The objective of the Electricity Network Reinforcement and Expansion Project are to improve reliability, and increase access to electricity services in Ethiopia. Some of the negative impacts and mitigation measures include: (1) the project shall control the speed of construction vehicles, conduct regular vehicle maintenance, watering of access roads during the dry season to suppress dusts, and prohibit idling of vehicles on site to minimize the generation...
Exibir mais
Document also available in :
Inglês
DETALHES
-
2022/05/31
-
Avaliação Ambiental
-
SFG3876
-
2
-
1
-
2022/08/02
-
Disclosed
-
Environmental and Social Impact Assessment for Lot-I : Metu-Masha 230 KV Single Circuit Transmission Line
DOWNLOADS
COMPLETAR RELATÓRIO
Versão oficial do documento (pode conter assinaturas, etc.)
-
Total Downloads** : 2654