Ratings of Western Indonesia National Roads Improvement Project for Indonesia were as follows: outcome was moderately satisfactory, Bank performance was moderately satisfactory, and monitoring and evaluation quality was substantial. Some of the lessons learned include: (i) Early inter-agency coordination and advance procurement of implementation support consulting services are key factors for success in Indonesia; (ii) Adequate engineering designs...