Skip to Main Navigation

Iraq - Emergency Electricity Reconstruction Project (Inglês)

Ratings for the Emergency Electricity Reconstruction Project for Iraq were as follows: outcomes were unsatisfactory, risk to development outcome was high, Bank performance was unsatisfactory, and Borrower performance was moderately unsatisfactory. Some lessons learned included: large infrastructure projects in fragile state environments may often require going for simpler new-build (green-fields) projects than rehabilitation or partial reconstruction works. Good technical studies can reduce risks for the bidders potentially leading to greater participation as well as lower costs. Fragile and conflict countries usually have significant capacity constraints as well as overwhelming demands on the government, including fiscal pressures, conflict concerns, and political stability concerns. These capacity constraints can be addressed by greater Bank engagement in the procurement process and project implementation through handholding, supported by appropriate training of the project management team (PMT) and hiring consultants. Regular communications and meetings are essential to ensure that issues affecting progress are quickly identified and resolved. A turnkey contract may have shifted many of the project risks to the contractor, possibly resulting in higher price discovery but a higher probability of project completion. The use of special commitments from the World Bank to provide comfort to the contractor should incorporate provisions for withdrawal of the World Bank from the project in face of visible indications of implementation failure. In case of projects in conflict countries, a separate allocation should be made for security costs for contractors as well as consultants. Ex ante arrangements for security may relieve bidder anxiety and foster greater bidder participation.

Detalhes

  • Data do documento

    2016/05/29

  • TIpo de documento

    Conclusão da Implementação e Relatórios sobre Resultados

  • No. do relatório

    ICR3577

  • Nº do volume

    1

  • Total Volume(s)

    1

  • País

    Iraque,

  • Região

    Oriente Médio e Norte da África,

  • Data de divulgação

    2016/06/08

  • Disclosure Status

    Disclosed

  • Nome do documento

    Iraq - Emergency Electricity Reconstruction Project

  • Palavras-chave

    Risks and Mitigation Measures;Environment and Social Management Plan;Oil for Food Program;environmental and social management;legal and regulatory framework;power station;Cost of Doing Business;Environmental and Social Safeguard;ip disbursements archived;allocation of counterpart fund;transmission and distribution network;economic and financial analysis;economic and sector work;power system planning;intermediate outcome;supply of good;fragile and conflict;reallocation of fund;quality at entry;supply and installation;quality of supervision;heavy fuel oil;availability of fund;power generation capacity;power and water;Oil & Gas;Environmental Management Plan;reconstruction and rehabilitation;outputs by components;operations and maintenance;power generation equipment;fuel oil tanks;environment impact assessment;issue of security;human development indicator;per capita income;lack of ownership;exchange rate variation;defects liability period;validity of bids;supply of spare;Oil and Gas;Access to Electricity;reliability of supply;supply of materials;consumers of electricity;per capita consumption;expansion of transmission;electricity sector;power supply;contract management;fuel supply;emergency electricity;specific capacity;power utility;power utilities;general management;local capacity;load shedding;main contractor;generating capacity;Gas Turbine;budgetary allocation;advance payment;Advisory services;disbursement profile;civil works;base load;security environment;supply gap;security situation;high security;bureaucratic delay;qualified bidder;peak demand;outcome indicator;bureaucratic procedure;price adjustment;additional expense;contract design;result indicator;Technical Training;supervision coordination;scarce resource;budgetary financing;waste heat;electricity price;management risk;contract amount;procurement review;noise measurement;economic investment;financial viability;installation work;effective participation;funding requirements;investment contract;consulting service;local bank;cycle plant;short-term consulting;gas field;contract agreement;Financing plans;security cost;production cost;project risk;international market;suitable mitigation;donor funding;sustainable operation;contract structure;future price;fuel availability;security arrangement;official action;technological development;turnkey contract;bid validity;inherent risk;reverse engineering;average cost;international guidelines;budget allocation;legal opinion;Conflict Prevention;conflict zones;commercial establishments;indirect beneficiary;external partner;direct beneficiaries;power shortage;institution building;results framework;primary author;safeguard approach;management indicator;operations management;private investment;electricity policy;investment climate;basic infrastructure;donor support;operational function;commercial operation;critical infrastructure;national grid;short period;technical expertise;infrastructure reconstruction;consulting contract;generation facilities;project delays;increased security;electrical system;Gas Pipeline;fuel tank;government bureaucracy;refuse collection;power outage;management capacity;political instability;oil reserve;grid electricity;generation plant;Exchange Rates;iraqi dinar;fuel type;fuel infrastructure;essential services;electricity system;transmission line;security concern;gas flare;visa requirements;local contractor;variation order;independent audit;overseas training;project costing;construction supervision;measuring instrument;alternative financing;grant funds;Consulting services;agreed recommendation;expansion plan;consultancy activities;

Downloads

COMPLETAR RELATÓRIO

Versão oficial do documento (pode conter assinaturas, etc.)

  • PDF oficial
  • TXT*
  • Total Downloads** :
  • Download Stats
  • *A versão do texto é um OCR incorreto e está incluído unicamente em benefício de usuários com conectividade lenta.