Dec-15 7,000,000 schools Printing of Educational Materials 1.2.6 1 SH Post N/A N/A May-19 N/A Jun-19 Jul-19 for Geography Subtotal Sub-component 1.3: Strengthening Key Institutions for Monitoring Equipment for NACET/office 1.3.1 1 NCB Post N/A N/A Feb-19 N/A May-19 Jun-19 equipment and servers/ 1.3.2 Furniture for NACET 1 SH Post N/A N/A Feb-19 N/A Mar-19 Apr-19 1.3.5 Equipment for Schools 3 NCB TBD Jul-19 Jul-19 Aug-19 Oct-19 Nov-19 Aug-21 Development of Educational 1.3.6 Software for Basic and High 1 ICB Post N/A N/A 2-Mar-17 N/A 12-Jun-17 11-Dec-17 180,000,000 Schools 1.3.7 Approval of design of NACET 1 SH Post N/A N/A 1-Mar-16 N/A 24-Mar-16 25-Apr-16 1,485,000 Subtotal Component 3. Project Management, Monitoring and Evaluation SH Post N/A N/A 24-Aug-16 N/A 8-Sep-16 8-Oct-16 917,000 3.1 Goods for PIU 2 SH Post N/A N/A Mar-20 N/A Mar-20 Apr-20 3.2 No According to the Cost Tables Total Subtotal Activities Office equipment for PIU Prior review NCB SH ICB DC DC Legend: 4 No of Packages SH Procurement Method Post Post Post Post Review by WB PRIOR/ Post N/A N/A N/A N/A Bidding Document submission to WB N/A N/A N/A N/A No-objection to the Bidding Document May-19 26-Jul-16 8-May-15 25-Aug-16 Invitation Date N/A N/A N/A N/A WB No to Bid Evaluation Report May-19 28-Jul-16 16-Sep-16 25-May-15 Contract Signing Date Jun-19 9-Jul-15 7-Aug-16 16-Oct-16 Completion Date Contract Price by Contract 861,800 2,622,000 7,962,750 No According to the Cost Tables Goods Contract Price in USD/date of Contract Currency contract signing/ Activities Contract No Supplier Status Component 1. Enhancing the Quality of General Education Sub-component 1.2: Enriching Upper Secondary Schools Equipment for laboratories in High Schools /not included in the list of 1.2.1_a the rehabilitated schools and for 5 rehabilitated High Schools/ Furniture for laboratories in High Schools /not included in the list of 1.2.1_b the rehabilitated schools and for 5 rehabilitated High Schools/ Equipment for laboratories in 7 1.2.2_a2 High Schools /for rehabilitated High Schools/ Furniture for laboratories in 7 High 1.2.2_b2 Schools /for rehabilitated High Schools/ Equipment for laboratories for general schools and colleges 1.2.4_a providing upper secondary education No According to the Cost Tables Contract Price in USD/date of Contract Currency contract signing/ Activities Contract No Supplier Status Furniture for laboratories for general schools and colleges 1.2.4_b providing upper secondary education Approval of designs of 5 high "Shin-Talg 1.2.5 AMD 14,495 pordzaget" Ltd. 30/15-EIP Contract completed schools Printing of Educational Materials 1.2.6 for Geography Subtotal 14,495 Sub-component 1.3: Strengthening Key Institutions for Monitoring Equipment for NACET/office 1.3.1 equipment and servers/ 1.3.2 Furniture for NACET 1.3.5 Equipment for Schools Development of Educational "Macadamian 1.3.6 Software for Basic and High AMD 372,964 AR" CJSC 10/17 Contract completed Schools "Seysmaanvtang 1.3.7 Approval of design of NACET AMD 3,089 utyun" LLC 12/16 Contract completed Subtotal 376,053 Component 3. Project Management, Monitoring and Evaluation AMD 1,931 Adamo LLC 48/16 Contract completed 3.1 Goods for PIU No According to the Cost Tables Contract Price in USD/date of Contract Currency contract signing/ Activities Contract No Supplier Status Computer AMD 16,647 3/15-EIP Contract completed Service AMD 1,809 Vega World 37/16 Contract completed 3.2 Office equipment for PIU AMD 5,535 LANS Ltd. 49/16 Contract completed Subtotal 25,922 Total 416,470 Legend: ICB NCB DC SH Prior review DC Consultancy Review by WB PRIOR/ No-objection to TORs Submission of TORs Contract signature Expected Proposal Selection Method Advertisement for Completion Date No of Packages Activities Sub Date EOI Date by WB to WB date Post Component 1. Enhancing the Quality of General Education Sub-component 1.1: Increasing Access and Quality of Preschool Education Survey on the development dynamics of 1.1.1 the children enrolled in the preschool 1 CQ Prior 15-Jun-15 19-Jun-15 26-Jun-15 27-Aug-15 3-Nov-15 30-Sep-19 micro projects institutions Engineer to assist in implementation of 1.1.2 1 IC Post 29-Dec-14 9-Feb-15 3-Apr-15 27-Apr-15 2-Jun-15 Dec-19 renovation projects Subtotal Sub-component 1.2: Enriching Upper Secondary Schools Finalization of Architectural and Technical 1.2.1 Designs for 5 high schools 1 CQ Prior 18-Feb-15 9-Mar-15 3-Apr-15 17-Apr-15 10-Aug-15 Oct-18 Development of Architectural and 5-May-16 5-Sep-16 1.2.2 Technical Designs and Author's monitoring 1 QCBS Prior 19-Feb-15 25-Mar-15 2-Apr-15 23-Dec-15 for 6 schools rehabilitation Development of Architectural and 5-May-16 5-Sep-16 1.2.3 Technical Designs and Author's monitoring 1 QCBS Prior 19-Feb-15 25-Mar-15 2-Apr-15 4-Feb-16 for 6 schools rehabilitation Development of Social and Environmental 1.2.5 1 IC Post 4-Jun-15 5-Jun-15 19-Jun-15 22-Jul-15 25-Apr-16 31-Jul-18 Management Plans of 12 High Schools Revision of EMPs for 5 schools by Armine 1.2.6 1 SSS Prior 12-Jan-16 16-Feb-16 N/A N/A 16-Feb-16 15-Apr-16 Simonyan Supervision of 5 High Schools rehabilitation 1.2.7 1 CQ Prior 28-Jul-15 21-Sep-15 17-Oct-15 2-Nov-15 1-Aug-16 15-Apr-19 works Supervision of 3 High Schools rehabilitation 1.2.8_a 1 CQ Post 1-Feb-19 Feb-19 Mar-19 Apr-19 May-19 May-21 works Review by WB PRIOR/ No-objection to TORs Submission of TORs Contract signature Expected Proposal Selection Method Advertisement for Completion Date No of Packages Activities Sub Date EOI Date by WB to WB date Post Component of 4the 1. Enhancing Supervision Quality High General Education ofrehabilitation Schools 1.2.8_b 1 CQ Post 1-Feb-19 Feb-19 Mar-19 Apr-19 May-19 Jul-21 works 1.2.9 Engineer to assist in implementation of 1 IC Post 29-Dec-14 9-Feb-15 3-Apr-15 27-Apr-15 2-Jun-15 1-Nov-16 rehabilitation projects Preliminary designs for 5 schools by 1.2.10 1 SSS Prior N/A N/A N/A N/A 26-Oct-15 5-Nov-15 Engineer League TA for development of a technical specifications for procurement of 1.2.11_a 4 IC Post 9-Dec-15 18-Dec-15 22-Dec-15 25-Feb-16 1-Jun-16 30-Sep-19 laboratory equipment and technical evaluation TA for development of a technical 1.2.11_b specifications for procurement of furniture 1 IC Post 8-Dec-16 12-Dec-16 13-Dec-16 2-Mar-17 10-Apr-17 30-Sep-19 and technical evaluation Development of Social and Environmental 1.2.13 Management Plans of 3 High Schools 1 IC Post 19-Sep-08 20-Sep-18 25-Sep-18 8-Oct-18 19-Oct-18 30-Nov-18 Development of Social and Environmental 1.2.14 Management Plans of 4 High Schools 1 IC Post 19-Sep-08 2-Oct-18 3-Oct-18 15-Oct-18 23-Oct-18 30-Nov-18 Subtotal Sub-component 1.3: Strengthening Key Institutions for Monitoring Integration of Educational Management 1.3.1 1 SSS Prior 13-Jul-16 21-Jul-16 N/A N/A 1-Aug-16 10-Feb-17 Information Systems Technical assistance for strengthening of 1.3.2 1 CQ Post 19-Apr-18 1-Jun-18 6-Jun-18 9-Jul-18 1-Oct-18 30-Jun-19 NaCET capacity Development of Architectural and 1.3.3 Technical Design and Author's monitoring 1 CQ Post 5-Feb-15 16-Feb-15 13-Apr-15 27-Apr-15 27-Oct-15 15-Apr-19 for NACET building rehabilitation Review by WB PRIOR/ No-objection to TORs Submission of TORs Contract signature Expected Proposal Selection Method Advertisement for Completion Date No of Packages Activities Sub Date EOI Date by WB to WB date Post Component 1. Enhancing Supervision the Quality of NACET of General rehabilitation Education works 1.3.4 1 CQ Prior 28-Jul-15 21-Sep-15 17-Oct-15 2-Nov-15 1-Aug-16 15-Apr-19 Development of Social and Environmental 1.3.5 1 IC Post 4-Jun-15 5-Jun-15 19-Jun-15 22-Jul-15 25-Apr-16 31-Jul-18 Management Plans of NACET Needs Assessment of Teaching and Non- teaching Staff of Educational Institutions for the Integration of ICT into the Teaching 1.3.6 1 CQ Prior 13-Apr-16 14-Apr-16 21-Apr-16 5-May-16 23-Nov-16 14-Jul-17 and Learning as well as Administrative Processes & Development of Training Modules and Training of Trainers Subtotal Subcomponent 1.4: Supporting further improvements in the quality of education through Curriculum Revisions Needs Assessment Study for Reviewing 1.4.1 General Education State Standards, 1 CQ Post 5-Mar-15 30-Apr-15 7-May-15 31-Aug-15 19-Oct-15 29-Feb-16 Curriculum and Syllabi Working Group on Reviewing General 1.4.2 12 IC Post 10-Nov-15 9-Jan-16 20-Jan-16 12-Feb-16 8-Apr-16 8-Oct-16 Education Curriculum and State standard TA for Reviewing State and Subject 1.4.4 1 IC Post 10-Nov-15 9-Jan-16 20-Jan-16 5-Feb-16 27-Apr-16 31-Oct-16 Standards and Syllabi for Main Subjects Study and Evaluation of the Project including High school attendance 1.4.5 1 CQ Post Dec-20 Dec-20 Dec-20 Jan-21 Jan-21 Aug-21 component and study of CIF grant effectiveness 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 National Consultant for Revision of Subject 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 Standards and Curricula for General 1.4.7 Secondary Education in the Context of General Education State Program /Armenian Language and Literature/ Review by WB PRIOR/ No-objection to TORs Submission of TORs Contract signature Expected Proposal Selection Method Advertisement for Completion Date No of Packages Activities Sub Date EOI Date by WB to WB date National Consultant for Revision of Subject Post Standards and Curricula for General Component 1. Enhancing the Quality of General Education1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 1.4.7 Secondary Education in the Context of General Education State Program 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 /Armenian Language and Literature/ 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 National Consultant for Revision of Subject 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 Standards and Curricula for General 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 1.4.8 Secondary Education in the Context of 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 General Education State Program /Social 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 Sciences/ 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 National Consultant for Revision of Subject 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 Standards and Curricula for General 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 1.4.9 Secondary Education in the Context of 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 General Education State Program /Foreign 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 Languages/ 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 National Consultant for Revision of Subject 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 Standards and Curricula for General 1.4.10 Secondary Education in the Context of General Education State Program /Arts/ 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 National Consultant for Revision of Subject 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 Standards and Curricula for General 1.4.11 Secondary Education in the Context of General Education State Program 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 /Technology/ Review by WB PRIOR/ No-objection to TORs Submission of TORs Contract signature Expected Proposal Selection Method Advertisement for Completion Date No of Packages Activities Sub Date EOI Date by WB to WB date Post Component 1. Enhancing National the Quality Consultant of General for Revision Education of Subject 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 Standards and Curricula for General Secondary Education in the Context of 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 1.4.12 General Education State Program /Physical 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 Training, Military Preparation and Safety 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 Activities/ 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 TA by International Consultant for Revision of Subject Standards and Curricula for 1.4.13 General Secondary Education in the 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 Context of General Education State Program /Social Sciences/ TA by International Consultant for Revision of Subject Standards and Curricula for 1.4.14 General Secondary Education in the 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 Context of General Education State Program /Foreign Languages/ TA by International Consultant for Revision of Subject Standards and Curricula for 1.4.15 General Secondary Education in the 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 Context of General Education State Program /Arts & Technology/ Review by WB PRIOR/ No-objection to TORs Submission of TORs Contract signature Expected Proposal Selection Method Advertisement for Completion Date No of Packages Activities Sub Date EOI Date by WB to WB date Post Component 1. Enhancing the Quality of General Education TA by International Consultant for Revision of Subject Standards and Curricula for General Secondary Education in the 1.4.16 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 Context of General Education State Program /Physical Training, Military Preparation and Safety Activities/ TA for 6 Subject Areas by International Consultant for Revision of Subject Standards and Curricula for General 1.4.17 Secondary Education in the Context of 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 General Education State Program /development of methodological issues and training modules/ TA by International Consultant for Gender 1.4.18 1 IC Post Feb-19 Feb-19 Mar-19 Mar-19 May-19 Mar-21 Issues for 6 Subject Areas Subtotal Component 2. Supporting tertiary education through Mainstreaming the Competitive Innovation Fund 1 IC Post 3-Jun-15 4-Jul-15 12-Aug-15 13-Nov-15 1-Dec-15 30-Dec-15 Evaluation of CIF Grant Proposals 1 IC Post 3-Jun-15 4-Jul-15 23-Aug-16 21-Oct-16 7-Nov-16 30-Dec-16 Evaluation of CIF Grant Proposals under the 2 IC Post Feb-19 Feb-19 Mar-19 Mar-19 Apr-19 May-19 second main stage (STEM area) 2.1 Evaluation of CIF Grant Proposals under the second main stage (Economics and 2 IC Post Feb-19 Feb-19 Mar-19 Mar-19 Apr-19 May-19 jurisprudence area) Review by WB PRIOR/ No-objection to TORs Submission of TORs Contract signature Expected Proposal Selection Method Advertisement for Completion Date No of Packages 2.1 Activities Sub Date EOI Date by WB to WB date Post Component 1. Enhancing the Quality of General Education Evaluation of CIF Grant Proposals under the 4 IC Post Feb-19 Feb-19 Mar-19 Mar-19 Apr-19 May-19 second main stage (functional experts) 5 IC Post 21-Jan-16 29-Jan-16 5-Feb-16 19-Feb-16 3-Mar-16 30-Dec-17 1 IC Post 21-Jan-16 29-Jan-16 14-Nov-16 16-Dec-16 10-Jan-17 30-Dec-18 1 IC Post 1-Mar-17 14-Mar-17 15-Mar-17 22-Mar-17 13-Apr-17 30-Apr-18 2.2 Assistance to CIF Implementation 1 IC Post 1-Mar-17 14-Mar-17 15-Mar-17 22-Mar-17 13-Apr-17 31-Jan-19 1 IC Post 1-Mar-17 14-Mar-17 15-Mar-17 22-Mar-17 13-Apr-17 30-Dec-18 1 SSS Post 2-Mar-17 17-Mar-17 N/A N/A 2-May-17 31-Jul-19 1 IC Post 21-Jan-16 29-Jan-16 12-Apr-17 19-Apr-17 2-May-17 31-May-18 2.4 CIF Projects Audit 1 LCS Post 25-May-15 8-Jul-15 6-Dec-17 29-Jan-18 12-Mar-18 31-Oct-19 Subtotal Component 3. Project Management, Monitoring and Evaluation 3.1 Project audit 1 LCS Prior 17-Aug-15 10-Sep-15 12-Oct-15 21-Dec-15 4-Mar-16 15-Jun-20 3.2 Project awareness campaign 1 IC Post 27-Jan-16 29-Jan-16 9-Feb-16 19-Feb-16 3-Mar-16 30-Mar-19 3.3 Other consultancies N/A IC Post N/A N/A N/A N/A Apr-15 Sep-21 1 IC Post 12-Feb-16 26-Feb-16 26-Feb-16 15-Mar-16 8-Apr-16 1-Aug-16 1 IC Post 12-Feb-16 26-Feb-16 3-Oct-16 21-Oct-16 18-Nov-16 1-Mar-17 3.3.1 Safeguard in project 1 IC Post 12-Feb-16 26-Feb-16 6-Apr-17 18-Apr-17 3-May-17 31-Jul-18 Review by WB PRIOR/ No-objection to TORs Submission of TORs Contract signature Expected Proposal Selection Method Advertisement for Completion Date No of Packages Activities Sub Date EOI Date by WB to WB 3.3.1 Safeguard in project date Post Component 1. Enhancing the Quality of General Education 1 IC Post 12-Feb-16 26-Feb-16 16-Jul-18 30-Jul-18 2-Aug-18 30-Apr-19 27-Jul-15 27-Sep-15 3.3.2 Translators in the project 1 IC Post 25-Mar-15 1-Apr-15 3-Apr-15 11-Apr-15 2-Mar-18 7-Mar-18 3.4 Upgrading CEP official website 1 SSS Prior 10-Aug-15 11-Aug-15 N/A N/A 27-Oct-15 27-Feb-16 Subtotal Total Legend QCBS, LCS, FBS, QBS SSS CQ IC Prior Review Firms SSS Individual Consultants USD/date of contract Contract Currency Contract Price by Contract Price in Comments Consultant Contract signing/ Status Contract in 70,235,262 AMD 148,026 “Baker Tilly Armenia� CJSC implementation Contract in 8,580,000 AMD 17,653 Vram Boyajyan implementation 165,678 JV “BABAYAN-LAT Contract 95,352,840 AMD 198,890 NAKHAGITZ� LLC and completed “MODUL 2015� LLC Contract 92,334,480 AMD 192,922 completed “HGSN� LLC AMD Not signed. Contract 105,185,320 AMD 219,773 completed “Horizon-95� LLC AMD Not signed. Contract 10,216,838 AMD 21,326 Kristine Sahakyan terminated Contract 2,811,782 AMD 5,668 Armine Simonyan completed Contract in 45,687,600 AMD 94,148 "PARAPET" LTD implementation USD/date of contract Contract Currency Contract Price by Contract Price in Comments Consultant Contract signing/ Status Contract is 5,418,387 AMD 11,266 Armen Gyulkhasyan terminated Contract 7,656,998 AMD 16,266 “Engineer League� CJSC completed Contracts in 1,920,000 AMD 4,018 Multiple implementation Contract in 440,000 AMD 906 Kamo Parsamyan implementation Contract 1,800,000 AMD 3,721 Kristine Sahakyan completed Contract 2,400,000 AMD 4,955 Nora Ayvazyan completed 773,858 Contract 22,500,000 AMD 47,231 "NACET" SNTO completed Contract in 21,173,732 AMD 43,813 Harmony Fund implementation Contract in 19,224,317 AMD 39,126 “Constanta Build� LLC implementation USD/date of contract Contract Currency Contract Price by Contract Price in Comments Consultant Contract signing/ Status Contract in 4,582,080 AMD 9,619 "PARAPET" LTD implementation Contract 583,162 AMD 1,217 Kristine Sahakyan completed Agence universitaire de Contract 72,894 EUR 77,333 la Francophonie completed 218,339 Contract 37,401,600 AMD 79,051 “EV Consulting� CJSC completed Contracts 14,300,000 AMD 29,577 Multiple completed Contract 36,900 USD 36,900 Vladimir Briller completed Contract Price by Contract Contract Currency Contract Price in USD/date of contract signing/ Consultant Status Comments Contract Price by Contract Contract Currency Contract Price in USD/date of contract signing/ Consultant Status Comments Contract Price by Contract 2,720,000 5,100,000 Contract Currency AMD AMD Contract Price in USD/date of contract 5,692 10,561 signing/ 145,529 Consultant Multiple Multiple Status Contracts Contracts completed completed Comments USD/date of contract Contract Currency Contract Price by Contract Price in Comments Consultant Contract signing/ Status Contracts 1,650,000 AMD 3,377 Multiple completed Contracts 250,000 AMD 516 Arshak Ghazaryan completed Contracts 500,000 AMD 1,028 Sargis Elbakyan completed Contract in 500,000 AMD 1,028 Tigran Poghosyan implementation Contracts 600,000 AMD 1,233 Tigran Petrosyan completed Contract in 1,050,000 AMD 2,166 Arshak Ghazaryan implementation Contracts 150,000 AMD 309 Levon Grigoryan completed Contract in 11,971,596 AMD 24,903 “Grant Thornton� CJSC implementation 50,813 Contract in 13,274,881 AMD 27,053 “PHP Audit� CJSC implementation Contract in 8,611,716 AMD 17,575 Lilit Hakobyan implementation Contract is 913,000 AMD 1,911 Arevik Hovsepyan terminated Contract is 730,000 AMD 1,523 Erik Grigoryan terminated Contract is 5,600,000 AMD 11,550 Edgar Pirumyan terminated USD/date of contract Contract Currency Contract Price by Contract Price in Comments Consultant Contract signing/ Status Contract in 780,000 AMD 1,621 Anna Karapetyan implementation Contract 844,873 AMD 1,768 Suren Tiraturyan completed Contract 120,051 AMD 250 Suren Tiraturyan completed Contract 2,982,054 AMD 6,326 “Helix Consulting� LLC completed 69,577 1,423,794