Skip to Main Navigation

Kenya - Electricity Expansion Project : environmental assessment (Vol. 8) : Environmental impact assessment for the Bamburi 33/11 kV Substation in Mombasa County (English)

The objectives of the Electricity Expansion Project for Kenya are to: (a) increase access to electricity in urban, peri-urban and rural areas; and (b) improve the efficiency, reliability and quality of service to consumers, while sustaining the policy, institutional and regulatory environment needed for these results to materialize. Negative impacts include: soil erosion, contamination of soil, decreased air quality due to dust emission, solid waste, impacts on water quality and water resources, noise and vibration, visual Intrusion and aesthetic impacts, traffic congestion, accidents as a result of increased traffic, damage to roads and transport infrastructure, occupational Health and safety impacts, and impacts on public health. Mitigation measures include: during construction, where water is available, sprinkle the construction area with water to keep dust levels down; dust masks should be provided to all personnel in areas prone to dust emissions throughout the period of construction; drivers of construction vehicles must be supervised so that they do not leave vehicles idling and they limit the vehicular speeds so that dust levels are lowered; no burning of any waste materials whatsoever should be permitted within the site during construction; areas cleared of vegetation at the substation site, and where no substation structures are, shall be rehabilitated by grass to prevent soil erosion; drainages shall be constructed to control storm water; noise pollution shall be mitigated by ensuring that noisy operations are done during the day only and also by properly maintaining construction machinery; HIV/AIDS awareness campaigns shall be carried out for employees and the surrounding members of public; solid wastes generated, shall be carted away as soon as possible for appropriate disposal; and occupational safety measures shall be put in place, including provision of suitable and adequate personal protective clothing and equipment to construction employees.

Details

  • Author

    Lucy,Dennis F.

  • Document Date

    2013/11/01

  • Document Type

    Environmental Assessment

  • Report Number

    SFG1101

  • Volume No

    8

  • Total Volume(s)

    13 (See all volumes)

  • Country

    Kenya,

  • Region

    Africa,

  • Disclosure Date

    2015/05/19

  • Disclosure Status

    Disclosed

  • Doc Name

    Environmental impact assessment for the Bamburi 33/11 kV Substation in Mombasa County

  • Keywords

    flooding, population densities, no, environmental quality, reclamation, economic growth, environmental quality standards, environmental protection, carbon dioxide, environmental degradation, fossil fuels, air quality, waste management, adverse impacts, forest management, topography, carbon, environmental problems, drainage systems, cadmium, waterways, coliform bacteria, agricultural production, suspended solids, discharge, producers, resource management, drainage channels, data collection, hydrology, timber, habitats, monitoring, emissions, housing, environmental issues, environmental regulations, incentives, models, water table, coastal plain, private property, bay, sustainable development, quality, ph, public health, audits, biological diversity, toxic substances, economic activity, wildlife, oil, study area, economic benefits, ozone layer, construction, options, currents, sand, biodiversity, rainfall, drainage, land degradation, pollution, forestry, land ownership, indicators, field investigation, natural resources, cod, storm water, field investigations, bacteria, crops, efficiency, fishing, greenhouse gases, taxes, land use, resources, bod, energy consumption, equity, economic impact, beach, vegetation, studies, continuous monitoring, environmental conservation, climate change, environmental policy, shrubs, environmental management, beaches, values, civil works, electricity demand, quality standards, environmental impacts, deforestation, climate, demand, forests, sustainable use, solid wastes, endangered species, land area, pollutants, electricity generation, agriculture, ammonia, property, logging, decision making, environmental performance, environment, environmental research, aesthetics, weather patterns, waste disposal, tax revenue, administration, fisheries, economic development, trade, agricultural purposes, erosion, land, lakes, dissolved solids, analysis, drinking water, coast, observations, mitigation, environmental education, public participation, conservation, farms, indigenous peoples, ecology, environmental impact statement, environmental management activities, water pollution, revenue, soils, restoration, risk management, recycling, arsenic, profits, emission standards, environmental, industrial use, public good, wetlands, implementation, hazardous wastes, economic conditions, economies, river

Downloads

COMPLETE REPORT

Official version of document (may contain signatures, etc)

  • Official PDF
  • TXT*
  • Total Downloads** :
  • Download Stats
  • *The text version is uncorrected OCR text and is included solely to benefit users with slow connectivity.

Citation

Lucy,Dennis F.

Kenya - Electricity Expansion Project : environmental assessment (Vol. 8) : Environmental impact assessment for the Bamburi 33/11 kV Substation in Mombasa County (English). Washington, D.C. : World Bank Group. http://documents.worldbank.org/curated/en/162331468254078439/Environmental-impact-assessment-for-the-Bamburi-33-11-kV-Substation-in-Mombasa-County