Thailand - Third Yanhee Project (English)

The proposed project would assist in financing the construction program for the period 1965-1968 which includes the installation of Units 3 and 4 at Bhumibol dam, construction of the penstocks for future Units 5 and 6, extension of 230 kv substations in Bangkok, extension of new 115 kv and 69 kv transmission lines and the provision of engineering services.

Details

  • Document Date

    1965/03/31

  • Document Type

    Staff Appraisal Report

  • Report Number

    TO458

  • Volume No

    1

  • Total Volume(s)

    1

  • Country

    Thailand,

  • Region

    East Asia and Pacific,

  • Disclosure Date

    2010/06/18

  • Disclosure Status

    Disclosed

  • Doc Name

    Thailand - Third Yanhee Project

  • Keywords

    long-term debt;Fixed Assets;internal cash generation;annual average growth rate;national power authority;kv transmission line;Valuation of fixed asset;foreign exchange;transmission system;government equity;total debt service;sources of fund;local currency loan;annual debt service;debt limitation covenant;financing plan;government loan;Financing plans;foreign exchange debt;foreign exchange loss;transfer of property;debt service payment;hydro generating capacity;foreign exchange expenditures;hydro power capacity;responsibility for water;high growth rate;cost equipment;cost of equipment;earned surplus;distribution facility;income statement;cash balance;capital expenditure;financial aspect;property transfer;grace period;fuel cost;load growth;power industry;average revenue;earlier investment;national energy;rural market;energy forecast;variable cost;transmission facility;financial situation;bulk power;welfare fund;construction work;discount value;government contribution;local costs;financial requirement;unit price;Cash flow;conservative approach;project costing;bulk rate;import duty;fuel purchase;working capital;net profit;income deduction;interest charge;deferred credit;account payable;deferred charges;capitalized interest;accumulated depreciation;Exchange Rates;account receivable;specific commitment;international bidding;long-term borrowing;high debt;Electric Power;energy sale;voltage transmission;power transformers;currency component;delivery time;kv line;construction expenditures;kv substation;load forecast;power planning;primary market;construction schedule;small industry;credit availability;peak load;Power Market;future cash;retail marketing;formal transfer;power supply;government fund;flood control;energy production;cost of energy production;suburban area;financial analysis;power investment;small loan;steam power;diesel power;financial capability;voltage line;appraisal mission;loan negotiation;government authority;cost decrease;promotional effort;Capital Investments;thermal generation;energy source;transmission distance;load center;hydro installation;hydro capacity;hydro energy;hydro source;capacity requirements;

Downloads

COMPLETE REPORT

Official version of document (may contain signatures, etc)

  • Official PDF
  • TXT*
  • Total Downloads** :
  • Download Stats
  • *The text version is uncorrected OCR text and is included solely to benefit users with slow connectivity.

Citation

Thailand - Third Yanhee Project (English). Technical operations projects series ; no. TO 458 Washington, D.C. : World Bank Group. http://documents.worldbank.org/curated/en/961651468118475069/Thailand-Third-Yanhee-Project