Ratings of Ibadan Urban Flood Management Project for Nigeria were as follows: outcome was moderately satisfactory, Bank performance was moderately satisfactory, and monitoring and evaluation quality was modest. Some of the lessons learned include: : (i) Bank support in these types of projects and environments should be adequate, consistent, technical, and diligent in enhancing the client’s capacity, deploying all available tools, resolving issues...