Skip to Main Navigation

Malaysia - Fifth Power Project (Inglês)

The project consists of the third stage at Tuanku Ja'afar (Port Dickson) Thermal Station and transmission lines and associated substations to deliver the power to the load centers. The third stages at Port Dickson comprises three new units (Units 5 to 7) each of 120 MW and will bring the station to its final total capacity of 600 MW. The civil works for all three units would be carried out together and two of the three 120 MW units (Units 5 and 6) would be in operation in 1974 to meet the conservatively estimated increase in power demand by that time. The third unit would be installed within two years thereafter to meet growth in power demand as it develops. NEB intends to order all three units at once, retaining the option to cancel the third unit should future demand projections show that it will not be needed as soon as presently planned. A new order would then be placed for a third unit to be installed in time to meet the revised load forecast.

Detalhes

  • Data do documento

    1970/06/30

  • TIpo de documento

    Memorando e recomendação do Presidente

  • No. do relatório

    P848

  • Nº do volume

    1

  • Total Volume(s)

    1

  • País

    Malásia,

  • Região

    Leste Asiático e Pacífico,

  • Data de divulgação

    2010/06/24

  • Disclosure Status

    Disclosed

  • Nome do documento

    Malaysia - Fifth Power Project

  • Palavras-chave

    average rate of return;expansion of transmission;transmission line;foreign exchange;internal cash generation;accelerated economic growth;per capita gnp;amount of loan;degree of autonomy;debt service payment;power system development;export of goods;total debt service;civil works;local currency expenditure;consumer price index;external public debt;load center;fixed asset;Fixed Assets;Electric Power;project finance;retail trade;land settlement;market price;bank's guidelines;private investment;external borrowing;debt-service ratio;public capital;internal resources;increased investment;merchandise import;commercial bank;federal government;public authority;cash reserve;financial gap;consulting service;Consulting services;Financing plans;load forecast;future demand;bulk power;auxiliary equipment;generating plant;annual tax;construction cost;capital requirement;construction period;international tender;water control;reticulation system;equipment specification;long-term contract;financial controller;hydroelectric scheme;diesel plant;hydroelectric plant;installed capacity;financial rate;urban income;increasing unemployment;oil palm;managerial capacity;tin mine;import substitution;

Downloads

COMPLETAR RELATÓRIO

Versão oficial do documento (pode conter assinaturas, etc.)

  • PDF oficial
  • TXT*
  • Total Downloads** :
  • Download Stats
  • *A versão do texto é um OCR incorreto e está incluído unicamente em benefício de usuários com conectividade lenta.