Urban Productive Safety Net Project (UPSNP) Procurement Plan I. General 2. Bank’s approval Date of the procurement Plan: February 2016 3. Date of General Procurement Notice: August 20, 2016 4. Period covered by this procurement plan: The procurement period of project covered from year January 2017 to December 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement # Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 1,500,000 All 2. NCB (Goods) Above US$ 1,000,000 All 3. ICB (Works) Above US$ 7 million All 4. NCB (Works) NA 5. (Non-Consultant Services) Below US$ 1,000,000 All 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Urban Productive Safety Net Project Implementation Manual (PIM) issued in June 2016 and UPSNP procurement manual issued May 2017. 5. Any Other Special Procurement Arrangements: Not Applicable 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 Estimated Packages Domestic Review Ref. Description Cost Preference by Bank Comments No. US$ million (yes/no) (Prior / Post) Summary of the ICB - - - - (Works) April 27, 2017 Summary of the ICB 1.2 1 Yes Prior (Goods) Summary of the NCB - - - - - (Works) Summary of the NCB 0.2 4 No Post - (Goods) Summary of the ICB - - - - (Non-Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comment Threshold 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) Above US$100,000 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_200,000_or engineering services estimated to cost US$ 300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not Applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Review Ref Description of Assignment Estimated Package by Bank Comments . Cost s (Prior / No. US$ million Post) Summary of number of 0.350 2 Prior contracts that will be let under QCBS Summary of number of 0.870 19 post IC contracts that will be let under other methods April 27, 2017 PROCUREMENT Ethiopia : Urban Productive Safety Net Project (UPSNP) PLAN General Information Country: Ethiopia Bank’s Approval Date of the Original Procurement Plan: 2017-05-15 2019-07-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151712 GPN Date: Project Name: Urban Productive Safety Net Project (UPSNP) Loan / Credit No: IDA / 57560 Executing Agency(ies):Ministry of Urban Development and Housing WORKS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DD/UJCFSA/UPSNP/W- SH/003/2017 / Construction Pending Request for Single Stage - One of Warehouse Store for IDA / 57560 1. Safety Net Support Post Open - National 49,883.00 0.00 Implementati 2018-01-05 2018-02-12 2018-04-13 Quotations Envelope public work hand tools and on materials ADAMA/UJCFSO/UPSNP/W- Pending NCB/004/2018 / Construction Single Stage - One IDA / 57560 1. Safety Net Support Post Request for Bids Open - National 200,322.00 0.00 Implementati 2018-02-16 2018-02-21 2018-03-23 2018-04-12 2018-04-30 2018-06-29 of 4 communal Latrine and Envelope on 800 meter Greenery Fence JJ/UPSNP/G-SH/007/2018 / Construction of communal Pending Request for Single Stage - One Toilet, Expansion of IDA / 57560 1. Safety Net Support Post Limited 72,832.00 0.00 Implementati 2018-03-05 2018-04-12 2018-06-11 Quotations Envelope elementary school & Health on post ASOSSA/UJCFSO/UPSNP/W- Under SH/003/2018 / Construction Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 17,370.00 0.00 Implementati 2018-03-19 2018-04-27 2018-06-01 of 4 public Toilet: (Semi Quotations Envelope on skilled labor and materials) HAWASSA/UJCFSA/UPSNP/ Pending SH-007/2018 / Procurement Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 32,000.00 0.00 Implementati 2018-05-21 2018-07-03 2018-08-17 of semi skilled labor Quotations Envelope on (Masonry and carpenter) HARAR/UJCFSA/UPSNP/W- RFQ/001/19 / Procurement Pending of Semi-skilled labor for the Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 4,900.00 0.00 Implementati 2019-03-17 2019-05-12 2019-07-11 construction of Latrine, Quotations Envelope on small bridges and Culverts etc... JJ/UJCFSO/UPSNP/W- Pending Request for Single Stage - One SH/01/19 / School Fence IDA / 57560 1. Safety Net Support Post Limited 44,174.00 0.00 Implementati 2019-02-03 2019-03-31 2019-05-30 Quotations Envelope Construction on JJ/UJCFSO/UPSNP/W- Pending Request for Single Stage - One SH/02/19 / For Construction IDA / 57560 1. Safety Net Support Post Limited 7,952.00 0.00 Implementati 2019-02-11 2019-04-08 2019-06-07 Quotations Envelope of 3 water points on JJ/UJCFSO/UPSNP/W- Request for Single Stage - One SH/03/19 / Construction of IDA / 57560 1. Safety Net Support Post Limited 19,450.00 0.00 Canceled 2019-02-20 2019-04-17 2019-06-16 Quotations Envelope 5 temporary stores JJ/UJCFSO/UPSNP/W- SH/04/19 / Construction of Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 19,450.00 0.00 Canceled 2019-02-25 2019-04-22 2019-06-21 5 Solid Waste temporary Quotations Envelope transfer station JJ/UJCFSO/UPSNP/W- SH/05/19 / Procurement of Pending Semi-skilled labor for the Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 46,780.00 0.00 Implementati 2019-02-13 2019-04-10 2019-06-09 construction of Water shade Quotations Envelope on activities and Social infrastructures Page 1 ASOSSA/UJCFSO/UPSNP/W O-RFQ/001/19 / Procurement Pending Request for Single Stage - One of semi-skilled labor for the IDA / 57560 1. Safety Net Support Post Limited 8,400.00 0.00 Implementati 2019-03-02 2019-04-27 2019-06-11 Quotations Envelope recruitment of Carpenters, on masonry GOODS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MUDH/UFSJCA/UPSNP/G- SH/008/17 / Procurement of Office Furniture (Swivel 3. Institutional Under Chair for managerial & Request for Single Stage - One IDA / 57560 Strengthening and Project Post Limited 58,374.00 0.00 Implementati 2017-05-30 2017-06-30 2017-07-17 Experts, Table for experts, Quotations Envelope Management on Guest Chair, File Cabinet, L-Shaped Table & White board) MUDH/UFSJCA/UPSNP/G- 3. Institutional Pending SH/009/17 / Procurement of Request for Single Stage - One IDA / 57560 Strengthening and Project Post Limited 2,967.00 0.00 Implementati 2017-06-06 2017-07-11 2017-07-21 Vacuum Cleaner and Water Quotations Envelope Management on cooler MUDH/UFSJCA/UPSNP/G- 3. Institutional Pending Request for Single Stage - One SH/010/17 / Procurement of IDA / 57560 Strengthening and Project Post Limited 660.00 0.00 Implementati 2017-06-06 2017-07-05 2017-07-12 Quotations Envelope Cash safe Box-100kg Management on MUDH/UFSJCA/UPSNPPA/G- 3. Institutional Pending SH/011/17 / Procurement of Request for Single Stage - One IDA / 57560 Strengthening and Project Post Limited 1,319.00 0.00 Implementati 2017-06-12 2017-07-11 2017-07-26 Leather Bag for Laptop & Quotations Envelope Management on documents MUDH/UFSJCA/UPSNP/G- NCB/004/17 / Procurement of Computers with all 3. Institutional Pending Single Stage - One accessories (Lot 1), Office IDA / 57560 Strengthening and Project Post Request for Bids Open - National 319,570.00 0.00 Implementati 2017-05-02 2017-05-09 2017-06-08 2017-06-19 2017-07-03 2017-08-17 Envelope equipment (Lot 2) and Management on Audiovisual equipment (Lot 3) AA/JCFSA/UPSNP/G- NCB/001/17 / Procurement of public works hand tools Pending Single Stage - One (Lot 1), waste collection & IDA / 57560 1. Safety Net Support Post Request for Bids Open - National 995,088.00 0.00 Implementati 2017-08-31 2017-09-06 2017-10-06 2017-10-26 2017-11-13 2017-12-13 Envelope transporting wheel carts on (Lot 2) and Gab ion in (lot 3) AA/JCFSA/UPSNP/G- SH/005/17 / Procurement of Pending Request for Single Stage - One first Aid Kit for public IDA / 57560 1. Safety Net Support Post Open - National 93,000.00 0.00 Implementati 2017-09-23 2017-10-27 2017-12-01 Quotations Envelope work beneficiary or on participants AA/JCFSA/UPSNP/G- Pending Request for Single Stage - One SH/004/17 / Procurement of IDA / 57560 1. Safety Net Support Post Open - National 4,006.00 0.00 Implementati 2017-09-19 2017-10-23 2017-11-07 Quotations Envelope different Seedlings on AA/JCFSA/UPSNP/G- Pending SH/003/17 / Procurement of Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Open - National 93,102.00 0.00 Implementati 2017-09-16 2017-10-20 2017-11-17 local made stand brooms Quotations Envelope on for Public work activity AA/JCFSA/UPSNP/G- Pending SH/002/17 / Procurement of Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Open - National 42,319.00 0.00 Implementati 2017-09-11 2017-10-18 2017-11-07 Client Cards for UPSNP Quotations Envelope on beneficiaries AA/JCFSA/UPSNP/G- SH/001/17 / Procurement of Pending Request for Single Stage - One hand Gloves made of IDA / 57560 1. Safety Net Support Post Open - National 98,392.00 0.00 Implementati 2017-09-16 2017-10-19 2017-11-18 Quotations Envelope Leather for public work on participants or beneficiaries. Page 2 MUDH/UJCFSA/UPSNP/G- NCB/005/2017 / Procurement of Computers and accessories Lot - 1 (Desktop & Laptop Computers, 3. Institutional Under Single Stage - One UPS, Heavy duty printers, IDA / 57560 Strengthening and Project Post Request for Bids Open - National 250,805.00 0.00 Implementati 2017-10-20 2017-10-25 2017-11-24 2017-12-25 2018-01-18 2018-03-19 Envelope External hard disk, ...) Management on AND Office electronics machine under Lot - 2 (Photocopiers, Scanners, LCD Projectors ...) MUDH/UJCFSA/UPSNP/G- SH/012/2017 / Procurement of Office Furniture (High 3. Institutional Pending Request for Single Stage - One Back Swivel Chair, Office IDA / 57560 Strengthening and Project Post Open - National 27,183.00 0.00 Implementati 2017-10-23 2017-12-08 2017-12-28 Quotations Envelope Table for experts, Box file Management on Cabinet-Metal for record keeping, ...) MUDH/UJCFSA/UPSNP/G- 3. Institutional Pending Request for Single Stage - One SH/013/2017 / Procurement IDA / 57560 Strengthening and Project Post Open - National 471.00 0.00 Implementati 2017-10-23 2017-12-01 2017-12-15 Quotations Envelope of Digital Photo Camera Management on AA/JCFSA/UPSNP/G- NCB/002/17 / Procurement locally made working cloth (Tuta) in Lot - 1, Procurement of locally made Pending working leather shoes in Single Stage - One IDA / 57560 1. Safety Net Support Post Request for Bids Open - National 1,392,307.00 0.00 Implementati 2017-10-13 2017-10-27 2017-11-27 2017-12-18 2018-01-05 2018-02-05 Lot - 2 and Procurement of Envelope on protection materials like "eye glass made of plastic materials, mouse & nose dust protection masks" in Lot - 3 AA/JCFSA/UPSNP/G- Pending SH/006/17 / Procurement of Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Open - National 69,230.00 0.00 Implementati 2017-10-25 2017-12-01 2017-12-26 Local made sunhat for PW Quotations Envelope on participants DD/UJCFSA/UPSNP/G- NCB/001/2017 / Procurement of Public Work Hand tools in Lot-1, Pending Procurement of personal Single Stage - One IDA / 57560 1. Safety Net Support Post Request for Bids Open - National 1,370,356.00 0.00 Implementati 2017-12-25 2018-01-01 2018-01-31 2018-02-14 2018-02-28 2018-03-30 Safety materials for public Envelope on work activities in Lot-2, procurement of galvanized Gabion wire for soil & water conservation in Lot-3 DD/UJCFSA/UPSNP/G- Pending SH/001/2017 / Procurement Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Open - National 11,111.00 0.00 Implementati 2018-01-02 2018-02-16 2018-03-16 of Locally made hand push Quotations Envelope on Carts DD/UJCFSA/UPSNP/G- SH/002/2017 / Procurement Pending Request for Single Stage - One of locally made stand IDA / 57560 1. Safety Net Support Post Open - National 13,425.00 0.00 Implementati 2017-12-29 2018-02-08 2018-03-15 Quotations Envelope brooms, locally made Hut on for public work participants DD/UJCFSA/UPSNP/G- Pending SH/004/2017 / Procurement Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Open - National 3,700.00 0.00 Implementati 2017-12-29 2018-02-01 2018-02-21 of First Aid kit for public Quotations Envelope on work participants DD/UJCFSA/UPSNP/G- Pending SH/005/2017 / Procurement Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Open - National 69,630.00 0.00 Implementati 2018-02-22 2018-03-29 2018-04-13 of Different seeds and Quotations Envelope on seedligs DD/UJCFSA/UPSNP/G- Pending Request for Single Stage - One SH/006/2017 / Procurement IDA / 57560 1. Safety Net Support Post Open - National 8,888.00 0.00 Implementati 2017-12-28 2018-02-01 2018-02-21 Quotations Envelope of Client Identification cards on Page 3 ADAMA/UJCFSO/UPSNP/G- Pending Single Stage - One NCB/001/2018 / Procurement IDA / 57560 1. Safety Net Support Post Request for Bids Open - National 129,671.00 0.00 Implementati 2018-02-01 2018-02-06 2018-03-08 2018-03-23 2018-04-05 2018-05-07 Envelope of Public Work Hand Tools on ADAMA/UJCFSO/UPSNP/G- Pending Single Stage - One NCB/002/2018 / Procurement IDA / 57560 1. Safety Net Support Post Request for Bids Open - National 341,134.00 0.00 Implementati 2018-02-07 2018-02-12 2018-03-14 2018-03-29 2018-04-12 2018-05-12 Envelope of Public Work Materials on ADAMA/UJCFSO/UPSNP/G- NCB/003/2018 / Procurement Pending Single Stage - One of Safety materials for IDA / 57560 1. Safety Net Support Post Request for Bids Open - National 259,479.00 0.00 Implementati 2018-01-31 2018-02-05 2018-03-07 2018-03-22 2018-04-05 2018-05-21 Envelope public work participants on (PPE) ADAMA/UJCFSO/UPSNP/G- Pending SH/001/2018 / procurement Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 12,388.00 0.00 Implementati 2018-02-19 2018-03-26 2018-04-16 of Local Materials (Peg and Quotations Envelope on Barela made of wood) ADAMA/UJCFSO/UPSNP/G- Pending SH/002/2018 / Procurement Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 14,522.00 0.00 Implementati 2018-06-04 2018-07-02 2018-07-17 of Seedling and Defective Quotations Envelope on Microorganism SEMERA- LOGIA/UJCFSO/UPSNP/G- Pending Request for Single Stage - One SH/001/2018 / Procurement IDA / 57560 1. Safety Net Support Post Limited 25,515.00 0.00 Implementati 2018-02-27 2018-04-02 2018-04-27 Quotations Envelope of Hand Tools for public on work participants SEMERA- Pending LOGIA/UJCFSO/UPSNP/G- Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 16,386.00 0.00 Implementati 2018-02-20 2018-03-30 2018-04-30 SH/002/2018 / Procurement Quotations Envelope on of Safety Materials (PPE) JJ/UPSNP/G-NCB/001/2018 Pending / Procurement of public Single Stage - One IDA / 57560 1. Safety Net Support Post Request for Bids Open - National 134,796.00 0.00 Implementati 2018-02-15 2018-02-20 2018-03-22 2018-04-05 2018-04-19 2018-05-24 work Hand Tools and Envelope on sanitation materials JJ/UPSNP/G-NCB/002/2018 Pending / Procurement of personal Single Stage - One IDA / 57560 1. Safety Net Support Post Request for Bids Open - National 136,738.00 0.00 Implementati 2018-02-20 2018-02-26 2018-03-28 2018-04-12 2018-04-30 2018-06-14 protective and Safety Envelope on materials Pending JJ/UPSNP/G-SH/003/2018 / Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 62,610.00 0.00 Implementati 2018-02-19 2018-03-23 2018-04-27 Procurement of Black Stone Quotations Envelope on JJ/UPSNP/G-SH/004/2018 / Pending Request for Single Stage - One Procurement of wooden pole IDA / 57560 1. Safety Net Support Post Limited 1,528.00 0.00 Implementati 2018-02-19 2018-03-26 2018-04-15 Quotations Envelope for fence on Pending JJ/UPSNP/G-SH/005/2018 / Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 6,114.00 0.00 Implementati 2018-02-21 2018-03-21 2018-04-20 Procurement of Compost Quotations Envelope on JJ/UPSNP/G-SH/006/2018 / Pending Request for Single Stage - One Procurement of Gabion IDA / 57560 1. Safety Net Support Post Limited 21,196.00 0.00 Implementati 2018-02-21 2018-04-05 2018-04-20 Quotations Envelope (double 1x1) on JJ/UPSNP/G-SH/002/2018 / Pending Request for Single Stage - One Procurement of polythene IDA / 57560 1. Safety Net Support Post Limited 24,457.00 0.00 Implementati 2018-05-07 2018-06-18 2018-07-03 Quotations Envelope Tube on ASOSSA/UJCFSO/UPSNP/G- Pending Request for Single Stage - One SH/001/2018 / Procurement IDA / 57560 1. Safety Net Support Post Open - National 31,180.00 0.00 Implementati 2018-03-06 2018-04-30 2018-05-30 Quotations Envelope of Public work hand tools on ASOSSA/UJCFSO/UPSNP/G- Pending SH/002/2018 / Procurement Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Open - National 52,948.00 0.00 Implementati 2018-03-12 2018-05-07 2018-06-06 of Safety Materials for Quotations Envelope on Public work participants Page 4 ASOSSA/UJCFSO/UPSNP/G- Pending SH/004/2018 / Procurement Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 8,815.00 0.00 Implementati 2018-05-14 2018-06-29 2018-07-19 of Polythene tube, seeds Quotations Envelope on and seedlings GAMBELLA/UJCFSO/UPSN P/G-NCB/001/2018 / Procurement of different Pending Single Stage - One Hand Tools under Lot - 1 IDA / 57560 1. Safety Net Support Post Request for Bids Open - National 219,002.00 0.00 Implementati 2018-02-20 2018-02-27 2018-03-29 2018-04-13 2018-05-11 2018-06-25 Envelope and Safety Materials under on Lot - 2 for public work participants GAMBELLA/UJCFSO/UPSN Under P/G-SH/002/2018 / Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 44,015.00 0.00 Implementati 2018-03-20 2018-05-15 2018-06-04 Procurement of different Quotations Envelope on seedlings for greenery GAMBELLA/UJCFSO/UPSN P/G-SH/003/2018 / Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 3,962.00 1,841.44 Completed 2018-02-28 2018-04-11 2018-04-26 Procurement of forest soil Quotations Envelope (fertile soil) JJ/UPSNP/G-SH/001/2018 / Pending Procurement of greenery Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Open - National 73,087.00 0.00 Implementati 2018-05-21 2018-07-06 2018-07-20 materials (small flowers, Quotations Envelope on grasses, seeds, seedlings) GAMBELLA/UJCFSO/UPSN Pending Request for Single Stage - One P/G-SH/001/2018 / IDA / 57560 1. Safety Net Support Post Limited 11,000.00 0.00 Implementati 2018-03-05 2018-04-16 2018-04-30 Quotations Envelope Procurement of Polythene on AA/UJCFSA/UPSNP/G- NCB/001/2018 / Procurement Pending Single Stage - One of Safety/protective IDA / 57560 1. Safety Net Support Post Request for Bids Open - National 493,926.00 0.00 Implementati 2018-03-08 2018-03-13 2018-04-12 2018-04-27 2018-05-11 2018-07-10 Envelope materials ( Hand Gloves, on masks, Eye glass etc.) AA/UJCFSA/UPSNP/G- Pending NCB/002/2018 / Procurement Single Stage - One IDA / 57560 1. Safety Net Support Post Request for Bids Open - National 155,295.00 0.00 Implementati 2018-03-15 2018-03-20 2018-04-19 2018-05-04 2018-05-18 2018-06-12 of different seedlings for Envelope on urban greenery activities MEKELLE/UJCFSO/UPSNP/ G-NCB/002/2018 / Pending Single Stage - One Procurement of Safety IDA / 57560 1. Safety Net Support Post Request for Bids Open - National 212,444.00 0.00 Implementati 2018-03-01 2018-03-06 2018-04-05 2018-04-20 2018-05-04 2018-06-08 Envelope Materials for public work on participants MEKELLE/UJCFSO/UPSNP/ G-NCB/003/2018 / Pending Single Stage - One Procurement of different IDA / 57560 1. Safety Net Support Post Request for Bids Open - National 115,000.00 0.00 Implementati 2018-03-20 2018-03-27 2018-04-26 2018-05-11 2018-05-25 2018-06-25 Envelope tree seeds seedlings for on greenery activities MEKELLE/UJCFSO/UPSNP/ Pending Request for Single Stage - One G-SH/001/2018 / IDA / 57560 1. Safety Net Support Post Open - National 37,037.00 0.00 Implementati 2018-04-02 2018-05-14 2018-05-29 Quotations Envelope Procurement of Mobile on Toilet MEKELLE/UJCFSO/UPSNP/ Pending Request for Single Stage - One G-SH/002/2018 / IDA / 57560 1. Safety Net Support Post Limited 6,296.00 0.00 Implementati 2018-04-09 2018-05-10 2018-05-25 Quotations Envelope Procurement of fruit seeds on HARER/UJCFSA/UPSNP/G- SH/001/2018 / Procurement Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 45,676.00 53,637.62 Completed 2018-03-19 2018-04-23 2018-05-23 of different types of public Quotations Envelope work hand tools HARAR/UJCFSA/UPSNP/G- SH/002/2018 / Procurement Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 52,101.00 53,158.85 Completed 2018-03-27 2018-05-03 2018-06-04 of Safety/personal protective Quotations Envelope materials HARAR/UJCFSA/UPSNP/G- Request for Single Stage - One SH/003/2018 / Procurement IDA / 57560 1. Safety Net Support Post Limited 28,770.00 28,116.22 Completed 2018-03-26 2018-04-26 2018-05-21 Quotations Envelope of construction materials Page 5 HARAR/UJCFSA/UPSNP/G- Pending SH/004/2018 / Procurement Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 1,478.00 0.00 Implementati 2018-04-02 2018-04-30 2018-05-15 of Polythene Tube for Quotations Envelope on seedling preparation HARAR/UJCFSA/UPSNP/G- SH/005/2018 / Procurement Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Open - National 35,246.00 29,034.09 Completed 2018-04-23 2018-06-01 2018-06-21 of different seed and Quotations Envelope seedlings HARAR/UJCFSA/UPSNP/G- SH/006/2018 / Procurement Request for Single Stage - One of metal safety fence for IDA / 57560 1. Safety Net Support Post Limited 24,889.00 17,849.64 Completed 2018-03-28 2018-04-27 2018-06-01 Quotations Envelope greenery area, Dust Bin, and sign board AA/UJCFSA/UPSNP/G- NCB/003/2018 / Procurement Pending Single Stage - One of ready-made stand brooms IDA / 57560 1. Safety Net Support Post Request for Bids Open - National 531,361.00 0.00 Implementati 2018-03-20 2018-03-27 2018-04-26 2018-05-11 2018-05-25 2018-07-24 Envelope and hats for public work on activities MEKELLE/UJCFSO/UPSNP/ G-NCB/01/2018 / Pending Single Stage - One Procurement of different IDA / 57560 1. Safety Net Support Post Request for Bids Open - National 102,056.00 0.00 Implementati 2018-03-05 2018-03-12 2018-04-11 2018-04-26 2018-05-10 2018-06-14 Envelope types of hand tools for on public work participants MEKELLE/UJCFSO/UPSNP/ Pending Request for Single Stage - One G-SH/003/2018 / IDA / 57560 1. Safety Net Support Post Limited 16,333.00 0.00 Implementati 2018-03-27 2018-05-04 2018-05-24 Quotations Envelope Procurement of construction on materials DESSIE/UJCFSO/UPSNP/G- Pending NCB/001/18 / Procurement Single Stage - One IDA / 57560 1. Safety Net Support Post Request for Bids Open - National 85,302.00 0.00 Implementati 2018-04-02 2018-04-09 2018-05-09 2018-05-24 2018-06-07 2018-07-06 of different Public work Envelope on hand tolls and materials DESSIE/UJCFSO/UPSNP/G- Pending NCB/002/18 / Procurement Single Stage - One IDA / 57560 1. Safety Net Support Post Request for Bids Open - National 136,074.00 0.00 Implementati 2018-03-30 2018-04-04 2018-05-04 2018-05-18 2018-06-01 2018-07-02 of personal safety materials Envelope on for public work participants DESSIE/UJCFSO/UPSNP/G- NCB/003/18 / Procurement of different industrial construction materials Pending Single Stage - One (Corrugated Iron sheet, IDA / 57560 1. Safety Net Support Post Request for Bids Open - National 147,429.00 0.00 Implementati 2018-04-04 2018-04-09 2018-05-09 2018-05-23 2018-06-06 2018-07-06 Envelope nails,Gab ion, Role meters, on Wires, Cements, blocks, paints, fencing wire, reinforcement bar etc) DESSIE/UJCFSO/UPSNP/G- SH/001/18 / Procurement of Pending local construction materials Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 41,553.00 0.00 Implementati 2018-04-23 2018-05-24 2018-06-08 (sand, stone, gravel, Quotations Envelope on different size pole, Lumber etc) DESSIE/UJCFSO/UPSNP/G- SH/002/18 / Procurement of Pending Request for Single Stage - One different seeds and IDA / 57560 1. Safety Net Support Post Limited 16,961.00 0.00 Implementati 2018-05-07 2018-06-07 2018-07-02 Quotations Envelope seedlings for greenery on activities DESSIE/UJCFSO/UPSNP/G- SH/004/18 / Procurement of drip irrigation equipment Pending Request for Single Stage - One with accessories (such as IDA / 57560 1. Safety Net Support Post Limited 42,653.00 0.00 Implementati 2018-05-07 2018-06-07 2018-06-22 Quotations Envelope Hoses, water holding tanks, on water pipe with accessories & fittings etc) HAWASSA/UJCFSO/UPSNP/ NCB-001/2018 / Procurement of different Pending Single Stage - One types of public work hand IDA / 57560 1. Safety Net Support Post Request for Bids Open - National 775,268.00 0.00 Implementati 2018-04-20 2018-04-25 2018-05-25 2018-06-07 2018-06-21 2018-07-23 Envelope tools and materials under on lot 1 AND Procurement of personal safety materials under lot 2 Page 6 HAWASSA/UJCFSA/UPSNP/ Request for Single Stage - One SH-001/2018 / Procurement IDA / 57560 1. Safety Net Support Post Limited 18,621.00 9,353.52 Completed 2018-05-02 2018-06-05 2018-06-25 Quotations Envelope of water holding materials HAWASSA/UJCFSA/UPSNP/ SH-002/2018 / Procurement Under Request for Single Stage - One of wast collection & IDA / 57560 1. Safety Net Support Post Limited 9,402.00 0.00 Implementati 2018-04-30 2018-05-31 2018-06-20 Quotations Envelope accumulation different color on plastic bages HAWASSA/UJCFSO/UPSNP/ SH-003/2018 / Procurement Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 96,000.00 13,600.61 Completed 2018-04-25 2018-05-25 2018-06-14 of different types of Quotations Envelope Seedlings for greenery activities HAWASSA/UJCFSA/UPSNP/ Pending SH-004/2018 / Procurement Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 88,864.00 0.00 Implementati 2018-05-15 2018-06-18 2018-07-13 of local fencing wood, peg, Quotations Envelope on pole & Timber HAWASSA/UJCFSO/UPSNP/ Pending SH-005/2018 / Procurement Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 42,256.00 0.00 Implementati 2018-05-07 2018-06-12 2018-07-02 of construction stone, sand, Quotations Envelope on Ash, gravel etc. HAWASSA/UJCFSA/UPSNP/ Pending Request for Single Stage - One SH-006/2018 / Procurement IDA / 57560 1. Safety Net Support Post Limited 1,822.00 0.00 Implementati 2018-05-07 2018-06-08 2018-06-22 Quotations Envelope of First Aid Kits on AA/UJCFSA/UPSNP/G- ICB/001/2018 / Procurement of public work hand tools Under in lot 1, one wheel carts in Open - Single Stage - One IDA / 57560 1. Safety Net Support Prior Request for Bids 8,138,704.00 0.00 Implementati 2018-04-30 2018-05-07 2018-06-21 2018-07-26 2018-08-30 2018-11-28 lot 2, gabion in lot 3, and International Envelope on procurement of personal protective and safety materials & cloths in lot 4. MEKELLE/UJCFSO/UPSNP/ G-SH/04/18 / Procurement of additional Personal Pending Request for Single Stage - One Protective materials (Hand IDA / 57560 1. Safety Net Support Post Limited 55,555.00 0.00 Implementati 2018-06-05 2018-07-03 2018-07-23 Quotations Envelope glove, Plastic boots, Hut, on Eye Glass working cloth etc.) MEKELLE/UJCFSO/UPSNP/ G-SH/05/18 / Procurement of additional Public Work Request for Single Stage - One hand tools (Stand Brooms IDA / 57560 1. Safety Net Support Post Limited 48,148.00 9,215.05 Signed 2018-06-06 2018-07-05 2018-07-25 Quotations Envelope made of plastic, Fork 10 finger, Scissors, different color plastic bags etc.) MEKELLE/UJCFSO/UPSNP/ G-SH/06/18 / Procurement Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 7,408.00 5,635.20 Signed 2018-06-11 2018-07-06 2018-07-20 of different seedlings for Quotations Envelope greenery MUDH/UJCFSA/UPSNP/G- UN-DC/001/18 / Procurement of 23 Vehicles 3. Institutional Under UN Agencies through UN Agency IDA / 57560 Strengthening and Project Post Direct 839,000.00 0.00 Implementati 2018-12-24 2018-12-29 2019-02-02 2019-08-01 (Direct) (UNOPS) direct contracting. Management on (13 4wd Hard top and 10 4wd pick up double cab) MUDH/UJCFSA/UPSNP/G- RFB/002/18 / Procurement 3. Institutional Under of Desktop computers with Single Stage - One IDA / 57560 Strengthening and Project Post Request for Bids Open - National 182,700.00 0.00 Implementati 2018-12-21 2018-12-26 2019-01-25 2019-02-24 2019-04-01 2019-06-30 printer and Photocopy Envelope Management on machine for all City level one stop shops MUDH/UJCFSA/UPSNP/G- RFQ/001/18 / Procurement 3. Institutional Request for Single Stage - One of office furniture (office IDA / 57560 Strengthening and Project Post Limited 17,960.00 8,367.95 Signed 2018-12-24 2019-02-18 2019-04-19 Quotations Envelope table and chair) for all city Management level one stop shops Page 7 HARAR/UJCFSO/UPSNP/GO- Pending RFQ/01/19 / Procurement of Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 38,162.00 0.00 Implementati 2019-02-04 2019-04-01 2019-05-01 different Hand Tools for Quotations Envelope on public work activities HARAR/UJCFSO/UPSNP/GO- Request for Single Stage - One RFQ/02/19 / Procurement of IDA / 57560 1. Safety Net Support Post Limited 56,230.00 59,929.76 Completed 2019-02-23 2019-04-20 2019-05-20 Quotations Envelope Safety/protective materials HARAR/UJCFSO/UPSNP/GO- Pending RFB/01/19 / Procurement of Single Stage - One IDA / 57560 1. Safety Net Support Post Request for Bids Open - National 130,490.00 0.00 Implementati 2019-02-25 2019-03-02 2019-04-13 2019-05-13 2019-06-17 2019-08-16 construction materials and Envelope on inputs HARAR/UJCFSO/UPSNP/GO- Pending RFQ/04/19 / Procurement of Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 79,185.00 0.00 Implementati 2019-04-07 2019-06-02 2019-07-02 different seeds, seedlings Quotations Envelope on and plantations HARAR/UJCFSO/UPSNP/GO- RFQ/06/19 / Procurement of Pending Request for Single Stage - One 51,200 liter of Water by IDA / 57560 1. Safety Net Support Post Limited 3,150.00 0.00 Implementati 2019-04-27 2019-06-22 2019-09-20 Quotations Envelope vehicle with water tank for on Urban greenery activities JJ/UJCFSO/UPSNP/G- SH/01/19 / Procurement of Pending Request for Single Stage - One Seeds, Seedlings, Grass and IDA / 57560 1. Safety Net Support Post Limited 72,122.00 0.00 Implementati 2019-02-02 2019-03-30 2019-05-29 Quotations Envelope small flowers for greenery on activities JJ/UJCFSO/UPSNP/GO- Pending Request for Single Stage - One SH/02/19 / Procurement of IDA / 57560 1. Safety Net Support Post Limited 7,952.00 0.00 Implementati 2019-02-09 2019-04-06 2019-05-06 Quotations Envelope Brooms on JJ/UJCFSO/UPSNP/GO- Pending Single Stage - One RFB/01/19 / Procurement of IDA / 57560 1. Safety Net Support Post Request for Bids Open - National 159,027.00 0.00 Implementati 2019-01-30 2019-02-04 2019-03-18 2019-04-17 2019-05-22 2019-07-21 Envelope Safety /protective materials on JJ/UJCFSO/UPSNP/GO- Pending Request for Single Stage - One SH/03/19 / Procurement of IDA / 57560 1. Safety Net Support Post Limited 54,540.00 0.00 Implementati 2019-02-09 2019-04-06 2019-05-06 Quotations Envelope Black Stone on JJ/UJCFSO/UPSNP/GO- Pending Request for Single Stage - One SH/04/19 / Procurement of IDA / 57560 1. Safety Net Support Post Limited 51,406.00 0.00 Implementati 2019-02-05 2019-04-02 2019-05-02 Quotations Envelope Gabion (Double 1x1) on GAMBELLA/UJCFSO/UPSN Pending P/GO-RFQ/01/19 / Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 33,690.00 0.00 Implementati 2019-02-23 2019-04-20 2019-06-19 Procurement of different Quotations Envelope on Hand Tools GAMBELLA/UJCFSO/UPSN Pending P/GO-RFQ/02/19 / Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 97,308.00 0.00 Implementati 2019-03-02 2019-04-27 2019-06-26 Procurement of Safety Quotations Envelope on Materials and Cloths GAMBELLA/UJCFSO/UPSN P/GO-RFQ/03/19 / Pending Request for Single Stage - One Procurement of Polythene IDA / 57560 1. Safety Net Support Post Limited 8,970.00 0.00 Implementati 2019-04-29 2019-06-24 2019-07-24 Quotations Envelope tube and Seedling plastic on box GAMBELLA/UJCFSO/UPSN Pending P/GO-RFQ/04/19 / Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 58,306.00 0.00 Implementati 2019-04-29 2019-06-24 2019-08-23 Procurement of different Quotations Envelope on Seedlings GAMBELLA/UJCFSO/UPSN Pending P/G-RFQ-005/19 / Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 10,100.00 0.00 Implementati 2019-02-25 2019-04-22 2019-05-22 Procurement of Local Quotations Envelope on Construction Materials GAMBELLA/UJCGSO/UPSN Pending P/G-RFQ/006/19 / Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 12,700.00 0.00 Implementati 2019-02-25 2019-04-22 2019-05-22 Procurement of Industrial Quotations Envelope on Construction Materials Page 8 ASOSSA/UJCFSO/UPSNP/G- Pending RFQ/001/19 / Procurement Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 43,310.00 0.00 Implementati 2019-02-23 2019-04-20 2019-05-20 of PW Hand Tools and Quotations Envelope on materials ASOSSA/UJCFSO/UPSNP/G- Pending RFB/001/19 / Procurement Single Stage - One IDA / 57560 1. Safety Net Support Post Request for Bids Open - National 101,600.00 0.00 Implementati 2019-02-22 2019-02-27 2019-04-10 2019-05-10 2019-06-14 2019-07-14 of Safety/protective Envelope on materials ASOSSA/UJCFSO/UPSNP/G- Pending RFQ/002/19 / Procurement Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 35,700.00 0.00 Implementati 2019-03-02 2019-04-27 2019-05-27 of Different seeds and Quotations Envelope on Seedlings ASOSSA/UJCFSO/UPSNP/G- RFQ/003/19 / Procurement Pending Request for Single Stage - One of construction materials for IDA / 57560 1. Safety Net Support Post Limited 22,500.00 0.00 Implementati 2019-03-05 2019-04-30 2019-05-30 Quotations Envelope the contraction 2 public on toilet ASOSSA/UJCFSO/UPSNP/G- RFQ/004/19 / Procurement of water pipes, joiners, gate Pending Request for Single Stage - One valves, water meter, unions, IDA / 57560 1. Safety Net Support Post Limited 18,350.00 0.00 Implementati 2019-02-23 2019-04-20 2019-05-20 Quotations Envelope Elbows etc for the on installation of water line for greenery activities HARER/UJCFSO/UPSNP/GO- Pending RFQ/003/19 / Procurement Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 38,500.00 0.00 Implementati 2019-03-16 2019-05-11 2019-06-10 of Concrete Chair and Quotations Envelope on Concrete tube/pipe HARER/UJCFSO/UPSNP/GO- RFQ/005/19 / Procurement Pending Request for Single Stage - One of 800 pcs ready made of IDA / 57560 1. Safety Net Support Post Limited 40,000.00 0.00 Implementati 2019-04-06 2019-06-01 2019-07-01 Quotations Envelope Safety fence (1mx1m), and on 140 Dust Bin SEMERS- Pending LOGIA/UJCFSO/UPSNP/GO- Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 29,200.00 0.00 Implementati 2019-02-20 2019-04-17 2019-05-17 RFQ/01/19 / Procurement of Quotations Envelope on public works Hand Tools SEMERA- Pending LOGIA/UJCFSO/UPSNP/GO- Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 26,640.00 0.00 Implementati 2019-02-12 2019-04-09 2019-05-09 RFQ/02/19 / Procurement of Quotations Envelope on Safety Materials SEMERA- Pending LOGIA/UJCFSO/UPSNP/GO- Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 11,780.00 0.00 Implementati 2019-03-06 2019-05-01 2019-05-31 RFQ/03/19 / Procurement Quotations Envelope on construction materials SEMERA- LOGIA/UJCFSO/UPSNP/GO- Pending Request for Single Stage - One RFQ/04/19 / Procurement of IDA / 57560 1. Safety Net Support Post Limited 4,650.00 0.00 Implementati 2019-03-10 2019-05-05 2019-06-04 Quotations Envelope Waste collection plastic bags on (50kg and 100kg) JJ/UJCFSA/UPSNP/GO- RFQ/05/19 / Procurement of Pending Request for Single Stage - One Galvanized Gabion wire for IDA / 57560 1. Safety Net Support Post Limited 19,600.00 0.00 Implementati 2019-05-22 2019-07-17 2019-08-16 Quotations Envelope water & soil conservation on (double 1x1) JJ/UJCFSA/UPSNP/GO- RFQ/06/19 / Procurement of Pending Request for Single Stage - One Black stone for soil and IDA / 57560 1. Safety Net Support Post Limited 18,300.00 0.00 Implementati 2019-05-25 2019-07-20 2019-08-09 Quotations Envelope water conservation (water on shad management) HARER/UJCFSO/UPSNP/GO- Pending RFQ-07/19 / Procurement of Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 76,716.00 0.00 Implementati 2019-06-29 2019-08-24 2019-09-08 Local Contraction materials Quotations Envelope on (Sand, wood, crush stone...) Page 9 HARER/UJCFSO/UPSNP/GO- RFQ/08/19 / Procurement of Pending Industrial contraction Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 32,000.00 0.00 Implementati 2019-06-30 2019-08-25 2019-09-09 materials (re-enforcement Quotations Envelope on bar, Wire 2mm, Metal sheet, Cements, ...) HARER/UJCFSA/UPSNP/GO- RFQ/01/2019/2020 / Pending Request for Single Stage - One Procurement of different IDA / 57560 1. Safety Net Support Post Limited 92,830.00 0.00 Implementati 2019-08-03 2019-09-28 2019-10-28 Quotations Envelope seedlings for greenery on activities GAMBELLA/UJCFSA/UPSN P/GO-RFQ/01/2019/20 / Pending Request for Single Stage - One Procurement of different IDA / 57560 1. Safety Net Support Post Limited 86,240.00 0.00 Implementati 2019-08-03 2019-09-28 2019-10-28 Quotations Envelope seedling for greenery on activities SEMERA- LOGIA/UJCFSO/UPSNP/GO- Pending RFQ/01/2019 / Procurement Request for Single Stage - One IDA / 57560 1. Safety Net Support Post Limited 21,760.00 0.00 Implementati 2019-08-03 2019-09-28 2019-10-28 of Seedlings, Fertilizer, Quotations Envelope on protection fence round with loading & unloading costs JIGJIGA/UJCFSO/UPSNP/G O-RFQ/01/2019/20 / Pending Request for Single Stage - One Procurement of Seedlings, IDA / 57560 1. Safety Net Support Post Limited 76,700.00 0.00 Implementati 2019-08-04 2019-09-29 2019-10-29 Quotations Envelope including transportation and on protective Fencing ASSOSA/UJCFSO/UPSNP/G Pending Request for Single Stage - One O-RFQ/01/2019/20 / IDA / 57560 1. Safety Net Support Post Limited 99,900.00 0.00 Implementati 2019-08-04 2019-09-29 2019-10-29 Quotations Envelope Procurement of Seedlings on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MUDH/UJCFSA/UPSNP/NCS- DC/024/17 / For renting 3. Institutional Pending additional office space for IDA / 57560 Strengthening and Project Post Direct Selection Direct 24,000.00 0.00 Implementati 2017-08-31 2017-09-05 2017-10-10 2018-10-10 UPSNP coordination Unit in Management on the same building rented before for 12 months MOLSA/UPSNP/UDS/DC/AD/ KETEMA S-CITY/1/19 / Procurement of Services to improve the economic, Pending educational and/or social IDA / 57560 1. Safety Net Support Post Direct Selection Direct 777,920.00 0.00 Implementati 2019-05-29 2019-06-03 2019-07-08 2021-07-07 reintegration of the on homeless street children through providing basic social and livelihood services MOLSA/UPSNP/UDS/DC/AK/ KALITI S-CITY/2/19 / Procurement of Services to improve the economic, Pending educational and/or social IDA / 57560 1. Safety Net Support Post Direct Selection Direct 311,168.00 0.00 Implementati 2019-05-29 2019-06-03 2019-07-08 2021-07-07 reintegration of the on homeless street children through providing basic social and livelihood services MOLSA/UPSNP/UDS/DC/AR ADA S-CITY/2/19 / Procurement of Services to improve the economic, Pending educational and/or social IDA / 57560 1. Safety Net Support Post Direct Selection Direct 657,585.00 0.00 Implementati 2019-05-29 2019-06-03 2019-07-08 2021-07-07 reintegration of the on homeless street children through providing basic social and livelihood services Page 10 MOLSA/UPSNP/UDS/DC/BO LE S-CITY/4/19 / Procurement of Services to improve the economic, Pending educational and/or social IDA / 57560 1. Safety Net Support Post Direct Selection Direct 522,665.00 0.00 Implementati 2019-05-29 2019-06-03 2019-07-08 2021-07-07 reintegration of the on homeless street children through providing basic social and livelihood services MOLSA/UPSNP/UDS/DC/GU LALLE/5/19 / Procurement of Services to improve the Pending economic, educational and/or IDA / 57560 1. Safety Net Support Post Direct Selection Direct 421,778.00 0.00 Implementati 2019-05-29 2019-06-03 2019-07-08 2021-07-07 social reintegration of the on homeless street children through providing basic social and livelihood services MOLSA/UPSNP/UDS/DC/KIR KOS S-CITY/6/19 / Procurement of Services to improve the economic, Pending educational and/or social IDA / 57560 1. Safety Net Support Post Direct Selection Direct 713,499.00 0.00 Implementati 2019-05-29 2019-06-03 2019-07-08 2021-07-07 reintegration of the on homeless street children through providing basic social and livelihood services MOLSA/UPSNP/UDS/DC- KOLFE S-CITY/7/19 / Procurement of Services to improve the economic, Pending educational and/or social IDA / 57560 1. Safety Net Support Post Direct Selection Direct 362,219.00 0.00 Implementati 2019-05-29 2019-06-03 2019-07-08 2021-07-07 reintegration of the on homeless street children through providing basic social and livelihood services MOLSA/UPSNP/UDS/DC/LID ETA S-CITY/8/19 / Procurement of Services to improve the economic, Pending educational and/or social IDA / 57560 1. Safety Net Support Post Direct Selection Direct 602,888.00 0.00 Implementati 2019-05-29 2019-06-03 2019-07-08 2021-07-07 reintegration of the on homeless street children through providing basic social and livelihood services MOLSA/UPSNP/UDS/DC/NIF AS SILK/9/19 / Procurement of Services to improve the Pending economic, educational and/or IDA / 57560 1. Safety Net Support Post Direct Selection Direct 320,892.00 0.00 Implementati 2019-05-29 2019-06-03 2019-07-08 2021-07-07 social reintegration of the on homeless street children through providing basic social and livelihood services MOLSA/UPSNP/UDS/DC/YE KA S-CITY/10/19 / Procurement of Services to improve the economic, Pending educational and/or social IDA / 57560 1. Safety Net Support Post Direct Selection Direct 331,831.00 0.00 Implementati 2019-05-29 2019-06-03 2019-07-08 2021-07-07 reintegration of the on homeless street children through providing basic social and livelihood services MOLSA/UPSNP/UDS/DC/AD AMA CITY/01/19 / Procurement of Services to improve the economic, Pending educational and/or social IDA / 57560 1. Safety Net Support Post Direct Selection Direct 520,234.00 0.00 Implementati 2019-05-29 2019-06-03 2019-07-08 2021-07-07 reintegration of the on homeless street children through providing basic social and livelihood services Page 11 MOLSA/UPSNP/UDS/DC/ME KELLE CITY/01/19 / Procurement of Services to improve the economic, Pending educational and/or social IDA / 57560 1. Safety Net Support Post Direct Selection Direct 523,880.00 0.00 Implementati 2019-05-29 2019-06-03 2019-07-08 2021-07-07 reintegration of the on homeless street children through providing basic social and livelihood services MOLSA/UPSNP/UDS/DC/HA WASSA CITY/01/19 / Procurement of Services to improve the economic, Pending educational and/or social IDA / 57560 1. Safety Net Support Post Direct Selection Direct 489,846.00 0.00 Implementati 2019-05-29 2019-06-03 2019-07-08 2021-07-07 reintegration of the on homeless street children through providing basic social and livelihood services MOLSA/UPSNP/UDS/DC/DIR E DAWA CITY/01/19 / Procurement of Services to improve the economic, Pending educational and/or social IDA / 57560 1. Safety Net Support Post Direct Selection Direct 427,856.00 0.00 Implementati 2019-05-29 2019-06-03 2019-07-08 2021-07-07 reintegration of the on homeless street children through providing basic social and livelihood services MOLSA/UPSNP/UDS/DC/DE SSIE CITY/01/19 / Procurement of Services to improve the economic, Pending educational and/or social IDA / 57560 1. Safety Net Support Post Direct Selection Direct 358,573.00 0.00 Implementati 2019-05-29 2019-06-03 2019-07-08 2021-07-07 reintegration of the on homeless street children through providing basic social and livelihood services MOLSA/UPSNP/UDS/DC/HA RER CITY/01/19 / Procurement of Services to improve the economic, Pending educational and/or social IDA / 57560 1. Safety Net Support Post Direct Selection Direct 200,558.00 0.00 Implementati 2019-05-29 2019-06-03 2019-07-08 2021-07-07 reintegration of the on homeless street children through providing basic social and livelihood services MOLSA/UPSNP/UDS/DC/GA MBELLA CITY/01/19 / Procurement of Services to improve the economic, Pending educational and/or social IDA / 57560 1. Safety Net Support Post Direct Selection Direct 108,180.00 0.00 Implementati 2019-05-29 2019-06-03 2019-07-08 2021-07-07 reintegration of the on homeless street children through providing basic social and livelihood services CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Interest Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MUDH/UFSJCA/UPSNP/C- 021/17 / scoping Consultant study/Assessment on people Pending IDA / 57560 1. Safety Net Support Post Qualification Open - National 98,000.00 0.00 2017-05-15 2017-06-05 2017-07-17 2017-07-24 2017-08-07 2017-10-06 with special needs (Urban Implementation Selection destitute) and service providers in 11 Cities MUDH/UFSJCA/UPSNP/C- 022/17 / Baseline study- 3. Institutional Consultant Pending Conduct baseline community IDA / 57560 Strengthening and Project Post Qualification Open - National 50,000.00 0.00 2017-06-15 2017-07-05 2017-08-16 2017-08-23 2017-09-06 2017-11-05 Implementation report card (CRC) or Score Management Selection (CSC) among beneficiaries. Page 12 MUDH/UJCFSA/UPSNP/C- Consultant Under 023/17 / Preparation of IDA / 57560 2. Livelihood Services Post Qualification Open - National 150,000.00 0.00 2017-08-14 2017-08-29 2017-10-12 2017-11-11 2017-12-16 2018-01-30 Implementation Livelihoods guidelines Selection MUDH/UJCFSA/UPSNP/C- 3. Institutional Consultant Pending 025/2017 / Organizational IDA / 57560 Strengthening and Project Post Qualification Open - National 25,150.00 0.00 2017-12-15 2017-12-29 2018-02-13 2018-03-15 2018-04-13 2018-06-07 Implementation Capacity Assessment Management Selection MOLSA/UPSNP/C-026/2017 Consultant / Conduct need assessment Pending IDA / 57560 1. Safety Net Support Post Qualification Open - National 39,726.00 0.00 2017-12-14 2017-12-29 2018-02-12 2018-03-14 2018-04-11 2018-06-10 for direct support to link Implementation Selection with service providers MUDH/UJCFSA/UPSNP/C- 3. Institutional 24/2017 / Procurement Least Cost IDA / 57560 Strengthening and Project Prior Open - National 100,000.00 44,012.62 Signed 2017-10-20 2017-11-06 2017-12-20 2018-01-22 2018-02-06 2018-03-07 2018-04-05 2018-06-04 Audit EFY 2009/10 in 11 Selection Management UPSNP cities MUDH/UJCFSA/UPSNP/C- 028/2018 / Design, 3. Institutional Quality And Cost- Open - Under Development and Training IDA / 57560 Strengthening and Project Post 455,000.00 0.00 2018-05-21 2018-06-11 2018-07-25 2018-08-22 2018-09-21 2018-10-26 2018-11-30 2020-05-30 Based Selection International Implementation of UPSNP Management Management Information System (MIS) MUDH/UJCFSA/UPSNP/C- 30/2018 / Consultancy service to Conduct six 3. Institutional Quality And Cost- Under month community score IDA / 57560 Strengthening and Project Post Open - National 160,210.00 0.00 2018-12-21 2019-01-11 2019-02-25 2019-03-25 2019-04-24 2019-05-29 2019-07-03 2020-07-02 Based Selection Implementation card/client report card Management (every six month in three phases) in each 11 cities ET-MUDH-96023-CS-QCBS 3. Institutional Quality And Cost- Pending / Public work review IDA / 57560 Strengthening and Project Post Open - National 122,000.00 0.00 2019-02-20 2019-03-13 2019-04-26 2019-05-24 2019-06-23 2019-07-28 2019-09-01 2019-10-31 Based Selection Implementation assessment Management ET-MUDH-100231-CS- 3. Institutional Quality And Cost- Open - Under QCBS / Second Round IDA / 57560 Strengthening and Project Prior 587,000.00 0.00 2019-02-28 2019-03-21 2019-05-04 2019-06-01 2019-07-01 2019-08-05 2019-09-09 2021-12-07 Based Selection International Implementation Impact Evaluation Management ET-MUDH-100264-CS- 3. Institutional QCBS / Third (3rd) round Quality And Cost- Pending IDA / 57560 Strengthening and Project Post Open - National 98,300.00 0.00 2019-02-25 2019-03-18 2019-05-01 2019-05-29 2019-06-28 2019-08-02 2019-09-06 2019-11-05 Proxy Means tests (PMT) Based Selection Implementation Management Verification INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual A/A CITY/UJCFSA/UPSNP/IC- 01/17 / Recruitment of 3. Institutional Individual Procurement Specialist for Under IDA / 57560 Strengthening and Project Prior Consultant Open 27,847.08 0.00 2017-08-29 2017-10-02 2017-10-17 2017-11-07 2018-11-07 Addis Ababa City UJCFSA Implementation Management Selection for three year (Sept. 2017 - Sept. 2020) on contractual bases HAWASA CITY/UJCFSA/UPSNP/IC- 02/17 / Recruitment of 3. Institutional Individual Procurement Expert for Under IDA / 57560 Strengthening and Project Prior Consultant Open 23,205.60 0.00 2017-08-29 2017-09-25 2017-10-10 2017-10-24 2018-10-24 Hawasa City UPSNP for Implementation Management Selection the period of three years (Sept.2017 - Sept.2020) on contractual bases Page 13 D/DAWA CITY/UJCFSA/UPSNP/IC- 03/2017 / Recruitment of Procurement Expert for 3. Institutional Individual Under Dire Dawa City IDA / 57560 Strengthening and Project Prior Consultant Open 23,205.60 0.00 2017-08-29 2017-10-02 2017-10-17 2017-10-31 2018-10-31 Implementation Administration UPSNP for Management Selection the period three years (Sept.2017 - Sept.2020) on contractual bases. ADAMA CITY/UJCFSA/UPSNP/IC- 042017 / Recruitment of 3. Institutional Individual Procurement Experts for Under IDA / 57560 Strengthening and Project Prior Consultant Open 23,205.60 0.00 2017-08-29 2017-10-02 2017-10-17 2017-10-31 2018-10-31 Adama city UPSNP for the Implementation Management Selection period three years (Sept.2017 - Sept.2020) on contractual bases. DESSIE CITY/UJCFSA/UPSNP/IC- 05/2017 / Recruitment of 3. Institutional Individual Procurement Expert for IDA / 57560 Strengthening and Project Prior Consultant Open 23,205.60 514.97 Signed 2017-08-29 2017-10-02 2017-10-17 2017-10-31 2018-10-31 Dessie City UPSNP for the Management Selection period of three years (Sept.2017 - Sept.2020) on contractual bases. MEKELE CITY/UJCFSA/UPSNP/IC- 06/2017 / Recruitment of 3. Institutional Individual Procurement Expert for Under IDA / 57560 Strengthening and Project Prior Consultant Open 23,205.60 0.00 2017-08-29 2017-10-02 2017-10-17 2017-10-31 2018-10-31 Mekele City UPSNP for the Implementation Management Selection period of three years (Sept.2017 - Sept. 2020) on contractual bases. MUDH/UJCFSA/UPSNP/C- 027/2018 / Recruitment of 3. Institutional Individual Senior Procurement Expert Under IDA / 57560 Strengthening and Project Prior Consultant Open 22,666.00 0.00 2018-02-15 2018-04-11 2018-05-02 2018-05-25 2019-05-25 for Federal PCU on Implementation Management Selection contractual bases for 3 years MUDH/UJCFSA/UPSNP/C/D 3. Institutional Under C/029/2018 / Upgrading of IDA / 57560 Strengthening and Project Prior Direct Selection Direct 9,000.00 0.00 2018-06-18 2018-07-02 2018-07-26 2018-08-30 Implementation UPASS Software Management ET-MUDH-108352-CS-INDV / Recruitment of Procurement Specialist who 3. Institutional Individual Pending will frequently travel and IDA / 57560 Strengthening and Project Prior Consultant Open 20,100.00 0.00 2019-04-14 2019-06-02 2019-06-23 2019-07-28 2021-07-27 Implementation support 5 emerging cities Management Selection (Jigjiga, Asossa, Gambella, Semera-Logia and Harer) Page 14