Ratings for the Second Phase of the Recurrent Cost and Reform Financing (RCRF II) Project for Somalia were as follows: outcome was highly satisfactory, Bank performance was satisfactory, and monitoring and evaluation (M and E) quality was substantial. Some lessons learned included: engaging the government fully in project design reaped benefits for the project. Supporting core human resource management (HRM) and public financial management (PFM) systems...
Exibir mais
DETALHES
-
2023/02/28
-
Conclusão da Implementação e Relatórios sobre Resultados
-
ICR5986
-
1
-
2023/03/08
-
Disclosed
-
Somalia - Second Phase of the Recurrent Cost and Reform Financing Project
DOWNLOADS
COMPLETAR RELATÓRIO
Versão oficial do documento (pode conter assinaturas, etc.)
-
Total Downloads** : 171
*A versão do texto é um OCR incorreto e está incluído unicamente em benefício de usuários com conectividade lenta.