Details
-
Author
-
Document Date
2019/12/05
-
Document Type
Implementation Status and Results Report
-
Report Number
ISR38033
-
Volume No
1
-
Total Volume(s)
1
-
Country
-
Region
-
Disclosure Date
2019/12/05
-
Disclosure Status
Disclosed
-
Doc Name
Disclosable Version of the ISR - BD Chittagong Water Supply Improvement and Sanitation Project - P103999 - Sequence No : 18
-
Keywords
access to safe water; people in urban area; water supply improvement; preparatory work; water treatment plant; number of water; Investment Project Financing; capacity development activity; permit water; standard operating procedure; investment planning; household water; risk category; distribution network; operational structure; operation risk; transmission line; bill collection; other water; physical work; water global; household connection; project intervention; water utilities; water utility; sustainable access; improved sanitation; drainage infrastructure; operational management; water sale; transmission main
- See More
Downloads
COMPLETE REPORT
Official version of document (may contain signatures, etc)
- Official PDF
- TXT*
- Total Downloads** :
- Download Stats
-
*The text version is uncorrected OCR text and is included solely to benefit users with slow connectivity.
Citation
Ahamed,Arif
Disclosable Version of the ISR - BD Chittagong Water Supply Improvement and Sanitation Project - P103999 - Sequence No : 18 (English). Washington, D.C. : World Bank Group. http://documents.worldbank.org/curated/en/453031575569811022/Disclosable-Version-of-the-ISR-BD-Chittagong-Water-Supply-Improvement-and-Sanitation-Project-P103999-Sequence-No-18