PROCUREMENT PLAN (Textual Part) Project information: country]Sri Lanka – Water Resources Management Project-P-166865 Project Implementation agency: Ministry of Mahaweli Development and Environment Date of the Procurement Plan: 24 June, 2019 Period covered by this Procurement Plan: 24 June 2019-31 Dee. 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with the Procurement Regulations for IPF Borrowers (July 2016, revised November 2017) (“Procurement Regulations”), when approaching the national market, as agreed in the Procurement Plan tables in STEP, the country’s own procurement procedures may be used. When the Borrower, for the procurement of goods, works and non-consulting services, uses its own national open competitive procurement arrangements as set forth in Sri Lanka’s Procurement Guidelines 2006, such arrangements shall be subject to paragraph 5.4 of the Bank’s Procurement Regulations and the following conditions: 1. Only bidding documents acceptable to the Bank shall be used for all national open competitive procurement. 2. The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 3. The eligibility of bidders shall be as defined under Section III of the World Bank Procurement Regulations for IPF Borrowers (Procurement Regulations): accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. PROCUREMENT Sri Lanka : Sri Lanka Integrated Watershed and Water Resources Management Project PLAN General Information Country: Sri Lanka Bank’s Approval Date of the Original Procurement Plan: 2019-06-28 2020-03-15 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166865 GPN Date: 2019-09-23 Project Name: Sri Lanka Integrated Watershed and Water Resources Management Project Loan / Credit No: / Executing Agency(ies): Ministry of Mahaweli Development and Environment WORKS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MOMDE-117185-CW- RFQ / Refurbishment of Component 4: Project Request for Single Stage - One / Post Limited 45,311.47 38,887.42 Signed 2019-06-26 2019-06-18 2019-08-14 2019-09-04 2019-11-12 PMU office Management Quotations Envelope (IWWRMP/PP/WORKS/01) LK-MOMDE-123620-CW- RFB / Improvements to Unnichchai LB main channel Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 923,033.71 0.00 Canceled 2019-12-09 2019-12-23 2020-01-13 2020-02-12 2020-03-18 2021-03-18 from stn 0+000 to stn Improvements Envelope 13+725 (IWWRMP- 2/WORKS/ID/OCBN/04-1) LK-MOMDE-124032-CW- RFB / Improvements to Unnichchai RB main channel Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 906,741.57 0.00 Canceled 2019-11-22 2019-12-06 2019-12-27 2020-01-26 2020-03-01 2021-03-01 from stn 0+000 to stn 4+950 Improvements Envelope ( IWWRMP- 2/WORKS/ID/OCBN/04-2 ) LK-MOMDE-124217-CW- RFB / Improvements to Unnichchai RB main channel Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 887,640.45 0.00 Canceled 2019-11-22 2019-12-06 2019-12-27 2020-01-26 2020-03-01 2021-03-01 from stn 4+950 to stn Improvements Envelope 10+000 ( IWWRMP- 2/WORKS/ID/OCBN/04-3 ) LK-MOMDE-124409-CW- RFB / Rehabilititation of Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 342,696.63 0.00 Canceled 2019-11-26 2019-12-10 2019-12-31 2020-01-30 2020-03-05 2021-03-05 Panama Tank ( IWWRMP- Improvements Envelope 2/WORKS/ID/OCBN/07 ) LK-MOMDE-124659-CW- RFB / Rehabilititation of Component 2: Infrastructure Single Stage - One Peramaduwa Scheme ( / Post Request for Bids Open - National 898,876.40 0.00 Canceled 2019-12-20 2020-01-03 2020-01-24 2020-02-23 2020-03-29 2021-03-29 Improvements Envelope IWWRMP- 2/WORKS/ID/OCBN/17 ) LK-MOMDE-124666-CW- RFB / Improvements Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 950,185.39 0.00 Canceled 2019-12-20 2020-01-03 2020-01-24 2020-02-23 2020-03-29 2021-03-29 Viyadikulam Spill ( Improvements Envelope IWWRMP- 2/WORKS/ID/OCBN/18-2 ) LK-MOMDE-124667-CW- RFB / Rehabilititation of Component 2: Infrastructure Single Stage - One Abakolawewa Tank ( / Post Request for Bids Open - National 325,505.62 0.00 Canceled 2020-01-24 2020-02-07 2020-02-28 2020-03-29 2020-05-03 2021-05-03 Improvements Envelope IWWRMP- 2/WORKS/ID/OCBN/19 ) LK-MOMDE-124683-CW- RFB / Rehabilititation of Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 393,258.43 0.00 Canceled 2019-11-25 2019-12-09 2019-12-30 2020-01-29 2020-03-04 2021-03-04 Karawita tank ( IWWRMP- Improvements Envelope 2/WORKS/ID/OCBN/20 ) LK-MOMDE-125489-CW- RFB / Rehabilititation of Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 464,775.28 0.00 Canceled 2019-12-23 2020-01-06 2020-01-27 2020-02-26 2020-04-01 2021-04-01 Madiyawa Tank ( IWWRMP- Improvements Envelope 2/WORKS/ID/OCBN/23 ) LK-MOMDE-125508-CW- RFB / Rehabilititation of Component 2: Infrastructure Single Stage - One Mannankatiya Tank ( / Post Request for Bids Open - National 280,898.88 0.00 Canceled 2019-12-27 2020-01-10 2020-01-31 2020-03-01 2020-04-05 2021-04-05 Improvements Envelope IWWRMP- 2/WORKS/ID/OCBN/27 ) LK-MOMDE-125511-CW- RFB / Rehabilititation of Component 2: Infrastructure Single Stage - One Main Canal of Kimbulawana / Post Request for Bids Open - National 347,780.90 0.00 Canceled 2019-12-09 2019-12-23 2020-01-13 2020-02-12 2020-03-18 2021-03-18 Improvements Envelope Oya Scheme (LBMC) ( IWWRMP- 2/WORKS/ID/OCBN/28-1 ) LK-MOMDE-125513-CW- RFB / Rehabilititation of Component 2: Infrastructure Single Stage - One Main Canal of Kimbulawana / Post Request for Bids Open - National 262,859.69 0.00 Canceled 2019-12-09 2019-12-10 2019-12-31 2020-01-30 2020-03-05 2021-03-05 Improvements Envelope Oya Scheme (RBMC) ( IWWRMP- 2/WORKS/ID/OCBN/28-2) Page 1 LK-MOMDE-125515-CW- RFB / Rehabilititation of Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 896,067.42 0.00 Canceled 2019-12-09 2019-12-23 2020-01-13 2020-02-12 2020-03-18 2021-03-18 Maha Andara Wewa ( Improvements Envelope IWWRMP- 2/WORKS/ID/OCBN/29 ) LK-MOMDE-125834-CW- RFB / Improvement of Component 2: Infrastructure Single Stage - One Spillway Tail Canal of / Post Request for Bids Open - National 369,101.12 0.00 Canceled 2019-11-26 2019-12-10 2019-12-31 2020-01-30 2020-03-05 2021-03-05 Improvements Envelope Kotmale Dam ( IWWRMP- 2/WORKS/MASL/OCBN/101 ) LK-MOMDE-125839-CW- RFB / Repairs to gates of irrigation structures in Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 337,078.65 0.00 Canceled 2019-12-06 2019-12-20 2020-01-10 2020-02-09 2020-03-15 2021-09-16 Kalawewa Left Bank main Improvements Envelope canal (IWWRMP- 2/WORKS/MASL//OCBN/105) LK-MOMDE-125846-CW- RFB / Reconstruction of Muthuiyankaddu RB Canal - Component 2: Infrastructure Single Stage - One Muthuiyankaddu Division - / Post Request for Bids Open - National 365,168.54 0.00 Canceled 2019-11-15 2019-11-29 2019-12-20 2020-01-19 2020-02-23 2020-11-19 Improvements Envelope Package 01 (RB/Track 03) ( IWWRMP- 2/WORKS/NPC/OCBN/200-1 ) LK-MOMDE-125994-CW- RFB / Reconstruction of Muthuiyankaddu LB Canal - Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 337,078.65 0.00 Canceled 2020-02-14 2020-02-28 2020-03-20 2020-04-19 2020-05-24 2020-11-20 Muthuiyankaddu Division - Improvements Envelope (LB/Track 02) ( IWWRMP- 2/WORKS/NPC/OCBN/200-6 ) LK-MOMDE-125995-CW- RFB / Reconstruction of Muthuiyankaddu LB Canal - Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 196,629.21 0.00 Canceled 2020-02-14 2020-02-28 2020-03-20 2020-04-19 2020-05-24 2021-02-18 Muthuiyankaddu Division - Improvements Envelope (LB/Track 04) ( IWWRMP- 2/WORKS/NPC/OCBN/200-7 ) LK-MOMDE-126158-CW- RFB / Reconstruction of Muthuiyankaddu LB Canal - Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 449,438.20 0.00 Canceled 2020-10-20 2020-11-03 2020-11-24 2020-12-24 2021-01-28 2021-10-25 Muthuiyankaddu Division - Improvements Envelope (LB/Track 01) (IWWRMP- 2/WORKS/NPC/OCBN/200-9) LK-MOMDE-126330-CW- RFB / Reconstruction of Muthuiyankaddu RB Canal - Component 2: Infrastructure Single Stage - One Muthuiyankaddu Division - / Post Request for Bids Open - National 674,157.30 0.00 Canceled 2020-04-17 2020-05-01 2020-05-22 2020-06-21 2020-07-26 2021-04-22 Improvements Envelope (RB/Track 04) ( IWWRMP- 2/WORKS/NPC/OCBN/200-10 ) LK-MOMDE-126332-CW- RFB / Reconstruction of Muthuiyankaddu LB Canal - Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 561,797.75 0.00 Canceled 2020-05-17 2020-05-31 2020-06-21 2020-07-21 2020-08-25 2021-05-22 Muthuiyankaddu Division - Improvements Envelope (LB/Track 03) ( IWWRMP- 2/WORKS/NPC/OCBN/200-11) LK-MOMDE-126333-CW- RFB / Reconstruction of Muthuiyankaddu RB Canal - Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 146,067.42 0.00 Canceled 2020-05-15 2020-05-29 2020-06-19 2020-07-19 2020-08-23 2021-05-20 Muthuiyankaddu Division - Improvements Envelope (RB/Track 08) (IWWRMP- 2/WORKS/NPC/OCBN/200-12) LK-MOMDE-126337-CW- RFB / Improvements of Muthuiyankaddu RB Main Component 2: Infrastructure Single Stage - One Canal - Muthuiyankaddu / Post Request for Bids Open - National 84,269.66 0.00 Canceled 2020-05-20 2020-06-03 2020-06-24 2020-07-24 2020-08-28 2021-05-25 Improvements Envelope Division ( IWWRMP- 2/WORKS/NPC/OCBN/200-13 ) LK-MOMDE-126338-CW- RFB / Improvements of Muthuiyankaddu LB Main Component 2: Infrastructure Single Stage - One Canal - Muthuiyankaddu / Post Request for Bids Open - National 84,269.66 0.00 Canceled 2020-07-20 2020-08-03 2020-08-24 2020-09-23 2020-10-28 2021-07-25 Improvements Envelope Division ( IWWRMP- 2/WORKS/NPC/OCBN/200-14 ) LK-MOMDE-126345-CW- RFB / Rehabilitation of Component 2: Infrastructure Single Stage - One Kalmadu Scheme Headworks / Post Request for Bids Open - National 1,404,494.38 0.00 Canceled 2019-11-18 2019-12-02 2019-12-23 2020-01-22 2020-02-26 2020-11-22 Improvements Envelope ( IWWRMP- 2/WORKS/NPC/OCBN/201-1 ) LK-MOMDE-126347-CW- RFB / Rehabilitation of channel to kandawalai under Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 449,438.20 0.00 Canceled 2021-08-23 2021-09-06 2021-09-27 2021-10-27 2021-12-01 2022-08-28 RB cannel under Kalmadu Improvements Envelope Scheme ( IWWRMP- 2/WORKS/NPC/OCBN/201-2 ) Page 2 LK-MOMDE-126353-CW- RFB / Rehabilitation of channel to Puliyampokkanai Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 224,719.10 0.00 Canceled 2020-10-20 2020-11-03 2020-11-24 2020-12-24 2021-01-28 2021-10-25 under RB cannel under Improvements Envelope Kalmadu Scheme ( IWWRMP- 2/WORKS/NPC/OCBN/201-3 ) LK-MOMDE-126367-CW- RFB / Improvements of Spill Component 2: Infrastructure Single Stage - One & spilltail under Kalmadu / Post Request for Bids Open - National 337,078.65 0.00 Canceled 2020-10-16 2020-10-30 2020-11-20 2020-12-20 2021-01-24 2021-10-21 Improvements Envelope Scheme ( IWWRMP- 2/WORKS/NPC/OCBN/201-5 ) LK-MOMDE-126371-CW- RFB / Rehabilitation of akkarayan kulam channel to Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 393,258.43 0.00 Canceled 2020-02-14 2020-02-28 2020-03-20 2020-04-19 2020-05-24 2021-02-18 kannagipuram under LB Improvements Envelope cannel ( IWWRMP- 2/WORKS/NPC/OCBN/202-1 ) LK-MOMDE-126376-CW- RFB / Rehabilitation of akkarayan kulam channel to Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 393,258.43 0.00 Canceled 2020-10-16 2020-10-30 2020-11-20 2020-12-20 2021-01-24 2021-10-21 Akkarayan under LB cannel Improvements Envelope & lift irrigation ( IWWRMP- 2/WORKS/NPC/OCBN/202-2 ) LK-MOMDE-126378-CW- RFB / Rehabilitation of Component 2: Infrastructure Single Stage - One akkarayan kulam RB cannel / Post Request for Bids Open - National 449,438.20 0.00 Canceled 2020-09-28 2020-10-12 2020-11-02 2020-12-02 2021-01-06 2021-10-03 Improvements Envelope ( IWWRMP- 2/WORKS/NPC/OCBN/202-3 ) LK-MOMDE-126387-CW- RFB / Rehabilitation of Component 2: Infrastructure Single Stage - One akkarayan kulam spill & / Post Request for Bids Open - National 449,438.20 0.00 Canceled 2020-10-16 2020-10-30 2020-11-20 2020-12-20 2021-01-24 2021-10-21 Improvements Envelope spilltail channel ( IWWRMP- 2/WORKS/NPC/OCBN/202-5 ) LK-MOMDE-126390-CW- RFB / Rehabilitation of Headworks under Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 224,719.10 0.00 Canceled 2020-09-28 2020-10-12 2020-11-02 2020-12-02 2021-01-06 2021-10-03 Piramanthalaru Scheme ( Improvements Envelope IWWRMP- 2/WORKS/NPC/OCBN/203-1 ) LK-MOMDE-126391-CW- RFB / Rehabilitation of Downstream under Component 2: Infrastructure Single Stage - One Piramanthalaru Irrigation / Post Request for Bids Open - National 112,359.55 0.00 Canceled 2019-11-18 2019-12-02 2019-12-23 2020-01-22 2020-02-26 2020-11-22 Improvements Envelope Scheme (phase 01) (IWWRMP- 2/WORKS/NPC/OCBN/203-2) LK-MOMDE-126392-CW- RFB / Rehabilitation of Downstream under Component 2: Infrastructure Single Stage - One Piramanthalaru Irrigation / Post Request for Bids Open - National 112,359.55 0.00 Canceled 2020-09-21 2020-10-05 2020-10-26 2020-11-25 2020-12-30 2021-09-26 Improvements Envelope Scheme (phase 02) ( IWWRMP- 2/WORKS/NPC/OCBN/203-3 ) LK-MOMDE-126396-CW- RFB / Rehabilitation of Headworks under Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 196,629.21 0.00 Canceled 2020-10-16 2020-10-30 2020-11-20 2020-12-20 2021-01-24 2021-10-21 Kanagambikai Irrigation Improvements Envelope Scheme (IWWRMP- 2/WORKS/NPC/OCBN/204-1) LK-MOMDE-126400-CW- RFB / Rehabilitation of Downstream under Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 224,719.10 0.00 Canceled 2019-11-22 2019-12-06 2019-12-27 2020-01-26 2020-03-01 2020-11-26 Kanagambikai Scheme ( Improvements Envelope IWWRMP- 2/WORKS/NPC/OCBN/204-2 ) LK-MOMDE-126410-CW- RFB / Rehabilitation of Component 2: Infrastructure Single Stage - One Head works of / Post Request for Bids Open - National 421,348.31 0.00 Canceled 2019-12-19 2020-01-02 2020-01-23 2020-02-22 2020-03-28 2020-12-23 Improvements Envelope Kudamuruddy Tank ( IWWRMP- 2/WORKS/NPC/OCBN/206-1) LK-MOMDE-126412-CW- RFB / Rehabilitation of Downstream under Component 2: Infrastructure Single Stage - One Kudamuruddy Tank / Post Request for Bids Open - National 224,719.10 0.00 Canceled 2020-09-28 2020-10-12 2020-11-02 2020-12-02 2021-01-06 2021-10-03 Improvements Envelope Irrigation Scheme ( IWWRMP- 2/WORKS/NPC/OCBN/206-2) LK-MOMDE-126413-CW- RFB / Rehabilitation of Head works of Kariyalai Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 1,123,595.51 0.00 Canceled 2019-12-16 2019-12-30 2020-01-20 2020-02-19 2020-03-25 2020-12-20 Nagapaduwan Tank ( Improvements Envelope IWWRMP- 2/WORKS/NPC/OCBN/207-1 ) Page 3 LK-MOMDE-126416-CW- RFB / Rehabilitation of LB cannel under Kariyalai Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 365,168.54 0.00 Canceled 2020-10-20 2020-11-03 2020-11-24 2020-12-24 2021-01-28 2021-10-25 Nagapaduwan Tank Improvements Envelope (IWWRMP- 2/WORKS/NPC/OCBN/207-2) LK-MOMDE-126417-CW- RFB / Rehabilitation of RB cannel under Kariyalai Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 308,988.76 0.00 Canceled 2020-10-20 2020-11-03 2020-11-24 2020-12-24 2021-01-28 2021-10-25 Nagapaduwan Tank ( Improvements Envelope IWWRMP- 2/WORKS/NPC/OCBN/207-3 ) LK-MOMDE-126418-CW- RFB / Rehabilitation of Downstream under Vaneri Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 224,719.10 0.00 Canceled 2020-09-28 2020-10-12 2020-11-02 2020-12-02 2021-01-06 2021-10-03 kulam Irrigation Scheme ( Improvements Envelope IWWRMP- 2/WORKS/NPC/OCBN/208-1 ) LK-MOMDE-126420-CW- RFB / Rehabilitation of Component 2: Infrastructure Single Stage - One Head works of Vaneri kulam / Post Request for Bids Open - National 224,719.10 0.00 Canceled 2020-10-16 2020-10-30 2020-11-20 2020-12-20 2021-01-24 2021-10-21 Improvements Envelope ( IWWRMP- 2/WORKS/NPC/OCBN/208-2 ) LK-MOMDE-126422-CW- RFB / Rehabilitation of Dowstream infrastructure in Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 112,359.55 0.00 Canceled 2019-11-22 2019-12-06 2019-12-27 2020-01-26 2020-03-01 2020-11-26 Periyapandivirichan Kulam Improvements Envelope ( IWWRMP- 2/WORKS/NPC/OCBN/209 ) LK-MOMDE-124402-CW- RFB / Improvements to Pending Component 2: Infrastructure Single Stage - One Huruluwewa Main Canal / Post Request for Bids Open - National 687,359.55 0.00 Implementati 2020-07-02 2020-07-16 2020-08-06 2020-09-05 2020-10-10 2022-04-03 Improvements Envelope (RB) (IWWRMP- on 2/WORKS/ID/OCBN/05-2) LK-MOMDE-124642-CW- Pending RFB / Improvements to Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 522,646.07 0.00 Implementati 2020-08-31 2020-09-14 2020-10-05 2020-11-04 2020-12-09 2021-12-09 Mavilaru Headworks (LB) ( Improvements Envelope on IWWRMP- 2/WORKS/ID/OCBN/15-1 ) LK-MOMDE-124593-CW- RFB / Rehabilititation of Pending Vahanery Tank bund from Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 551,604.19 0.00 Implementati 2020-10-16 2020-10-30 2020-11-20 2020-12-20 2021-01-24 2022-01-24 Stn 0+000 to Stn 2+100 ( Improvements Envelope on IWWRMP- 2/WORKS/ID/OCBN/11-1 ) LK-MOMDE-124671-CW- RFB / Improvements of Pending Access road of Vahanery Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 775,000.00 0.00 Implementati 2020-10-20 2020-11-03 2020-11-24 2020-12-24 2021-01-28 2022-01-28 tank form Stn 0+000 to Improvements Envelope on 7+683 (Santhiyar road) ( IWWRMP- 2/WORKS/ID/OCBN/11-2 ) LK-MOMDE-124660-CW- RFB / Improvements to RB Pending Main canal from 0+000Km Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 676,471.91 0.00 Implementati 2020-08-28 2020-09-11 2020-10-02 2020-11-01 2020-12-06 2021-12-06 to 1+465Km of Viyadikulam Improvements Envelope on Scheme ( IWWRMP- 2/WORKS/ID/OCBN/18-1) LK-MOMDE-125855-CW- RFB / Reconstruction of Pending Muthuiyankaddu RB Canal - Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 634,831.46 0.00 Implementati 2020-08-16 2020-08-30 2020-09-20 2020-10-20 2020-11-24 2022-05-18 Muthuiyankaddu Division - Improvements Envelope on (RB/Track 01) ( IWWRMP- 2/WORKS/NPC/OCBN/200-4) LK-MOMDE-123606-CW- RFB / Rehabilitation of Pending Component 2: Infrastructure Single Stage - One Dewahuwa Scheme ( / Post Request for Bids Open - National 579,550.56 0.00 Implementati 2020-06-29 2020-07-13 2020-08-03 2020-09-02 2020-10-07 2021-10-07 Improvements Envelope IWWRMP- on 2/WORKS/ID/OCBN/03 ) LK-MOMDE-123594-CW- RFB / Improvement to Pending Bathalagoda main bund road Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 122,134.83 0.00 Implementati 2020-08-24 2020-09-07 2020-09-28 2020-10-28 2020-12-02 2021-09-08 ch from 0 to 1+525 ( Improvements Envelope on IWWRMP- 2/WORKS/ID/OCBN/01-2 ) LK-MOMDE-124592-CW- RFB / Rehabilititation of Pending Component 2: Infrastructure Single Stage - One Wadamunai Tank ( / Post Request for Bids Open - National 369,932.58 0.00 Implementati 2020-10-16 2020-10-30 2020-11-20 2020-12-20 2021-01-24 2022-01-24 Improvements Envelope IWWRMP- on 2/WORKS/ID/OCBN/10 ) LK-MOMDE-125854-CW- RFB / Reconstruction of Pending Muthuiyankaddu RB Canal - Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 617,977.53 0.00 Implementati 2020-08-17 2020-08-31 2020-09-21 2020-10-21 2020-11-25 2021-11-25 Muthuiyankaddu Division - Improvements Envelope on (RB/Track 05) ( IWWRMP- 2/WORKS/NPC/OCBN/200-3 ) Page 4 LK-MOMDE-125494-CW- RFB / Rehabilititation of Pending Component 2: Infrastructure Single Stage - One Muhathankulam Scheme ( / Post Request for Bids Open - National 629,213.48 0.00 Implementati 2020-09-11 2020-09-25 2020-10-16 2020-11-15 2020-12-20 2021-12-20 Improvements Envelope IWWRMP- on 2/WORKS/ID/OCBN/24 ) LK-MOMDE-125496-CW- RFB / Rehabilititation of Pending Component 2: Infrastructure Single Stage - One Arawatta tank bund ( / Post Request for Bids Open - National 169,151.69 0.00 Implementati 2020-08-31 2020-09-14 2020-10-05 2020-11-04 2020-12-09 2021-12-09 Improvements Envelope IWWRMP- on 2/WORKS/ID/OCBN/25 ) LK-MOMDE-124649-CW- Pending RFB / Improvements to Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 412,247.19 0.00 Implementati 2020-08-31 2020-09-14 2020-10-05 2020-11-04 2020-12-09 2021-12-09 Mavilaru Headworks (RB) ( Improvements Envelope on IWWRMP- 2/WORKS/ID/OCBN/15-2 ) LK-MOMDE-126382-CW- RFB / Rehabilitation of Pending Component 2: Infrastructure Single Stage - One akkarayan kulam Headworks / Post Request for Bids Open - National 842,696.63 0.00 Implementati 2021-07-16 2021-07-30 2021-08-20 2021-09-19 2021-10-24 2022-07-21 Improvements Envelope ( IWWRMP- on 2/WORKS/NPC/OCBN/202-4 ) LK-MOMDE-125838-CW- RFB / Supply and Pending Component 2: Infrastructure Single Stage - Two Installation of Gantry Crane / Post Request for Bids Open - National 1,185,393.26 0.00 Implementati 2020-09-14 2020-09-28 2020-10-19 2021-02-05 2022-02-05 Improvements Envelope for Udawalawe Dam ( on IWWRMP- 2/WORKS/MASL//OCBN/104 ) LK-MOMDE-124594-CW- Pending RFB / Rehabilititation of Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 422,191.01 0.00 Implementati 2020-07-16 2020-07-30 2020-08-20 2020-09-19 2020-10-24 2021-10-24 Hali Ela Tank ( IWWRMP- Improvements Envelope on 2/WORKS/ID/OCBN/12 ) LK-MOMDE-124408-CW- RFB / Improvements to (22 Pending km) Branch canal and Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 815,235.96 0.00 Implementati 2020-07-02 2020-07-16 2020-08-06 2020-09-05 2020-10-10 2022-04-03 structures of Illukuchenal Improvements Envelope on Unit ( IWWRMP- 2/WORKS/ID/OCBN/06 ) LK-MOMDE-125835-CW- RFB / Installation of Automated Geodetic Survey Pending Component 2: Infrastructure Single Stage - Two Systems in Kotmale & / Post Request for Bids Open - National 1,623,595.51 0.00 Implementati 2020-06-29 2020-07-13 2020-08-03 2020-11-20 2021-11-20 Improvements Envelope Randenigala Dams for Dam on Movement Monitoring ( IWWRMP- 2/WORKS/MASL//OCBN/102 ) LK-MOMDE-123596-CW- RFB / Improvement to Pending Bathalagoda Anicut Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 110,505.62 0.00 Implementati 2020-10-22 2020-11-05 2020-11-26 2020-12-26 2021-01-30 2021-11-06 (Mechanical works) ( Improvements Envelope on IWWRMP- 2/WORKS/ID/OCBN/01-3 ) LK-MOMDE-124412-CW- RFB / Rehabilitation of tank bund (1.5 km) including Rip Pending Component 2: Infrastructure Single Stage - One Rap and sluice of / Post Request for Bids Open - National 337,640.45 0.00 Implementati 2020-07-09 2020-07-23 2020-08-13 2020-09-12 2020-10-17 2022-10-17 Improvements Envelope Mahalindawewa Tank ( on IWWRMP- 2/WORKS/ID/OCBN/08 ) LK-MOMDE-124090-CW- RFB / Improvements to Pending Component 2: Infrastructure Single Stage - One Main Canal (LB) of / Post Request for Bids Open - National 647,022.47 0.00 Implementati 2020-07-02 2020-07-16 2020-08-06 2020-09-05 2020-10-10 2022-04-03 Improvements Envelope Huruluwewa Scheme ( on IWWRMP- 2/WORKS/ID/OCBN/05-1) LK-MOMDE-125831-CW- RFB / Improvements to Walawa RB 41 km Main Pending Canal from 23+400 km to Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 2,444,167.62 0.00 Implementati 2020-06-22 2020-07-06 2020-07-27 2020-08-26 2020-09-30 2023-03-29 33+420 km and 34+640km Improvements Envelope on to 40+910 km ( IWWRMP- 2/WORKS/MASL/OCBN/100-2 ) LK-MOMDE-125836-CW- RFB / Supply and Pending Component 2: Infrastructure Single Stage - Two Installation of Gantry Crane / Post Request for Bids Open - National 2,000,000.00 0.00 Implementati 2020-07-13 2020-07-27 2020-08-17 2020-12-04 2021-12-04 Improvements Envelope for Polgolla Barrage ( on IWWRMP- 2/WORKS/MASL//OCBN/103 ) LK-MOMDE-126155-CW- RFB / Reconstruction of Pending Muthuiyankaddu RB Canal - Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 196,629.21 0.00 Implementati 2020-08-21 2020-09-04 2020-09-25 2020-10-25 2020-11-29 2021-08-26 Muthuiyankaddu Division - Improvements Envelope on (RB/Track 06) (IWWRMP- 2/WORKS/NPC/OCBN/200-8) LK-MOMDE-123597-CW- RFB / Improvement to Pending Bathalagoda main CHL road Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 179,606.74 0.00 Implementati 2020-10-22 2020-11-05 2020-11-26 2020-12-26 2021-01-30 2021-11-06 from 0+000 to 2+100 km ( Improvements Envelope on IWWRMP- 2/WORKS/ID/OCBN/01-4 ) Page 5 LK-MOMDE-125529-CW- RFB / Improvements to Pending Walawa RB 41 km Main Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 2,302,251.70 0.00 Implementati 2019-11-22 2019-12-06 2019-12-27 2020-01-26 2020-03-01 2022-08-28 Canal from 0+000 km to Improvements Envelope on 17+400 km ( IWWRMP- 2/WORKS/MASL/OCBN/100-1) LK-MOMDE-124596-CW- RFB / Rehabilititation of Pending Component 2: Infrastructure Single Stage - One Pavatkulam Tank ( / Post Request for Bids Open - National 874,719.10 0.00 Implementati 2020-06-29 2020-07-13 2020-08-03 2020-09-02 2020-10-07 2021-10-07 Improvements Envelope IWWRMP- on 2/WORKS/ID/OCBN/14 ) LK-MOMDE-124595-CW- RFB / Rehabilititation of Pending Component 2: Infrastructure Single Stage - One Akathimurippu Tank ( / Post Request for Bids Open - National 1,216,044.94 0.00 Implementati 2020-06-29 2020-07-13 2020-08-03 2020-09-02 2020-10-07 2021-10-07 Improvements Envelope IWWRMP- on 2/WORKS/ID/OCBN/13 ) LK-MOMDE-125832-CW- RFB / Hydro Mechanical Pending works of Walawa RB Main Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 332,261.49 0.00 Implementati 2020-06-29 2020-07-13 2020-08-03 2020-09-02 2020-10-07 2022-04-20 Canal ( IWWRMP- Improvements Envelope on 2/WORKS/MASL/OCBN/100-3 ) LK-MOMDE-125851-CW- RFB / Reconstruction of Pending Muthuiyankaddu RB Canal - Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 325,842.70 0.00 Implementati 2020-07-13 2020-07-27 2020-08-17 2020-09-16 2020-10-21 2021-07-18 Muthuiyankaddu Division - Improvements Envelope on (RB/Track 07) ( IWWRMP- 2/WORKS/NPC/OCBN/200-2 ) LK-MOMDE-125856-CW- RFB / Reconstruction of Pending Muthuiyankaddu RB Canal - Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 831,460.67 0.00 Implementati 2020-08-24 2020-09-07 2020-09-28 2020-10-28 2020-12-02 2021-08-29 Muthuiyankaddu Division - Improvements Envelope on (RB/Track 02) ( IWWRMP- 2/WORKS/NPC/OCBN/200-5) LK-MOMDE-123602-CW- RFB / Rehabilitation of D5, Pending D7, D7 RB canals in Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 205,505.62 0.00 Implementati 2020-10-29 2020-11-12 2020-12-03 2021-01-02 2021-02-06 2022-02-06 Bathalagoda Scheme ( Improvements Envelope on IWWRMP- 2/WORKS/ID/OCBN/02-2 ) LK-MOMDE-124591-CW- Pending RFB / Rehabilititation of Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 725,466.29 0.00 Implementati 2020-06-25 2020-07-09 2020-07-30 2020-08-29 2020-10-03 2021-10-03 Nagadeepa Tank ( IWWRMP- Improvements Envelope on 2/WORKS/ID/OCBN/9 ) LK-MOMDE-123600-CW- RFB / Rehabilitation of D1, Pending Component 2: Infrastructure Single Stage - One D2, D4 canals in / Post Request for Bids Open - National 259,662.92 0.00 Implementati 2020-10-29 2020-11-12 2020-12-03 2021-01-02 2021-02-06 2022-02-06 Improvements Envelope Bathalagoda Scheme ( on IWWRMP- 2/WORKS/ID/OCBN/02-1) LK-MOMDE-125833-CW- RFB / Ecological Improvements and Marking Pending Component 2: Infrastructure Single Stage - One Reservation along Walawa / Post Request for Bids Open - National 422,232.84 0.00 Implementati 2020-06-29 2020-07-13 2020-08-03 2020-09-02 2020-10-07 2022-04-20 Improvements Envelope RB Main Canal ( IWWRMP- on 2/WORKS/MASL/OCBN/100-4 ) LK-MOMDE-125506-CW- RFB / Rehabilititation of Pending Component 2: Infrastructure Single Stage - One Waduwawala Scheme ( / Post Request for Bids Open - National 352,808.99 0.00 Implementati 2020-07-27 2020-08-10 2020-08-31 2020-09-30 2020-11-04 2021-11-04 Improvements Envelope IWWRMP- on 2/WORKS/ID/OCBN/26 ) LK-MOMDE-123572-CW- RFB / Improvements to Pending Bathalagoda Anicut & Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 397,191.01 0.00 Implementati 2020-06-22 2020-07-06 2020-07-27 2020-08-26 2020-09-30 2021-09-30 Anicut inlet CHL road from Improvements Envelope on CH0 to 3+775 (IWWRMP- 2/WORKS/ID/OCBN/01-1) LK-MOMDE-124655-CW- Pending RFB / Rehabilititation of Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 595,505.62 0.00 Implementati 2020-09-28 2020-10-12 2020-11-02 2020-12-02 2021-01-06 2022-01-06 Peramadu Tank ( IWWRMP- Improvements Envelope on 2/WORKS/ID/OCBN/16 ) LK-MOMDE-125488-CW- RFB / Rehabilititation of Pending Component 2: Infrastructure Single Stage - One Haththota Anicut Scheme ( / Post Request for Bids Open - National 600,425.69 0.00 Implementati 2020-09-10 2020-09-24 2020-10-15 2020-11-14 2020-12-19 2021-12-19 Improvements Envelope IWWRMP- on 2/WORKS/ID/OCBN/22 ) LK-MOMDE-163016-CW- RFB / Reconstruction of Pending Muthuiyankaddu LB Canal - Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 589,887.64 0.00 Implementati 2021-02-16 2021-03-02 2021-03-23 2021-04-22 2021-05-27 2022-02-21 Muthuiyankaddu Division - Improvements Envelope on (LB/Track 01) (IWWRMP- 2/WORKS/NPC/OCBN/200-9) Page 6 LK-MOMDE-163023-CW- RFB / Reconstruction of Pending Muthuiyankaddu LB Canal - Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 365,168.54 0.00 Implementati 2020-07-30 2020-08-13 2020-09-03 2020-10-03 2020-11-07 2021-08-04 Muthuiyankaddu Division - Improvements Envelope on (LB/Track 03) ( IWWRMP- 2/WORKS/NPC/OCBN/200-11) LK-MOMDE-163026-CW- RFB / Rehabilitation of Pending Headworks under Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 327,865.17 0.00 Implementati 2020-08-31 2020-09-14 2020-10-05 2020-11-04 2020-12-09 2021-09-05 Piramanthalaru Scheme Improvements Envelope on (IWWRMP- 2/WORKS/NPC/OCBN/203-1) LK-MOMDE-126401-CW- RFB / Rehabilitation of Pending Component 2: Infrastructure Single Stage - One Head works in Periyamdu / Post Request for Bids Open - National 1,765,730.34 0.00 Implementati 2021-07-01 2021-07-15 2021-08-05 2021-09-04 2021-10-09 2022-07-06 Improvements Envelope Tank ( IWWRMP- on 2/WORKS/NPC/OCBN/205 ) LK-MOMDE-163031-CW- RFB / Improvement of Pending Spillway Tail Canal and Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 842,696.63 0.00 Implementati 2020-06-29 2020-07-13 2020-08-03 2020-09-02 2020-10-07 2021-10-07 removing rock boulders in Improvements Envelope on Kotmale Dam ( IWWRMP- 2/WORKS/MASL/OCBN/101 ) LK-MOMDE-163036-CW- RFB / Repairs to gates of Pending irrigation structures in Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 449,438.20 0.00 Implementati 2020-07-06 2020-07-20 2020-08-10 2020-09-09 2020-10-14 2022-04-17 Kalawewa Left Bank main Improvements Envelope on canal (IWWRMP- 2/WORKS/MASL//OCBN/105) LK-MOMDE-163038-CW- RFB / Rehabilitation of Downstream under Pending Component 2: Infrastructure Single Stage - One Piramanthalaru Irrigation / Post Request for Bids Open - National 121,573.03 0.00 Implementati 2020-11-18 2020-12-02 2020-12-23 2021-01-22 2021-02-26 2021-11-23 Improvements Envelope Scheme (phase 01) on (IWWRMP- 2/WORKS/NPC/OCBN/203-2) LK-MOMDE-163041-CW- RFB / Improvements of Spill Pending Component 2: Infrastructure Single Stage - One & spilltail under Kalmadu / Post Request for Bids Open - National 235,955.06 0.00 Implementati 2020-11-16 2020-11-30 2020-12-21 2021-01-20 2021-02-24 2021-11-21 Improvements Envelope Scheme ( IWWRMP- on 2/WORKS/NPC/OCBN/201-5 ) LK-MOMDE-163044-CW- RFB / Rehabilitation of Pending Component 2: Infrastructure Single Stage - One Head works of / Post Request for Bids Open - National 510,000.00 0.00 Implementati 2021-02-15 2021-03-01 2021-03-22 2021-04-21 2021-05-26 2022-02-20 Improvements Envelope Kudamuruddy Tank ( on IWWRMP- 2/WORKS/NPC/OCBN/206-1) LK-MOMDE-163045-CW- RFB / Rehabilitation of Pending Component 2: Infrastructure Single Stage - One Kalmadu Scheme Headworks / Post Request for Bids Open - National 1,623,595.51 0.00 Implementati 2020-11-18 2020-12-02 2020-12-23 2021-01-22 2021-02-26 2021-11-23 Improvements Envelope (IWWRMP- on 2/WORKS/NPC/OCBN/201-1) LK-MOMDE-163046-CW- RFB / Rehabilitation of Pending Downstream under Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 240,000.00 0.00 Implementati 2020-09-21 2020-10-05 2020-10-26 2020-11-25 2020-12-30 2021-09-26 Kanagambikai Scheme Improvements Envelope on (IWWRMP- 2/WORKS/NPC/OCBN/204-2) LK-MOMDE-163051-CW- RFB / Rehablitation of tank Pending Bund (0.8km) including Rip Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 505,617.98 0.00 Implementati 2020-11-25 2020-12-09 2020-12-30 2021-01-29 2021-03-05 2021-11-30 Rap, Spill and both sluice to Improvements Envelope on Meiyankal Tank (IWWRMP- 2/WORKS/EPC/OCBN/300) LK-MOMDE-126361-CW- RFB / Rehabilitation of Pending channel to kalmadu nagar Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 393,258.43 0.00 Implementati 2021-01-10 2021-01-24 2021-02-14 2021-03-16 2021-04-20 2022-01-15 under LB cannel under Improvements Envelope on Kalmadu Scheme ( IWWRMP- 2/WORKS/NPC/OCBN/201-4 ) LK-MOMDE-163052-CW- RFB / Construction of concrete lining to LB&RB channels of Pending Chadayanthalawa anicut, Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 226,320.22 0.00 Implementati 2020-11-25 2020-12-09 2020-12-30 2021-01-29 2021-03-05 2021-11-30 Kadukkayan anicut, Improvements Envelope on Neendakari anicut, and Weeramunai anicut in Chadayanthalawa Scheme (IWWRMP- 2/WORKS/EPC/OCBN/301) LK-MOMDE-163053-CW- RFB / Reconstruction of Pending Saliyapura anicut of Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 121,629.21 0.00 Implementati 2020-11-30 2020-12-14 2021-01-04 2021-02-03 2021-03-10 2021-12-05 Paravipanchan scheme Improvements Envelope on (IWWRMP- 2/WORKS/EPC/OCBN/302) Page 7 LK-MOMDE-163054-CW- RFB / Improvements to canal System (18km) Pending Component 2: Infrastructure Single Stage - One inculuding structures of / Post Request for Bids Open - National 561,797.75 0.00 Implementati 2020-12-29 2021-01-12 2021-02-02 2021-03-04 2021-04-08 2023-04-08 Improvements Envelope Puluganawai-Kankaniyar on scheme (IWWRMP- 2/WORKS/EPC/OCBN/303) LK-MOMDE-163055-CW- RFB / Improvements of tank bund(1.5km), including Rip Pending Component 2: Infrastructure Single Stage - One Rap and Sluice Structure to / Post Request for Bids Open - National 168,539.33 0.00 Implementati 2020-11-30 2020-12-14 2021-01-04 2021-02-03 2021-03-10 2023-03-10 Improvements Envelope Puluganawai-Kankaniyar on scheme (IWWRMP- 2/WORKS/EPC/OCBN/305) LK-MOMDE-163059-CW- RFB / Rehabilitation of Head works and Pending Component 2: Infrastructure Single Stage - One Downstream infrastructure of / Post Request for Bids Open - National 510,000.00 0.00 Implementati 2021-02-16 2021-03-02 2021-03-23 2021-04-22 2021-05-27 2022-02-21 Improvements Envelope Kariyalai Nagapaduwan on Tank (IWWRMP- 2/WORKS/NPC/OCBN/207) LK-MOMDE-163064-CW- Pending RFB / Rehabilitation of Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 840,000.00 0.00 Implementati 2020-09-28 2020-10-12 2020-11-02 2020-12-02 2021-01-06 2021-10-03 Nithakaikulam (IWWRMP- Improvements Envelope on 2/WORKS/NPC/OCBN/208) LK-MOMDE-163066-CW- RFB / Immediate Pending Component 2: Infrastructure Single Stage - One improvement of upper / Post Request for Bids Open - National 786,516.85 0.00 Implementati 2021-10-04 2021-10-09 2021-11-20 2021-12-20 2022-01-24 2023-01-19 Improvements Envelope phephary of Polgolla Dam - on Phase I (IWWRMP- 2/WORKS/MASL/OCBN/106-1) GOODS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MOMDE-117380-GO-DIR / Procurement of Relevant Data and Maps for Component 1: Watershed preparation of GIS maps / and Water Resources Post Direct Selection Direct 15,151.52 0.00 Canceled 2019-08-05 2019-08-13 2019-09-17 2020-01-15 including specific geographic Planning locations/sub-watersheds (IWWRMP/PP/GOODS/01) LK-MOMDE-123586-GO-RFB / Procurement of Crew Cabs Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 475,000.00 0.00 Canceled 2020-06-09 2020-06-23 2020-08-04 2020-09-03 2020-10-08 2021-04-06 ( IWWRMP- Improvements Envelope 2/GOODS/PMU/OCBN/3 ) LK-MOMDE-124216-GO-DIR / Purchasing of GIS Maps Component 1: Watershed and Satellite Images ( / and Water Resources Post Direct Selection Direct 30,000.00 0.00 Canceled 2020-01-27 2020-02-10 2020-03-21 2020-09-17 IWWRMP- Planning 1/GOODS/PMU/OCBN/6 ) LK-MOMDE-123574-GO-RFB / Procurement of clay Pending Component 2: Infrastructure Single Stage - One grouting machines ( / Post Request for Bids Open - National 675,000.00 0.00 Implementati 2020-12-28 2021-01-11 2021-02-22 2021-03-24 2021-04-28 2022-02-22 Improvements Envelope IWWRMP- on 2/GOODS/PMU/OCBN/1 ) LK-MOMDE-123581-GO-RFB Pending / Procurement of water Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 845,000.00 0.00 Implementati 2020-09-21 2020-10-05 2020-11-16 2020-12-16 2021-01-20 2021-11-16 weeds removers ( IWWRMP- Improvements Envelope on 2/GOODS/PMU/OCBN/2 ) LK-MOMDE-124212-GO-RFB Component 1: Watershed Pending / Procurement of computer Single Stage - One / and Water Resources Post Request for Bids Open - National 60,000.00 0.00 Implementati 2021-01-28 2021-02-11 2021-03-25 2021-04-24 2021-05-29 2021-09-26 and accessories-1 ( IWWRMP- Envelope Planning on 2/GOODS/PMU/OCBN/4 ) LK-MOMDE-124214-GO-RFB Pending / Procurement of Photocopy Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 30,000.00 0.00 Implementati 2020-04-27 2020-05-11 2020-06-22 2020-07-22 2020-08-26 2020-12-24 Machines-1 ( IWWRMP- Improvements Envelope on 2/GOODS/PMU/OCBN/5 ) LK-MOMDE-124219-GO-RFB Component 1: Watershed Pending / Procurement of Office Single Stage - One / and Water Resources Post Request for Bids Open - National 30,000.00 0.00 Implementati 2021-03-01 2021-03-15 2021-04-26 2021-05-26 2021-06-30 2021-10-28 Equipments-1 ( IWWRMP- Envelope Planning on 2/GOODS/PMU/OCBN/7 ) NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 8 LK-MOMDE-157171-NC- RFQ / Conducting Asset Pending Component 4: Project Request for Single Stage - One verification and Valuation / Post Limited 2,808.99 0.00 Implementati 2020-05-30 2020-07-18 2020-08-17 Management Quotations Envelope for the PMU-IWWRMP on Assets CONSULTING FIRMS Activity Reference No. / Short List and Draft Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Request for Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Request for Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Interest Notice Proposals as Issued Proposals / Minutes Technical Proposal Proposals Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MOMDE-116917-CS- INDV / Consultancy services Consultant Component 3: Multi-sector for Preparation of TOR for / Post Qualification Limited 9,090.91 0.00 Canceled 2019-07-25 2019-08-08 2019-09-07 2019-10-12 2020-04-09 Water Resources Planning River Basin Management Selection Plan (IWWRMP/PP/CONS/30) LK-MOMDE-120102-CS- QCBS / Consultancy service Component 1: Watershed to finalize the Bid Quality And Cost- / and Water Resources Post Open - National 12,121.21 0.00 Canceled 2019-09-16 2019-10-07 2019-11-20 2019-12-18 2020-01-17 2020-02-21 2020-03-27 2021-03-27 documents for irrigation dam Based Selection Planning rehabilitation of Component 1 (IWWRMP/PP/CONS/35) LK-MOMDE-121715-CS-CQS / Consultancy Service for Component 1: Watershed Consultant preparation of Watershed / and Water Resources Post Qualification Open - National 15,151.52 0.00 Canceled 2019-07-17 2019-08-07 2019-09-20 2019-10-20 2019-11-24 2020-05-22 Management plans for Planning Selection selected area (IWWRMP/PP/CONS/36) LK-MOMDE-121716-CS-CQS / Consultancy services for Consultant Component 2: Infrastructure preparation of Risk / Post Qualification Open - National 30,303.03 0.00 Canceled 2019-09-15 2019-10-06 2019-11-19 2019-12-19 2020-01-23 2020-07-21 Improvements Assesment Selection (IWWRMP/PP/CONS/37) LK-MOMDE-125891-CS- QCBS / Consultancy service for preparation of Watershed management plan for seven Component 1: Watershed selected divisions -Nuwara Quality And Cost- Open - / and Water Resources Post 1,348,314.61 0.00 Canceled 2019-12-05 2019-12-26 2020-02-08 2020-03-07 2020-04-06 2020-05-11 2020-06-15 2021-06-15 Eliya, Badulla, Walapnae & Based Selection International Planning Kandy (Delthota, Haguranketha and Pahatha Hewaheta) (IWWRMP- 1/CS/QCBS/1) LK-MOMDE-125993-CS- QCBS / Consultancy Service for study and recommendation for back erosion of Rantambe dam spillway tail canal ,LB Component 2: Infrastructure Quality And Cost- Open - / Post 786,516.85 0.00 Canceled 2019-11-25 2019-12-16 2020-01-29 2020-02-26 2020-03-27 2020-05-01 2020-06-05 2021-06-05 erosion of Victoria dam Improvements Based Selection International spillway tail canal, Back Analysis for Victoria dam and Kotmale Dam grouting gallery inspection (IWWRMP- 2/CS/QCBS/7) LK-MOMDE-126757-CS- QCBS / Development of Component 1: Watershed Basin Management plan for Quality And Cost- / and Water Resources Post Open - National 421,348.31 0.00 Canceled 2020-05-25 2020-06-15 2020-07-29 2020-08-26 2020-09-25 2020-10-30 2020-12-04 2021-12-04 Walawa & Ma Oya Based Selection Planning including the stakeholder workshops (IWWRMP- 1/CS/QCBS/5) LK-MOMDE-126759-CS- QCBS / Consultancy service Component 1: Watershed for Expansion and Quality And Cost- / and Water Resources Post Open - National 561,797.75 0.00 Canceled 2020-10-29 2020-11-19 2021-01-02 2021-01-30 2021-03-01 2021-04-05 2021-05-10 2023-05-10 enhancement of WMS/MASL Based Selection Planning bulk water allocation model (IWWRMP-1/CS/QCBS/6) LK-MOMDE-138818-CS-CQS / Consultancy on improving reservoir capacity by Component 1: Watershed Consultant dredging sand deposits - / and Water Resources Post Qualification Open - National 112,359.55 0.00 Canceled 2020-04-01 2020-04-22 2020-06-05 2020-07-05 2020-08-09 2021-08-09 medium and minor irrigation Planning Selection tanks within the watershed (IWWRMP-1/CS/CQS/2) LK-MOMDE-138828-CS-CQS / Establishment of policy and institutional Consultant Component 2: Infrastructure arrangements for dam / Post Qualification Open - National 112,359.55 0.00 Canceled 2020-04-14 2020-05-05 2020-06-18 2020-07-18 2020-08-22 2021-08-22 Improvements safety, and water resources Selection management (IWWRMP- 2/CS/CQS/15) Page 9 LK-MOMDE-138831-CS-CQS / Consultancy service for Preparation of Environmental Social Management Consultant Framework and Component 2: Infrastructure / Post Qualification Open - National 25,280.90 0.00 Canceled 2020-12-16 2021-01-06 2021-02-19 2021-03-21 2021-04-25 2022-04-25 Environmental social Improvements Selection screening report for rehabiliate dams & canals cluster VII (IWWRMP- 2/CS/CQS/18) LK-MOMDE-138832-CS-CQS / Consultancy service for Preparation of Environmental Social Management Consultant Framework and Component 2: Infrastructure / Post Qualification Open - National 25,280.90 0.00 Canceled 2019-12-13 2020-01-03 2020-02-16 2020-03-17 2020-04-21 2021-04-21 Environmental social Improvements Selection screening report for rehabilitate dams & canals cluster VIII (IWWRMP- 2/CS/CQS/19) LK-MOMDE-138824-CS-CQS / Consultancy service for Preparation of Environmental Social Management Consultant Framework and Component 2: Infrastructure / Post Qualification Open - National 56,179.78 0.00 Canceled 2020-09-09 2020-09-30 2020-11-13 2020-12-13 2021-01-17 2021-07-16 Environmental social Improvements Selection screening report for rehabilitate dams & canals cluster IV ( IWWRMP- 2/CS/CQS/11) LK-MOMDE-138829-CS-CQS / Consultancy service for Preparation of Environmental Social Management Consultant Framework and Component 2: Infrastructure / Post Qualification Open - National 11,235.96 0.00 Canceled 2020-02-17 2020-03-09 2020-04-22 2020-05-22 2020-06-26 2021-06-26 Environmental social Improvements Selection screening report for rehabiliate dams & canals cluster V (IWWRMP- 2/CS/CQS/16) LK-MOMDE-138830-CS-CQS / Consultancy service for Preparation of Environmental Social Management Consultant Framework and Component 2: Infrastructure / Post Qualification Open - National 22,471.91 0.00 Canceled 2019-12-09 2019-12-30 2020-02-12 2020-03-13 2020-04-17 2021-04-17 Environmental social Improvements Selection screening report for rehabilitate dams & canals cluster VI (IWWRMP- 2/CS/CQS/17) LK-MOMDE-138822-CS-CQS / Consultancy service for Preparation of Environmental Social Management Consultant Framework and Component 2: Infrastructure / Post Qualification Open - National 56,179.78 0.00 Canceled 2020-02-28 2020-03-20 2020-05-03 2020-06-02 2020-07-07 2021-01-03 Environmental social Improvements Selection screening report for rehabilitate dams & canals cluster II (IWWRMP- 2/CS/CQS/9) LK-MOMDE-138835-CS-CQS / Feasibility study tocheck Consultant the possibility of diverson of Component 2: Infrastructure / Post Qualification Open - National 280,898.88 0.00 Canceled 2020-09-28 2020-10-19 2020-12-02 2021-01-01 2021-02-05 2022-02-05 Kaluganga Water to the Improvements Selection CKD area (IWWRMP- 2/CS/CQS/22) LK-MOMDE-138823-CS-CQS / Consultancy service for Preparation of Environmental Social Management Consultant Framework and Component 2: Infrastructure / Post Qualification Open - National 56,179.78 0.00 Canceled 2020-08-31 2020-09-21 2020-11-04 2020-12-04 2021-01-08 2021-07-07 Environmental social Improvements Selection screening report for rehabilitate dams & canals cluster III ( IWWRMP- 2/CS/CQS/10) LK-MOMDE-138836-CS-CQS / Preparation of guidline Consultant Component 2: Infrastructure for sustainable Dam safety / Post Qualification Open - National 11,235.96 0.00 Canceled 2020-07-30 2020-08-20 2020-10-03 2020-11-02 2020-12-07 2021-12-07 Improvements and Hydraulic Assets ( Selection IWWRMP-2/CS/CQS/23 ) LK-MOMDE-138838-CS-CQS Consultant Component 2: Infrastructure Pending / Risk assessment for all / Post Qualification Open - National 280,898.88 0.00 2020-11-01 2020-11-22 2021-01-05 2021-02-04 2021-03-11 2022-03-11 Improvements Implementation identified dams Selection LK-MOMDE-162963-CS- QCBS / Consultancy service for preparation of Mahaweli Component 1: Watershed Quality And Cost- Pending Upper Watershed / and Water Resources Post Open - National 337,078.65 0.00 2020-06-16 2020-07-07 2020-08-20 2020-09-17 2020-10-17 2020-11-21 2020-12-26 2021-12-26 Based Selection Implementation management intervention Planning plan for cluster I (IWWRMP- 1/CS/QCBS/1) Page 10 LK-MOMDE-162965-CS- QCBS / Consultancy service for preparation of Mahaweli Component 1: Watershed Quality And Cost- Pending Upper Watershed / and Water Resources Post Open - National 280,898.88 0.00 2020-10-29 2020-11-19 2021-01-02 2021-01-30 2021-03-01 2021-04-05 2021-05-10 2022-05-10 Based Selection Implementation management intervention Planning plan for cluster II (IWWRMP-1/CS/QCBS/2) LK-MOMDE-138837-CS-CQS / preparation of O & M Consultant Manuals and Emergency Component 2: Infrastructure Pending / Post Qualification Open - National 280,898.88 0.00 2021-12-01 2021-12-22 2022-02-04 2022-03-06 2022-04-10 2023-04-10 Action plans for selected Improvements Implementation Selection dams ( IWWRMP- 2/CS/CQS/24 ) LK-MOMDE-138834-CS-CQS / Feasibility Study for Construction of Pooneryn Consultant Tank and Barrages including Component 2: Infrastructure Pending / Post Qualification Open - National 252,808.99 0.00 2020-09-20 2020-10-11 2020-11-24 2020-12-24 2021-01-28 2022-01-28 Investigation, Detailed Improvements Implementation Selection Design, BD preparation, EIA and Social assessment (IWWRMP-2\/CS/CQS/21) LK-MOMDE-162967-CS- QCBS / Consultancy service for preparation of Mahaweli Component 1: Watershed Quality And Cost- Pending Upper Watershed / and Water Resources Post Open - National 224,719.10 0.00 2021-02-01 2021-02-22 2021-04-07 2021-05-05 2021-06-04 2021-07-09 2021-08-13 2022-08-13 Based Selection Implementation management intervention Planning plan for cluster III (IWWRMP-1/CS/QCBS/3) LK-MOMDE-138820-CS-CQS / Development of Component 1: Watershed Consultant Pending Groundwater Data & / and Water Resources Post Qualification Open - National 56,179.78 0.00 2020-07-01 2020-07-22 2020-09-04 2020-10-04 2020-11-08 2021-11-08 Implementation Information System for WRB Planning Selection (IWWRMP-1/CS/CQS/4) LK-MOMDE-138825-CS-CQS / Consultancy Service for Consultant preparation of Livelihood Component 2: Infrastructure Pending / Post Qualification Open - National 56,179.78 0.00 2020-09-06 2020-09-27 2020-11-10 2020-12-10 2021-01-14 2021-07-13 Support Assistance Plan Improvements Implementation Selection (LSA) ( IWWRMP- 2/CS/CQS/12 ) LK-MOMDE-162968-CS- QCBS / Consultancy Service development of best practices Component 1: Watershed Quality And Cost- Pending for water management using / and Water Resources Post Open - National 56,179.78 0.00 2020-09-29 2020-10-20 2020-12-03 2020-12-31 2021-01-30 2021-03-06 2021-04-10 2021-10-07 Based Selection Implementation native , herbal, economical Planning important species (IWWRMP- 1/CS/QCBS/4) LK-MOMDE-138819-CS-CQS / Development Groundwater Component 1: Watershed Consultant management plans & legal Pending / and Water Resources Post Qualification Open - National 140,449.44 0.00 2020-09-25 2020-10-16 2020-11-29 2020-12-29 2021-02-02 2022-02-02 framework for basins and Implementation Planning Selection national level (WRB) (IWWRMP-1/CS/CQS/3) LK-MOMDE-121717-CS-CQS Consultant / Preparation of Management Component 4: Project Pending / Post Qualification Open - National 12,121.21 0.00 2020-10-01 2020-10-22 2020-12-05 2021-01-04 2021-02-08 2021-08-07 Information System Management Implementation Selection (IWWRMP/PP/CONS/15) LK-MOMDE-138839-CS-CQS / Consultancy Service for Consultant Component 4: Project Pending Development for Project / Post Qualification Open - National 14,044.94 0.00 2020-10-15 2020-11-05 2020-12-19 2021-01-18 2021-02-22 2021-05-23 Management Implementation Website (IWWRMP- Selection 4/CS/CQS/26) LK-MOMDE-138827-CS-CQS / Consultancy service for Consultant design of Bridge at 4+000 Component 2: Infrastructure Pending / Post Qualification Open - National 28,089.89 0.00 2020-10-20 2020-11-10 2020-12-24 2021-01-23 2021-02-27 2021-08-26 km of walawa RB main Improvements Implementation Selection canal (IWWRMP- 2\/CS/CQS/14) LK-MOMDE-138821-CS-CQS / Consultancy service for Preparation of Environmental Social Management Consultant Component 2: Infrastructure Pending Framework and / Post Qualification Open - National 56,179.78 0.00 2020-08-21 2020-09-11 2020-10-25 2020-11-24 2020-12-29 2021-06-27 Improvements Implementation Environmental social Selection screening report for rehabiliate dams & canals EPC LK-MOMDE-138826-CS-CQS / Consultancy Service for inspection, identification of Consultant defects and repair works of Component 2: Infrastructure Pending / Post Qualification Open - National 84,269.66 0.00 2020-09-20 2020-10-11 2020-11-24 2020-12-24 2021-01-28 2021-07-27 syphone from 3+950 km to Improvements Implementation Selection 4+330 km of walawa RB main canal (IWWRMP- 2/CS/CQS/13) Page 11 LK-MOMDE-162972-CS- QCBS / Consultancy service for development for Component 1: Watershed Quality And Cost- Pending integrated design proposal / and Water Resources Post Open - National 56,179.78 0.00 2020-09-29 2020-10-20 2020-12-03 2020-12-31 2021-01-30 2021-03-06 2021-04-10 2022-04-10 Based Selection Implementation for upper periphary of Planning Polgolla reservoir (IWWRMP- 1/CS/QCBS/5) LK-MOMDE-118633-CS- QCBS / Consultancy Service for study and recommendation for back erosion of Rantambe dam spillway tail canal ,LB Component 2: Infrastructure Quality And Cost- Open - Pending / Prior 1,202,448.09 0.00 2020-11-19 2020-12-10 2021-01-23 2021-02-20 2021-03-22 2021-04-26 2021-05-31 2022-05-31 erosion of Victoria dam Improvements Based Selection International Implementation spillway tail canal, Back Analysis for Victoria dam and Kotmale Dam grouting gallery inspection (IWWRMP/PP/CONS/31) LK-MOMDE-118622-CS- QCBS / Consultancy Services for Feasibility study on Component 2: Infrastructure Quality And Cost- Open - Pending / Post 842,696.63 0.00 2020-11-02 2020-11-23 2021-01-06 2021-02-03 2021-03-05 2021-04-09 2021-05-14 2022-05-14 Safety of Senanayaka Improvements Based Selection International Implementation Samudraya Headworks (IWWRMP/PP/CONS/33) LK-MOMDE-162975-CS-CQS / Consultancy service for Component 1: Watershed Consultant Open - Pending Expansion and enhancement / and Water Resources Prior Qualification 561,795.75 0.00 2020-11-02 2020-11-23 2021-02-06 2021-03-08 2021-04-19 2022-04-19 International Implementation of WMS/MASL bulk water Planning Selection allocation model LK-MOMDE-162977-CS-CQS / Consultancy service for Preparation of Environmental Social Management Consultant Component 2: Infrastructure Pending Framework and / Post Qualification Open - National 84,269.00 0.00 2020-08-30 2020-09-20 2020-11-03 2020-12-03 2021-01-07 2021-03-08 Improvements Implementation Environmental social Selection screening report for rehabilitation of dams & canals NPC INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MOMDE-113221-CS- INDV / Consultancy services for Environmental Social Individual Impact Assessment for Component 2: Infrastructure / Post Consultant Limited 9,090.91 9,340.87 Signed 2019-05-30 2019-05-08 2019-06-02 2019-05-28 2019-06-07 2019-06-03 2019-06-17 2019-06-03 2019-08-16 Rehabilitation of Elahara Improvements Selection scheme, Haththota scheme and Arawatta Tank (IWWRMP/PP/CONS/01) LK-MOMDE-113250-CS- INDV / Consultancy services for Environmental Social Impact Assessment for Individual Component 2: Infrastructure Rehabilitation of Hali Ela / Post Consultant Limited 12,121.21 3,593.15 Signed 2019-05-30 2019-05-08 2019-06-02 2019-05-28 2019-06-07 2019-06-02 2019-06-15 2019-06-03 2019-08-14 Improvements Tank, Akathimuripu Tank, Selection Madiyawa Tank and Waduwala Scheme (IWWRMP/PP/CONS/02) LK-MOMDE-113252-CS- Individual INDV / Consultancy services Component 2: Infrastructure / Post Consultant Limited 6,060.61 0.00 Under Review 2019-05-30 2019-05-08 2019-06-02 2019-06-07 2019-06-17 2019-08-16 for Aquatic Survey Improvements Selection (IWWRMP/PP/CONS/03) LK-MOMDE-116871-CS- INDV / Consultancy service for Preparation of Operation manual for river basin planning and management, Individual customized to the selected Component 2: Infrastructure / Post Consultant Limited 24,242.42 0.00 Under Review 2019-05-30 2019-05-08 2019-06-02 2019-06-07 2019-06-17 2019-08-16 river basins (Walawa Improvements Selection including the Walawa RB preparation of ESMP, Kalawewa and Mahalindawewa) (IWWRMP/PP/CONS/06) LK-MOMDE-116883-CS- INDV / Consultancy for Component 1: Watershed Individual Preparation of guideline for / and Water Resources Post Consultant Limited 12,121.21 8,274.72 Signed 2019-08-01 2019-07-01 2019-08-06 2019-05-03 2019-08-27 2019-07-09 2019-10-01 2019-07-15 2020-03-29 Sustainable Watershed Planning Selection Management (IWWRMP/PP/CONS/08) LK-MOMDE-116900-CS- INDV / Short-term Individual Component 4: Project assignment for Personal / Post Consultant Limited 3,030.30 0.00 Canceled 2019-05-30 2019-05-08 2019-06-04 2019-06-18 2019-07-09 2020-01-05 Management Assistant Selection (IWWRMP/PP/CONS/17) Page 12 LK-MOMDE-116901-CS- INDV / Consultancy services for Environmental Social Individual Impact Assesment for Component 2: Infrastructure / Post Consultant Limited 12,121.21 2,756.51 Signed 2019-05-30 2019-05-08 2019-06-02 2019-05-09 2019-06-07 2019-05-27 2019-06-17 2019-05-30 2019-08-16 Rehabilitation of Improvements Selection Muththuiyankaddu irrigation scheme (IWWRMP/PP/CONS/18) LK-MOMDE-116902-CS- INDV / Consultancy services for Environmental Social Impact Assesment for Individual Rehabilitation of Periyamadu Component 2: Infrastructure Pending / Post Consultant Limited 24,242.42 0.00 2019-08-30 2019-09-04 2019-09-25 2019-10-30 2019-12-29 Tank and Kariyalai Improvements Implementation Selection Nagarpaduwan Tank & irrigation scheme and Periyapandivirichchan scheme (IWWRMP/PP/CONS/19) LK-MOMDE-116903-CS- INDV / Consultancy services for Environmental Social Impact Assesment for Rehabilitation of Individual Component 2: Infrastructure Pending Akkarayankulam irrigation / Post Consultant Limited 27,272.73 0.00 2019-08-30 2019-09-04 2019-09-25 2019-10-30 2020-04-27 Improvements Implementation scheme, Kudamuruthy Tank Selection and Vannerikulam headworks & irrigation scheme (IWWRMP/PP/CONS/20) LK-MOMDE-116906-CS- INDV / Consultancy services for Environmental Social Impact Assesment for Individual Component 2: Infrastructure Rehabilitation of Dewahuwa / Post Consultant Limited 12,121.21 1,875.18 Signed 2019-05-30 2019-05-08 2019-06-04 2019-04-09 2019-06-09 2019-05-27 2019-06-19 2019-06-03 2019-08-18 Improvements tank & scheme and Selection Baththalagoda Anicut & scheme (IWWRMP/PP/CONS/22) LK-MOMDE-116907-CS- INDV / Consultancy services for Environmental Social Impact Assessment for Individual Component 2: Infrastructure Rehabilitation of / Post Consultant Limited 21,212.12 9,340.87 Signed 2019-05-30 2019-05-08 2019-06-02 2019-04-09 2019-06-07 2019-04-10 2019-06-17 2019-06-03 2019-08-16 Improvements Huruluwewa irrigation Selection scheme, Karawita Tank & Ambakolawewa Tank (IWWRMP/PP/CONS/23) LK-MOMDE-116909-CS- INDV / Consultancy services for Environmental Social Impact Assesment for Rehabilitation of Vahanery Individual Component 2: Infrastructure Dam, Panama Tank, / Post Consultant Limited 24,242.42 14,236.74 Signed 2019-05-30 2019-05-08 2019-06-04 2019-05-28 2019-06-11 2019-05-28 2019-06-25 2019-06-03 2019-09-23 Improvements Unnichchai scheme, Selection Nagadeepa Tank, Illukuchenal & Senanayake Samudraya Reservoir (IWWRMP/PP/CONS/24) LK-MOMDE-116910-CS- INDV / Consultancy services for Environmental Social Impact Assesment for Rehabilitation of Pavatkulam Individual Component 2: Infrastructure Tank, Muhathankulam / Post Consultant Limited 24,242.42 13,898.79 Signed 2019-05-30 2019-05-08 2019-06-04 2019-04-09 2019-06-11 2019-05-28 2019-06-25 2019-05-30 2019-09-23 Improvements Scheme, Viyadhikulam Selection irrigation scheme, Peramadu Tank & Scheme and Mavilaru Headworks (IWWRMP/PP/CONS/25) LK-MOMDE-116911-CS- INDV / Consultancy service Individual for preparation of Livelihood Component 2: Infrastructure / Post Consultant Limited 18,181.82 0.00 Canceled 2019-07-09 2019-07-14 2019-08-04 2019-09-08 2020-03-06 Support Assistance Plan Improvements Selection (LSA) - Walawa (IWWRMP/PP/CONS/26) LK-MOMDE-116912-CS- INDV / Consultancy services for Environmental Social Individual Component 2: Infrastructure Impact Assesment for / Post Consultant Limited 9,090.91 3,736.75 Signed 2019-05-30 2019-05-08 2019-06-04 2019-05-15 2019-06-11 2019-05-24 2019-06-25 2019-06-20 2019-08-24 Improvements Rehabilitation of Kothmale Selection Dam & irrigation scheme (IWWRMP/PP/CONS/27) LK-MOMDE-116914-CS- INDV / Individual Consultancy services to prepare mechanical Individual specification, Estimation & Component 2: Infrastructure / Post Consultant Limited 9,090.91 11,032.96 Signed 2019-05-30 2019-05-08 2019-06-02 2019-05-23 2019-06-07 2019-05-28 2019-06-17 2019-06-03 2020-06-16 Bid documents for Gantry Improvements Selection crane Polgolla, Udawalawe and Gate Automation for Bowatenna (IWWRMP/PP/CONS/28) Page 13 LK-MOMDE-116896-CS- INDV / Short-term Individual Component 4: Project assignment for Procurement / Post Consultant Limited 3,030.30 0.00 Under Review 2019-05-30 2019-05-08 2019-06-02 2019-06-07 2019-06-17 2019-12-14 Management Assistant Selection (IWWRMP/PP/CONS/16) LK-MOMDE-116904-CS- INDV / Consultancy services for Environmental Social Impact Assesment for Rehabilitation of Individual Piramanthalaru Kulam Component 2: Infrastructure / Post Consultant Limited 27,272.27 8,299.72 Signed 2019-05-30 2019-05-08 2019-06-02 2019-05-23 2019-06-07 2019-05-24 2019-06-17 2019-05-30 2019-08-16 irrigation scheme, Improvements Selection Kanagambikaikulam irrigation scheme and Kalmadu tank irrigation scheme (IWWRMP/PP/CONS/21) LK-MOMDE-121767-CS- INDV / Individual consultancy services for preparation and reviewing Individual Component 2: Infrastructure the RFP of study & / Post Consultant Open 60,000.00 0.00 Canceled 2019-07-28 2019-09-15 2019-10-06 2019-11-10 2020-05-08 Improvements recommendation for selected Selection MASL Dams (Rantambe, Victoria, Kothmale) (IWWRMP/PP/CONS/32) LK-MOMDE-121782-CS- INDV / Consultancy for Individual Preparation of guideline for Component 2: Infrastructure / Post Consultant Limited 12,121.21 0.00 Canceled 2019-09-18 2019-09-23 2019-10-14 2019-11-18 2020-05-16 sustainable Dam safety and Improvements Selection Hydraulic Assert (IWWRMP/PP/CONS/07) LK-MOMDE-138929-CS- INDV / Consultancy services Individual Component 2: Infrastructure for Preparation of TOR for / Post Consultant Limited 8,426.97 0.00 Canceled 2020-05-29 2020-06-03 2020-06-24 2020-07-29 2021-07-29 Improvements River Basin Management Selection Plan (IWWRMP-2/CS/IC/20) LK-MOMDE-162970-CS- INDV / Consultancy service for Preparation of Environmental Social Management Framework and Individual Component 2: Infrastructure Pending Environmental social / Post Consultant Limited 11,235.96 0.00 2020-08-03 2020-08-08 2020-08-15 2020-08-29 2020-11-27 Improvements Implementation screening report for Selection Rehabilitation of Wadamunai tank & Lunugamwehera Reservoir (IWWRMP- 2/CS/QCBS/15) LK-MOMDE-118665-CS- INDV / Training program on Individual Procurement (Evaluation of Component 4: Project Pending / Post Consultant Limited 6,060.61 0.00 2020-11-15 2020-11-20 2020-12-11 2021-01-15 2021-01-22 Consultancy, Goods and Management Implementation Selection Works) (IWWRMP/PP/CONS/41) Page 14