Skip to Main Navigation

Nigeria - Electricity and Gas Improvement Project : environmental assessment (Vol. 2) : Environmental and social management plan for the rehabilitation/reinforcement of Sagamu (Ogun state), Awka (Anambra state), Yandev (Benue state), and Gasau (Zamfara state) 132/33kV transmission sub-stations (English)

The development objectives of the Electricity and Gas Improvement Project for Nigeria are to: (i) improve the availability and reliability of gas supply to increase power generation in existing public sector power plants; and (ii) improve the power network’s capacity and efficiency to transmit and distribute quality electricity to the consumers. Some of the negative impacts and mitigation measures include: (1) identify and confirm suitable sites for the construction camps, if any, and storage areas for materials; (2) identify disposal sites for construction waste approved by the local authority; (3) identify the excavation depth and width according to the drawing design; (4) implement preventive maintenance program for vehicles and equipment working on site and promptly repair vehicles with visible exhaust fume; (5) provide ear muffs to construction workers usually located near noisy machines; (6) the contractor should make health and safety facilities available in the project site; and (7) prevent storage of construction materials, equipment, and machineries on traffic lanes.

Details

  • Author

    Medani,Ogochukwu Joy

  • Document Date

    2016/01/01

  • Document Type

    Environmental Assessment

  • Report Number

    SFG1848

  • Volume No

    2

  • Total Volume(s)

    3

  • Country

    Nigeria,

  • Region

    Africa,

  • Disclosure Date

    2016/03/01

  • Disclosure Status

    Disclosed

  • Doc Name

    Environmental and social management plan for the rehabilitation/reinforcement of Sagamu (Ogun state), Awka (Anambra state), Yandev (Benue state), and Gasau (Zamfara state) 132/33kV transmission sub-stations

  • Keywords

    federal law;Environmental and Social Impact Assessment;Environmental and Social Management Plan;Environmental Management and Monitoring Plan;land use act;social and economic development;health and safety issue;disposal of construction waste;electric and magnetic field;Environmental and Social Safeguard;community health and safety;Occupational health and safety;construction and operation;satellite image;negative environmental impact;host country regulation;disposal of waste;population and environment;international good practice;soak away pit;demand for electricity;asbestos-containing materials;replacement of equipment;natural disaster risk;quantity of waste;physical cultural resources;supply and installation;corporate social responsibility;law and regulation;Solid Waste Management;probability of occurrence;hand dug well;capacity of infrastructure;access to transmission;number of jobs;economic impact assessment;local government area;impact evaluation methodology;socio economic impact;court of law;environmental resource;Environmental Resources;mechanical equipment;building material;mitigation measure;national regulation;financing institution;construction site;

Downloads

COMPLETE REPORT

Official version of document (may contain signatures, etc)

Citation

Medani,Ogochukwu Joy

Nigeria - Electricity and Gas Improvement Project : environmental assessment (Vol. 2) : Environmental and social management plan for the rehabilitation/reinforcement of Sagamu (Ogun state), Awka (Anambra state), Yandev (Benue state), and Gasau (Zamfara state) 132/33kV transmission sub-stations (English). Washington, D.C. : World Bank Group. http://documents.worldbank.org/curated/en/742611468122975436/Environmental-and-social-management-plan-for-the-rehabilitation-reinforcement-of-Sagamu-Ogun-state-Awka-Anambra-state-Yandev-Benue-state-and-Gasau-Zamfara-state-132-33kV-transmission-sub-stations