Skip to Main Navigation

Botswana - Morupule B Generation and Transmission Project : resettlement plan (Vol. 2) : Draft resettlement policy framework (Inglês)

The overall objectives of the Botswana Morupule B Generation and Transmission Project are to: (i) secure reliable and affordable supply of electricity as soon as possible; and (ii) to build institutional capacity for sustainable development of the energy sector. Negative measures include: valuation of assets, land, reconstruction of buildings, and compensation for crop loss. Mitigation measures include: compensation to the family will consist of an equivalent plot of land located approximately five-six km from Palapye in a similar setting of undeveloped land. The location should allow them to continue present livelihood activities which include: collection of firewood, mopane worms and other fruits for sale in Palapye, and growing of some crops for their own consumption. Compensation will also consist of assistance by Botswana Power Corporation (BPC) with the process of resettlement, including moving the family's belongings and assisting with reconstruction of housing, structures, and fencing. Subject to the family's agreement, BPC may also assist by providing materials and labor to improve the standard of the buildings with more durable materials. BPC will also provide compensation equivalent to this year's foregone crop opportunities as the family did not plant their usual subsistence crops, aware that they will be moved.

Detalhes

  • Autor

    Botswana Power Corporation

  • Data do documento

    2009/05/19

  • TIpo de documento

    Plano de reassentamento

  • No. do relatório

    RP812

  • Nº do volume

    2

  • Total Volume(s)

    2

  • País

    Botsuana,

  • Região

    África,

  • Data de divulgação

    2010/07/01

  • Disclosure Status

    Disclosed

  • Nome do documento

    Draft resettlement policy framework

  • Palavras-chave

    replacement cost;market value of land;Land Acquisition and Resettlement;compensation in cash;compensation for loss;acquisition of asset;adverse social impact;customary land right;transmission line;replacement land;grievance redress mechanism;customary land tenure;parcel of land;possession of land;security of tenure;court of law;dispute resolution mechanism;valuation of asset;loss of asset;water supply component;loss of livelihood;acquisition of land;loss of land;access to land;public information dissemination;land use planning;residence or habitat;standard of living;allocation of resource;land tenure system;project affected persons;place of work;compensation for land;cost of transport;Fixed Assets;power station;involuntary resettlement;external monitoring;transfer tax;resettlement activities;arable land;agricultural land;field investigation;cash compensation;kv line;displaced people;Social Assessment;resettlement implementation;transfer cost;baseline information;fruit tree;cultivated area;socioeconomic survey;grazing land;resettlement area;transition period;grievance procedure;resettlement impacts;affected households;salvage material;legal framework;Natural Resources;resettlement assistance;building material;business income;resettlement plan;agricultural field;community meetings;commercial land;baseline survey;residential structures;vegetable garden;site development;baseline data;lease holder;social infrastructure;market area;district officials;governance levels;eligible applicant;employment assistance;tree owner;internal monitoring;public consultation;agricultural laborer;compensation rate;monitoring process;project impact;construction work;land cover;flat topography;income substitution;relocation support;land usage;commercial site;legal provision;Population Displacement;customary right;living standard;hold land;emergency sanitation;residential land;resettlement sites;mutual agreement;common resources;law applicable;adequate compensation;high court;applicable law;industrial land;productive potential;improved public;infrastructure facility;market cost;construction site;land allocation;customary use;land register;asset inventory;legal recourse;electrical reticulation;affordable supply;adequate arrangement;compensation provision;Energy Sector;transmission system;kv substation;fiber optic;resettlement cost;water well;budgetary provision;field survey;displaced person;fuel wood;institutional responsibilities;stock water;community participation;lost land;unforeseen circumstance;social issue;grievance mechanism;institutional requirements;adequate provision;project costing;

Downloads

COMPLETAR RELATÓRIO

Versão oficial do documento (pode conter assinaturas, etc.)

  • PDF oficial
  • TXT*
  • Total Downloads** :
  • Download Stats
  • *A versão do texto é um OCR incorreto e está incluído unicamente em benefício de usuários com conectividade lenta.