Cote d'Ivoire - Abidjan Environmental Protection Project (Inglês)

The outcome of the Abidjan Environmental Protection Project for Cote d'Ivoire was satisfactory. The project achieved most of its objectives, institutional development was partially achieved, sustainability is likely, and the performance of both the Bank and Borrower was satisfactory. Several lessons can be learned from this project. First, establishing surcharges on water tariffs for further remittance to other entities, particularly for financing operating expenditures, is risky. Second, mitigation plans are essential. An environmental protection project may generate negative side effects. The impact of construction works in urban areas should not be overlooked. Third, contract packaging should not aim exclusively at minimizing the number of contracts to simplify procurement, as large and heterogeneous contracts may have their shortcomings in terms of contract management. Finally, time-based conditionalities should be attached to a dated deadline.

Detalhes

  • Data do documento

    1996/06/17

  • TIpo de documento

    Conclusão da Implementação e Relatórios sobre Resultados

  • No. do relatório

    15736

  • Nº do volume

    1

  • Total Volume(s)

    1

  • País

    Costa do Marfim,

  • Região

    África,

  • Data de divulgação

    2010/06/18

  • Disclosure Status

    Disclosed

  • Nome do documento

    Cote d'Ivoire - Abidjan Environmental Protection Project

  • Palavras-chave

    Present Value of Benefits;adjustment of contract price;final disposal of waste;sewerage and drainage;net present value;lease contract;ocean outfall;assessment of outcome;industrial waste water;terms of contract;waste water disposal;cost recovery policy;cost recovery mechanism;lack of commitment;accumulation of arrears;rural water service;flow of fund;Urban Water Supply;private water supply;maintenance of facilities;environment and sanitation;cost of work;industrial water consumption;assignment of responsibility;high population density;water concession contract;water supply sector;water supply company;cumulative loan;allocation of water;private sector management;pollution monitoring;sewerage system;water user;financial covenant;discount rate;financial autonomy;debt service;pumping station;financial relations;environmental regulation;private operator;water bill;physical work;residential area;physical achievement;sea water;construction work;environmental benefit;sewerage network;environmental specialist;Exchange Rates;baseline survey;contractual framework;Project Monitoring;contract management;popular participation;sanitation system;industrial zone;global environmental;On-Site Sanitation;sectoral adjustment;industrial effluent;finance objective;financial restructuring;operational responsibility;operational sustainability;procurement activities;sand trap;organizational change;environmental objective;collect revenue;project risk;national strategy;organic pollution;incremental expenditure;industrial units;project operation;contract packaging;sewerage facilities;economic depression;mitigation plans;bank assistance;minor damage;water tariff;ocean water;property value;administrative delays;monitoring program;public consultation;low-income area;government financing;sanitation tax;drainage system;organic waste;regulatory responsibility;study including;domestic waste;pollution load;marine water;regulatory experience;beneficiary participation;environmental environmental;work regulation;permit system;water quality;financial sustainability;sanitation facility;operational plan;macro policy;macro policies;gender issue;social objective;institutional framework;Water Services;coastal pollution;physical facility;counterpart fund;coastal line;city limits;environmental consultant;liquid waste;entire portfolio;competitive bidding;coastal ocean;work contracts;budget fund;economic recession;effective demand;financial indicator;investment program;financial statement;house connection;Fixed Assets;physical implementation;adjustment effort;Sanitation Services;performance rating;control laboratory;financial resource;land development;confined water;squatter settlement;calculation period;commercial company;financial analyst;public water;public finance;treatment plant;financial consultant;land price;Marine Pollution;inflation rate;construction period;construction contractor;external assistance;Sanitary Regulations;participatory approach;ministerial department;external expertise;project costing;financial proposal;positive outcome;lagoon fishery;procurement process;maintenance expenditure;water rate;Property tax;contractual arrangement;procurement delay;main contractor;negative growth;domestic arrears;tender process;chemical parameters;sediment samples;industrial plant;bacterial contamination;draft regulation;

Downloads

COMPLETAR RELATÓRIO

Versão oficial do documento (pode conter assinaturas, etc.)

  • PDF oficial
  • TXT*
  • Total Downloads** :
  • Download Stats
  • *A versão do texto é um OCR incorreto e está incluído unicamente em benefício de usuários com conectividade lenta.