Nicaragua - Hurricane Felix Emergency Recovery Project (English)

Ratings for the Hurricane Felix Emergency Recovery Project for Nicaragua were as follows: outcomes were unsatisfactory, the risk to development outcome was high, the Bank performance was moderately unsatisfactory, and the Borrower performance was unsatisfactory. Some lessons learned included: implementation arrangements for emergency operations should be straightforward and pragmatic, even if attempting to be responsive to national decentralization...
See More

DETAILS

DOWNLOADS

COMPLETE REPORT

Official version of document (may contain signatures, etc)


Citation

Nicaragua - Hurricane Felix Emergency Recovery Project (English). Washington, D.C. : World Bank Group. http://documents.worldbank.org/curated/en/811771468191065161

This document is being processed or is not available.