Ratings for the Flood and Landslide Emergency Recovery Project for Myanmar were as follows: outcome was unsatisfactory, Bank performance was moderately satisfactory, and monitoring and evaluation (M and E) quality was modest. Some lessons learned included: the immediate response mechanism (IRM) proved to be too complex to implement effectively, particularly in a fragility, conflict, and violence (FCV) context. The scope of emergency activities must...
Exibir mais
DETALHES
-
2023/06/29
-
Conclusão da Implementação e Relatórios sobre Resultados
-
ICR6073
-
1
-
2023/07/05
-
Disclosed
-
Myanmar - Flood and Landslide Emergency Recovery Project
DOWNLOADS
COMPLETAR RELATÓRIO
Versão oficial do documento (pode conter assinaturas, etc.)
-
Total Downloads** : 191
*A versão do texto é um OCR incorreto e está incluído unicamente em benefício de usuários com conectividade lenta.