China - Energy Efficiency Financing Second Project (English)

Ratings of Energy Efficiency Financing Second Project for China were as follows: outcomes were moderately unsatisfactory, risk to development outcome was substantial, Bank performance was moderately satisfactory, and Borrower performance was moderately unsatisfactory. Some of the lessons learned included: (I) Participating Financial Intermediary's (PFI) continuing commitment and appropriate internal organization are essential factors in the success...