Tanzania - Backbone Transmission Investment Project (Inglês)

The Backbone Transmission Investment Project for Tanzania seeks a restructuring in this report. This Restructuring Paper proposes to extend the closing date of the Backbone Transmission Investment Project (BTIP), by 21 months. The project implementation was delayed two years after it became effective, principally due to slow procurement of the main contract. The project design required joint clearance of the main procurement contract by the lenders...