This is the sixth progress report to the Board of Executive Directors on implementation of the management action plan (MAP) in response to the inspection panel investigation report for Private Power Generation (Bujagali) Project for Uganda. On March 7, 2007, the inspection panel registered a request for inspection from the Ugandan national association of professional environmentalists (NAPE) and others alleging various environmental, social, and cultural harms as a result of the project. Management responded to the request on April 5, 2007. Following Board approval of the panel’s recommendation on May 18, 2007, the inspection panel undertook to investigate the allegations. The inspection panel submitted its investigation report to the Board on August 29, 2008. On November 7, 2008, management submitted its report and recommendation, along with a detailed MAP, which included strengthening institutional capacity of the various authorities responsible for the project; social assessment and mitigation measures, including updating of the socio-economic baseline, follow up on programs to address vulnerable groups, and sharing of project benefits; measures to address physical cultural resources, including chance find procedures; and environmental assessment and mitigation measures.
Details
-
Document Date
2017/02/21
-
Document Type
Investigation Report
-
Report Number
114774
-
Volume No
1
-
Total Volume(s)
1
-
Country
-
Region
-
Disclosure Date
2017/05/03
-
Disclosure Status
Disclosed
-
Doc Name
Uganda - Private Power Generation (Bujagali) Project : Sixth Progress Report on the Implementation of Management's Action Plan in Response to the Inspection Panel Investigation Report
-
Keywords
sustainable management;Environmental and Social Impact Assessment;provision of water supply service;double circuit line;transmission line;land title;Environmental and Social Safeguard;number of connections;power generation capacity;household survey data;Access to Electricity;socio-economic survey;earth fill dam;physical cultural resources;confirmation of fund;reallocation of fund;rural electrification program;compensation for loss;electricity distribution system;class action suit;delivery of service;vulnerable group;hydropower plant;Environmental Assessment;mitigation measure;
- See More
Downloads
COMPLETE REPORT
Official version of document (may contain signatures, etc)
- DOCX
- Official PDF
- TXT*
- Total Downloads** :
- Download Stats
-
*The text version is uncorrected OCR text and is included solely to benefit users with slow connectivity.
Citation
Uganda - Private Power Generation (Bujagali) Project : Sixth Progress Report on the Implementation of Management's Action Plan in Response to the Inspection Panel Investigation Report (English). Washington, D.C. : World Bank Group. http://documents.worldbank.org/curated/en/905131493842147708/Uganda-Private-Power-Generation-Bujagali-Project-Sixth-Progress-Report-on-the-Implementation-of-Managements-Action-Plan-in-Response-to-the-Inspection-Panel-Investigation-Report