The World Bank Implementation Status & Results Report Guinea Integrated Agricultural Development Project (PDAIG) (P164326) Guinea Integrated Agricultural Development Project (PDAIG) (P164326) AFRICA | Guinea | Agriculture Global Practice | IBRD/IDA | Investment Project Financing | FY 2019 | Seq No: 1 | ARCHIVED on 20-Mar-2019 | ISR35407 | Implementing Agencies: Ministry of Agriculture, Ministry of Economy and Finance Key Dates Key Project Dates Bank Approval Date: 09-Jul-2018 Effectiveness Date: 08-Mar-2019 Planned Mid Term Review Date: -- Actual Mid-Term Review Date: -- Original Closing Date: 19-Jun-2023 Revised Closing Date: 19-Jun-2023 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The project development objective is to increase agricultural productivity and market access for producers and agricultural small and medium enterprises (SMEs) in selected value chains in project areas. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Component 1: Increasing agricultural productivity:(Cost $20.37 M) Component 2: Increasing market access:(Cost $12.66 M) Component 3: Strenghening institutional capacity:(Cost $5.20 M) Component 4: Project coordination and implementation:(Cost $4.33 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO -- Satisfactory Overall Implementation Progress (IP) -- Satisfactory Overall Risk Rating -- Substantial Implementation Status and Key Decisions Beyond the Legal Opinion, the two additional Conditions of Effectiveness were: (i) The Project Steering Committee (PSC) and the Project Implementation Unit (PIU) have been duly established in accordance with the Financial Agreement, and key personnel referred namely, the director of operations, rural engineer, procurement specialist and accountant, have been duly recruited; (ii) The Project Implementation Manual (PIM) has been duly prepared and adopted, in form and substance satisfactory to the Association.The project team has reviewed all the effectiveness evidences submitted by the Recipient and found them satisfactory. The project was declared effective on March 8, 2019. 3/20/2019 Page 1 of 7 The World Bank Implementation Status & Results Report Guinea Integrated Agricultural Development Project (PDAIG) (P164326) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Substantial -- Substantial Macroeconomic Moderate -- Moderate Sector Strategies and Policies Substantial -- Substantial Technical Design of Project or Program Moderate -- Moderate Institutional Capacity for Implementation and Sustainability High -- High Fiduciary Substantial -- Substantial Environment and Social Substantial -- Substantial Stakeholders Moderate -- Moderate Other -- -- -- Overall Substantial -- Substantial Results PDO Indicators by Objectives / Outcomes Increase agricultural productivity and market access for producers and SMEs in selected value chains IN00655026 ►Percent increase in yield of targeted products achieved by project direct beneficiaries (disaggregated by product: rice, maize, potato, egg and fish) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 20.00 Date 14-Feb-2018 -- 06-Feb-2019 19-Jun-2023 IN00655027 Percent increase in yield of targeted products achieved by project direct beneficiaries (disaggregated by product: rice, maize, potato, egg and fish) - Rice (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 30.00 Date 14-Feb-2018 -- 06-Feb-2019 19-Jun-2023 IN00655028 Percent increase in yield of targeted products achieved by project direct beneficiaries (disaggregated by product: rice, maize, potato, egg and fish) - Potatoes (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target 3/20/2019 Page 2 of 7 The World Bank Implementation Status & Results Report Guinea Integrated Agricultural Development Project (PDAIG) (P164326) Value 0.00 -- 0.00 20.00 Date 14-Feb-2018 -- 06-Feb-2019 19-Jun-2023 IN00655029 Percent increase in yield of targeted products achieved by project direct beneficiaries (disaggregated by product: rice, maize, potato, egg and fish) - Maize (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 20.00 Date 14-Feb-2018 -- 06-Feb-2019 19-Jun-2023 IN00655030 Percent increase in yield of targeted products achieved by project direct beneficiaries (disaggregated by product: rice, maize, potato , egg and fish) - Egg (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 20.00 Date 15-Feb-2018 -- 06-Feb-2019 19-Jun-2023 IN00655031 Percent increase in yield of targeted products achieved by project direct beneficiaries (disaggregated by product: rice, maize, potato , egg and fish) - Fish (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 20.00 Date 15-Feb-2018 -- 06-Feb-2019 19-Jun-2023 IN00655032 ►Percent increase in volume of market sales of targeted products achieved by project direct beneficiaries (disaggregated by product: rice, maize, potato, egg, fish) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 40.00 Date 14-Feb-2018 -- 06-Feb-2019 19-Jun-2023 IN00655033 ►Farmers reached with agricultural assets or services (Number, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 150,000.00 Date 14-Feb-2018 -- 06-Feb-2019 19-Jun-2023 IN00655034 Farmers reached with agricultural assets or services - Women (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 60,000.00 Date 14-Feb-2018 -- 06-Feb-2019 19-Jun-2023 IN00655035 Farmers reached with agricultural assets or services - Youth (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target 3/20/2019 Page 3 of 7 The World Bank Implementation Status & Results Report Guinea Integrated Agricultural Development Project (PDAIG) (P164326) Value 0.00 -- 0.00 45,000.00 Date 14-Feb-2018 -- 06-Feb-2019 19-Jun-2023 Intermediate Results Indicators by Components Component 1: Increasing agricultural productivity IN00655038 ►Area provided with new/improved irrigation or drainage services (Hectare(Ha), Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 3,000.00 Date 15-Feb-2018 -- 06-Feb-2019 19-Jun-2023 IN00655040 ►Number of operational water user's associations created and/or strengthened (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 50.00 Date 15-Feb-2018 -- 06-Feb-2019 19-Jun-2023 IN00655041 ►Area under improved technologies diffused by the project (Hectare(Ha), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 50,000.00 Date 15-Feb-2018 -- 06-Feb-2019 19-Jun-2023 IN00655042 ►Number of users of improved technologies diffused by the project (disaggregated by gender) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 100,000.00 Date 15-Feb-2018 -- 06-Feb-2019 19-Jun-2023 IN00655044 Number of users of improved technologies diffused by the project - Women (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 40,000.00 Date 15-Feb-2018 -- 06-Feb-2019 19-Jun-2023 IN00655046 ►Number of agricultural technicians trained (disaggregated by gender) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 3/20/2019 Page 4 of 7 The World Bank Implementation Status & Results Report Guinea Integrated Agricultural Development Project (PDAIG) (P164326) Value 0.00 -- 0.00 1,000.00 Date 15-Feb-2018 -- 06-Feb-2019 19-Jun-2023 Component 2: Increasing market access IN00655036 ►Number of Micro-Projects financed with Matching Grant (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 900.00 Date 15-Feb-2018 -- 06-Feb-2019 19-Jun-2023 IN00655043 ►Number of Subprojects financed through the Matching Grant for Small and Medium Enterprises (SMEs) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 50.00 Date 15-Feb-2018 -- 06-Feb-2019 19-Jun-2023 IN00655045 ►Number of producers, agri-entrepreneurs and SMEs trained (disaggragated by gender and youth) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 2,000.00 Date 15-Feb-2018 -- 06-Feb-2019 19-Jun-2023 IN00655047 Number of producers, agri-entrepreneurs and SMEs trained - Youth (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 600.00 Date 15-Feb-2018 -- 06-Feb-2019 19-Jun-2023 IN00655048 Number of producers, agri-entrepreneurs and SMEs trained - Women (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 600.00 Date 12-Feb-2018 -- 06-Feb-2019 19-Jun-2023 IN00655049 Number of producers, agri-entrepreneurs and SMEs trained - SMEs (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 100.00 Date 15-Feb-2018 -- 06-Feb-2019 19-Jun-2023 3/20/2019 Page 5 of 7 The World Bank Implementation Status & Results Report Guinea Integrated Agricultural Development Project (PDAIG) (P164326) Component 3: Strengthening institutional capacity IN00655037 ►Agricultural and livestock census completed (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 15-Feb-2018 -- 06-Feb-2019 19-Jun-2023 Component 4: Project coordination and implementation IN00655039 ►Beneficiary satisfaction rate with services and assets provided by the project (by gender and youth) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 80.00 Date 14-Feb-2018 -- 06-Feb-2019 19-Jun-2023 Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P164326 IDA-62570 Effective USD 40.00 40.00 0.00 0.00 38.69 0% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P164326 IDA-62570 Effective 09-Jul-2018 11-Aug-2018 08-Mar-2019 19-Jun-2023 19-Jun-2023 Cumulative Disbursements 3/20/2019 Page 6 of 7 The World Bank Implementation Status & Results Report Guinea Integrated Agricultural Development Project (PDAIG) (P164326) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 3/20/2019 Page 7 of 7