Skip to Main Navigation

India - Koyna Hydroelectric Project (Inglês)

This report covers an appraisal of the first stage of the Koyna Hydro-Electric Power project for India which will include; a transmission line to Bombay, and a transmission line south of the project to serve a number of small towns, villages, and their small industries. Stage I, now under construction, will have an installed capacity of 240 MW; Stage II will provide an additional 240 mw, and water storage for irrigation; Stage III will utilize the tailrace waters of the Stage II power plant and irrigation water, and it will add an additional 90 mw. The continually growing demand for power requires the provision of new generating capacity of the magnitude of Koyna and the development of this project is the most economical method of providing the power.

Detalhes

  • Data do documento

    1959/03/31

  • TIpo de documento

    Relatório sobre Avaliação do Pessoal

  • No. do relatório

    TO182

  • Nº do volume

    1

  • Total Volume(s)

    1

  • País

    Índia,

  • Região

    Sul da Ásia,

  • Data de divulgação

    2010/06/18

  • Disclosure Status

    Disclosed

  • Nome do documento

    India - Koyna Hydroelectric Project

  • Palavras-chave

    construction work in progress;payment of income tax;interest during construction;foreign exchange requirement;underground power plant;total debt service;transmission line;electric utility industry;supply of electricity;construction cost estimate;availability of water;transmission and distribution;quantity of water;rate of growth;thermal power plant;demand for power;construction and operation;local self government;ton of coal;thermal plant;civil works;generating capacity;interest charge;installed capacity;firm capacity;cubic feet;water storage;irrigation water;utility practice;fertilizer plant;dam foundations;river bed;energy sale;annual production;annual saving;small industry;transmission system;net profit;corporate body;retained earnings;financial aspect;Capital Investments;important policy;foreign currency;power production;initial capital;perpetual succession;common seal;loan finance;initial loss;electrical engineer;financial matter;previous paragraph;power rate;accumulated depreciation;export industry;heavy rainfall;chemical industry;oil refinery;lightning arresters;sluice gate;waste product;representative body;physical changes;domestic coal;alternative investment;hydro installation;railway system;hydroelectric facility;main river;foreign expenditure;international bidding;financial result;construction period;sinking fund;load forecast;agricultural land;financial statement;heat rate;Hydro Power;contingency allowance;local expenditure;annual consumption;textile mill;coverage ratio;integrated system;dry year;construction boards;thermal capacity;retail business;field study;information supply;hydroelectric development;consulting engineer;net investment;power system;Hydroelectric Power;power cost;regulatory features;indian rupee;demand forecast;latest forecast;water right;irrigation purpose;voltage line;butterfly valves;long tunnel;fuel cost;foreign service;river flow;construction schedule;transmission tower;long-term loan;local funds;load growth;reasonable contribution;financial analysis;capital structure;Power Generation;capital expenditure;catchment area;dam site;hydrological data;geological survey;

Downloads

COMPLETAR RELATÓRIO

Versão oficial do documento (pode conter assinaturas, etc.)

  • PDF oficial
  • TXT*
  • Total Downloads** :
  • Download Stats
  • *A versão do texto é um OCR incorreto e está incluído unicamente em benefício de usuários com conectividade lenta.